Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

2018 International Conference on Smart Grid and Clean Energy Technologies

Assessment on Various Allocations of Energy Storages Systems on Radial


Distribution Network for Maximum PV Systems Penetration

Jimmy Hee Chin Yong1, Jianhui Wong1, Yun Seng Lim1, and Jun Huat Tang2
1
Faculty of Engineering Science, Universiti Tunku Abdul Rahman, Selangor, Malaysia
2
TNB Research Sdn. Bhd, Selangor, Malaysia
e-mail: jimmyhee@1utar.my; wongjh@utar.edu.my; yslim@utar.edu.my; tangjunhuat@tnbr.com.my

Abstract—The intermittent nature of renewable energy sources, point of common coupling by reducing the quantity of
voltage variation and voltage fluctuation can be noticed when energy exported from the feeder [5]. A planning framework
large amount of renewable energy (RE) sources are connected has been proposed to optimize the minimum storage capacity
on the distribution network, this is even worst during low load at multiple locations in the 33 kV UK distribution network in
condition. Energy storage system is a possible solution, order to reduce the curtailment from renewable distribution
particularly on solving power quality issues caused by large generation [6]. These two studies show the promising result
penetration of grid-connected renewable energy sources. however the case studies are carried out at the 11 kV
However, improper placement of the energy storage system network.
can lead to unsatisfactory mitigation of power quality issues. In
There are also case studies carry out at the low voltage
addition, poor sizing of the system can cause the energy storage
(LV) network. Many reseach projects have proposed to
system to be very costly. In this study, a typical Malaysian
Medium Voltage (MV) distribution network is modeled using
utilise distributed energy storage to overcome the voltage
Digsilent PowerFactory to perform an investigation on the rise issues caused by high penetration of renewable energy
voltage impacts of various allocation of energy storage system [7]-[9]. Nevertheless, there are also research projects
and photovoltaic systems along the distribution feeder. It is proposed to use fuzzy control algorithm in ESS to overcome
noticed that the voltage impact is significant for high voltage unbalance factor caused by single-phase PV systems
penetration of PV system power output at the feeder end as on a small section of distribution network rated at 400 V
compared to the same capacity connected at feeder front. The [10]-[12]. However, these models did not evaluate and study
investigation also shows that energy storage systems connected the effectiveness of multiple ESS on a greater area of
along the location on feeder end can regulate the feeder distribution networks.
voltages. It is essential to develop an effective an innovative
coordination control for the operation multiple units of ESS
Keywords-coordination; digsilent powerfactory; energy on real distribution network. However, assessment of the
storage system; power quality available network has to be carried out before carry out any
control algorithm for the network. This paper presents and
I. INTRODUCTION discusses on the investigation of voltage impact of high PV
Malaysia has committed to reduce its GHGs emission penetration along the feeder with various locations and the
intensity of GDP by 40% by year 2020 [1]. In order to impacts of energy storage system connected at various point
achieve this, the Malaysian government has taken various along the feeder to regulate the network voltage.
measures such as promoting the utilisation of green energy, II. METHODOLOGY
provide tax exemptions and incentives to enhance green
growth in the country. However, the nature of renewable A. Modelling of Malaysian Medium Voltage (MV)
energy (RE) sources are intermittent and as such, many Distribution Network
studies have been performed to investigate and assess the
technical impacts of RE integration to the network. Research A simulation model of typical Malaysian Medium
has shown that large amount of PV systems connected on the Voltage (MV) distribution network as shown in Fig. 1 is
distribution networks without proper coordination can causes modelled with Digsilent Power Factory. The MV network
the power quality issues such as voltage rise, voltage consists of one main intake substation namely, Pencawang
unbalance, reverse power flow, flicker and fluctuation [2], Masuk Utama (PMU) rated at 132/33 kV feeding to the main
[3]. distributed substation namely, Pencawang Pembahagian
Energy storage system has been proposed to store any Utama (PPU) rated at 33/11 kV.
surplus power generated by the RE sources in the national The main distributed substation (PPU) is then further
grid [4], and supply the energy whenever there are demand distributes the electricity supply across 44 units of distributed
in the national grid to mitigate power quality issues caused substation, namely Pencawang Elektrik (P/E) via five main
by the imbalance in generation and demand. Research has feeders, namely Feeder 1 to Feeder 5 respectively. The
proven that the installation of ESS on the 11 kV UK voltage at the distributed substation (P/E) is stepped down
distribution network is capable to control the voltage at the from 11 kV to 0.4 kV using on-load tap changer transformer

978-1-5386-6410-0/18/$31.00 ©2018 IEEE 89


rated 0.75 MVA Fig. 2 shows the details of the main bus coupler will be configured in normally close (N/C), so
distributed substation (PPU) where two transformer rated at that the downstream feeders are supplied by the active
30 MVA, 33/ 11 kV are connected across a bus coupler transformer to ensure the supply reliability while maintaining
(CBS) to supply feeder 1 to feeder 5. Under normal work can be carried out on the faulty transformer.
operation, the bus coupler is in normally open (N/O) The details of each distributed substation is showed in
configuration. Fig. 3 where the intake is supplied to non-load tap changer
transformer rated at 11/0.4 kV. At this point of view, the
consumers load and photovoltaic systems are connected
across the network via the feeders.

Figure 1. Typical Malaysia medium voltage distribution network.

In case of contingency situation or maintenance is Figure 2. Typical distributed substation (P/E).


required whereby one of the transformer is out of order, the

Figure 3. Main distributed substation network (PPU).

90
TABLE I. CABLE DATASHEET FOR THE CONNECTING CONDUCTORS
[13]
Conductor Specifications (3 cores)
Voltage Description Cross-
Level Mater- R X
(Underground sectional Insulator
ial (ohm/km) (ohm/km)
Cable) Area (mm2)
A11ABC240 Ald 240 PVCc 0.2110 0.1013
A11UG70PILC3C Cue 70 PILCb 0.5240 0.0938
A11UG185PILC3C Cue 185 PILCb 0.1950 0.0829
e
11kV A11UG300PILC3C Cu 300 PILCb 0.1200 0.0787
A11UG120XLPE3C Ald 120 XLPEa 0.2990 0.0873
A11UG150XLPE3C Ald 150 XLPEa 0.2645 0.1603
A11UG240XLPE3C Ald 240 XLPEa 0.1610 0.1524
33kV A33UG630XLPE1C Ald 630 XLPEa 0.0627 0.1070

Footnote: a XLPE: cross – linked polyethylene bPILC: paper insulated, lead


covered c PVC: PolyVinyl Chloride dAl: Aluminium eCu: Copper
Figure 4. Voltage drop along the feeder 1 to feeder 5 with constant load of
TABLE II. TRANSFORMER SPECIFICATION [14] 320 kVA, 0.97 pf lagging.

Distributed Three-phase Transformer


Description Voltage Rated Power Vector Short-Circuit
Level (kV) (MVA) Group impedance, UK (%)
T132T33M90 132/33 90 Yd1 13.04
T33T11M30 33/11 30 Dyn11 10.00
T11T0.4M0.75 11/0.4 0.75 Dyn11 4.57

B. Transmission Line and Transformer Parameters


The unit impedance of the connecting conductors is
being used in the simulation model is showed in Table 1 and
the transformer specifications in Table 2. The Specification
data are obtained from Tenaga Cable Industries [13] and
Malaysia Transformer Manufacturer (MTM) [14]
respectively.
III. CASE STUDY IN 3 PHASE VOLTAGE

A. Case Study 1: Simulation Model Verification Figure 5. Voltage drop along feeder 4 with various load factor.

The utility guidebook [15] is considered as the reference Further verification is conducted to evaluate the voltage
standard to determine the voltage violations in the feeders. In profile along feeder 4 with a variation of load factor. Feeder
Malaysia, the low voltage distribution network shall comply 4 consists of 11 units of distributed substations (P/E), with
with a voltage regulation within +10% and -6% of 0.4 kV. each rated at 0.75 MVA. Fig. 5 shows the voltage regulation
The analysis is carried out to investigate the voltage drop at each substation with a load factor of 25%, 45%, 55% and
across the feeders with respect to a constant loading. The 73% which is equivalent to 187.5 kVA, 337.5 kVA, 412.5
reliability of the electricity supply within a power system is kVA and 547.5 kVA respectively. The result has shown that,
important, and therefore, the distribution system is designed a load factor of less than 45% of the rated capacity is suitable
in such a way to consider redundancy. in the further studies. A tap setting of 7.5% can be applied to
In this case study, each of the distributed transformer is improve the feeder end voltage for load factor more than
assumed to be loaded with a 45% load factor with respect to 25% of the rated capacity of 750 kVA.
the transformer rated capacity, which is equivalent of 320 Case Study 2:Investigation of Voltage Profile with Respect
kVA. Fig. 4 plots the steady state voltage along the feeder to Different Location and Penetration Level
with respect to the feeder length across all five feeders that
are connected to the main intake substation. The result shows The case study is carried out to investigate the
that if the distributed substation is loaded with a 45% load voltage impact on feeder 4 with the integration of PV
factor, the customers who are attached to the feeder end of systems installed at various location as shown in Table
feeder 4 will experience severe voltage drop along the line as 3. In this case study, assume a constant load of 320
the distance increased. Hence, a tap setting of 7.5% is kVA at 0.97 power factor lagging are loaded across all
applied to feeder 4 to ensure the voltage at feeder end are substation along feeder 4, and the study is divided into
regulated within the statutory limit. four extreme scenarios as follows:

91
x Scenario 1: No PV system is installed at any point of PV power generation, the maximum allowable PV system
the feeder. capacity connected on low-voltage feeder pillar is 90% [16]
x Scenario 2: PV systems with various penetration level of the transformer capacity, while maintaining the voltage
are installed at the first 6 substations of the feeder. regulation within +6% and -10% [16]. From Fig. 6 shows
this result where voltage at the last substation has improved
x Scenario 3: PV systems with various penetration level by 1.23% if there is only 15% of PV penetration level.
are installed at the last 6 substations of the feeder. However, if the PV system penetration level is increased up
x Scenario 4: PV systems with various penetration level to 90%, there will be better performance which the overall
are installed at the every substations of the feeder. feeder voltage will be improved 5.68%.

TABLE III. INST ALLATION LOCATION OF THE PV SYSTEM FOR


SCENARIO 1–4

Substation Substation PV Systems Connection Terminal:


Name Location Scenario
(KM)
1 2 3 4
PMU1 0.00
PPU2 14.00
P/E 94 15.60 • •
P/E 91 18.00 • •
P/E 42 20.10 • •
P/E 35 22.40 • •
P/E 37 25.60 No PV • •
installed
P/E 97 28.60 • • •
P/E 98 30.80 • •
P/E 96 32.90 • •
P/E 34 36.90 • •
P/E 71 39.30 • •
P/E 95 41.20 • • Figure 7. Voltage profile with different penetration level with respect to
the installation at feeder end.

Figure 6. Voltage profile with different penetration level with respect to Figure 8. Voltage profile with different penetration level with respect to
the installation at feeder front. the installation along the feeder.

The results for scenario 2 where PV systems with various The voltage profile for scenario 3, where different PV
penetration level are installed at the first 6 substations of the systems penetration levels with respect to the installation
feeder namely, P/E 94, P/E 91, P/E 42, P/E 35, P/E 37 and location at feeder end is showed in Fig. 7. The PV systems
P/E 97 is showed in Fig. 6. The PV penetration levels are are installed at the last 6 substations of the feeder which are
varies from 0% (benchmark), 15%, 30%, 45%, 60%, 75% P/E 97, P/E 98, P/E 96, P/E 34, P/E 71 and P/E 95. From this
and 90% with respect to the power rating of the transformer. result, it can be seen that the PV penetration level at 15% has
According to the utility handbook for grid interconnection of improved by 4.26% of the overall voltage performance.

92
Another positive result is when PV penetration level increase loading range. Case study 2 is to investigate the voltage
to 90%, the voltage profile of has improved by 19.77%. profile with different PV installation points with respect to
However, with the 90% of the PV penetration level, last 5 different PV penetration level. The scenario installation of
substations at the feeder 4 are experiencing the voltage rise PVs are categorized as first 6 substation of the feeder, last 6
which is out of the statutory limit. substation of the feeder and along the feeder. This study is to
Fig. 8 shows the results for scenario 4 where PV systems ensure the voltage profile is remained within the statutory
are installed at all the substations. It is noticed that the limit when the PV is installed at that particular point. As
voltage at the last substation experience a voltage increment voltage violation on the low voltage (LV) network are more
of 5.23% with 15% of penetration level while the last likely with feeder connected batteries or PV. From the data
substation experience an increment of 23.4% with 90% of comparison, installing the PV along the feeder cause all the
penetration level. However, from Figure 8, PV penetration substation experience high voltage profile which is out of the
level with 90% will incur most of the substations experience voltage boundary.
voltage rise which are out of statutory boundary. Hence, all
substations with 60% of PV penetrations is enough to ACKNOWLEDGMENT
perform good voltage profile as the voltage is within the The authors would like to thank Universiti Tunku Abdul
statutory limit. Rahman for providing the facilities and research fund to
carry out the research.
REFERENCES
[1] “Eleventh Malaysia Plan, 2016-2020 | Laman Web Rasmi Unit
Perancang Ekonomi.” [Online]. Available:
http://www.epu.gov.my/en/rmk/eleventh-malaysia-plan-2016-2020.
[Accessed: 12-Feb-2018].
[2] J. Wong, Y. S. Lim, J. H. Tang, and E. Morris, “Grid-connected
photovoltaic system in Malaysia: A review on voltage issues,” Renew.
Sustain. Energy Rev., vol. 29, pp. 535–545, Jan. 2014.
[3] J. Wong, Y. S. Lim, P. Taylor, and S. Morris, “Optimal utilisation of
small-scale embedded generators in a developing country – A case
study in Malaysia,” Renew. Energy, vol. 36, no. 9, pp. 2562–2572,
Sep. 2011.
[4] T. Mahto and V. Mukherjee, “Energy storage systems for mitigating
the variability of isolated hybrid power system,” Renew. Sustain.
Energy Rev., vol. 51, pp. 1564–1577, Nov. 2015.
[5] N. Wade, P. Taylor, P. Lang, and J. Svensson, “Energy storage for
power flow management and voltage control on an 11kV UK
distribution network,” in CIRED 2009 - 20th Int. Conf. and Exhibition
Figure 9. Energy storage system installed at the feeder end for maximum
on Electricity Distribution - Part 1, 2009, pp. 1–4.
PV system penetration.
[6] s Alnaser and L. F. Ochoa, “Optimal sizing and control of energy
storage in wind power-rich distribution networks,” in Proc. of 2016
Fig. 9 shows the voltage profile of each substation along IEEE Power and Energy Society General Meeting (PESGM), 2016,
feeder 4 with respect to different placement location of the pp. 1–1.
PV systems. It has shown that photovoltaic system, as a [7] F. Marra, Y. T. Fawzy, T. Bülo, and B. Blažic, “Energy storage
distributed generator is able to improve the voltage profile at options for voltage support in low-voltage grids with high penetration
the distribution network. However, the placement of the of photovoltaic,” in Proc. of 2012 3rd IEEE PES Innovative Smart
distributed generator makes a differences in terms on the Grid Technologies Europe (ISGT Europe), 2012, pp. 1–7.
voltage when the allocation is different. From this result, it [8] G. Mokhtari, G. Nourbakhsh, and A. Ghosh, “Smart Coordination of
can be seen that if the placement of photovoltaic system are Energy Storage Units (ESUs) for Voltage and Loading Management
in Distribution Networks,” IEEE Trans. Power Syst., vol. 28, no. 4,
installed at the feeder front, the overall voltage is improved pp. 4812–4820, Nov. 2013.
by 5% while maintaining within the voltage limit. However, [9] L. Wang, D. H. Liang, A. F. Crossland, P. C. Taylor, D. Jones, and N.
in case the same capacity of PV systems are installed at the S. Wade, “Coordination of Multiple Energy Storage Units in a Low-
feeder end, it can be seen that the overall voltage is increased Voltage Distribution Network,” IEEE Trans. Smart Grid, vol. 6, no. 6,
by 19%. pp. 2906–2918, Nov. 2015.
[10] K. H. Chua, Y. S. Lim, P. Taylor, S. Morris, and J. Wong, “Energy
IV. CONCLUSION Storage System for Mitigating Voltage Unbalance on Low-Voltage
Networks With Photovoltaic Systems,” IEEE Trans. Power Deliv.,
The objective of this study has been to present not only a vol. 27, no. 4, pp. 1783–1790, Oct. 2012.
case study of analyzing the effective allocation of energy [11] Wong Jianhui, Seng Lim Yun, and Morris Ezra, “Distributed Energy
based storage system (ESS) on a modern distributed network Storage Systems with an Improved Fuzzy Controller for Mitigating
with integrated high photovoltaic (PV) penetration but also Voltage Unbalance on Low-Voltage Networks,” J. Energy Eng., vol.
maintaining the voltage within the voltage boundary which is 142, no. 1, p. 04014058, Mar. 2016.
stated in the statutory limit. Case study 1 is verifying the [12] Wong Jianhui, Lim Yun Seng, and Morris Ezra, “Novel Fuzzy
Controlled Energy Storage for Low-Voltage Distribution Networks
network capability in the meantime to find out the suitable

93
with Photovoltaic Systems under Highly Cloudy Conditions,” J. [15] “TNB Better. Brighter.,” TNB Better. Brighter. [Online]. Available:
Energy Eng., vol. 141, no. 1, pp. B4014001, Mar. 2015. https://www.tnb.com.my/commercial-industrial/for-housing-
[13] “Tenaga Cable Industries Sdn Bhd | Manufacturing and Distribution developers-electrical-contractors. [Accessed: 07-Feb-2018].
of An Extensive Range of Power Cables.” [Online]. Available: [16] Azit, A. H., et al. (2012). TNB technical guidebook on grid-
http://www.tcisb.com.my/. [Accessed: 05-Mar-2017]. interconnection of photovoltaic power generation system to LV and
[14] “DISTRIBUTION TRANSFORMER | Malaysia Transformer MV networks, Tenaga Nasional Berhad, Malaysia.
Manufacturing Sdn. Bhd.” [Online]. Available:
http://www.mtmsb.com.my/. [Accessed: 05-Apr-2017].

94

You might also like