Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

SPECIAL FOCUS: GREEN TECHNOLOGIES

Reduce emissions and save energy with an


unconventional flare gas recovery system
A. H. AL-TIJANI, Saudi Aramco, Dhahran, Saudi Arabia; and
I. ASHIQ, Yanbu NGL Fractionation Plant, Saudi Aramco, Yanbu, Saudi Arabia

An unconventional flare gas recovery gas compressors have recurring main- continuous flare gas at 0.48 psig, using
system (FGRS) can be designed without tenance, operating spare and reliabil- 0.95 MMsft3d of available high-pressure
a gas compressor to collect the boiloff ity issues, similar to any other rotating gas as motive gas. The process scheme
gas from the ethane tank to the boilers at equipment in a process plant. It would, was modeled, simulated and confirmed
the utility area. This innovative recovery therefore, be an attractive and economic possible, using proprietary software.a
system will provide significant capital venture if the use of a gas compressor can To this end, a recovery system utilizing
and operating cost savings by eliminat- be eliminated from the FGRS without high-pressure gas at 380 psig as motive
ing the installation and operation of a gas jeopardizing the performance and safety gas—in an ejector to transport the gas
compressor as part of the conventional of the system. To this end, a scheme was from the flare site to the boiler utility
FGRS. The FGRS scheme includes the evaluated using a gas ejector that can area—was established. FIG. 2 shows the
use of a gas ejector with high-pressure provide additional operating flexibility calculated flowrates and pressures for
motive gas to boost low-pressure ethane and reliability to the system. the feeds and outlet streams of the ejec-
flare gas to the intermediate pressure, At the Yanbu NGL fractionation tor. FIG. 3 shows the flow scheme for the
which is required to return the gas to the plant, the purge gas used is ethane. ejector-based FGRS.
boilers at the utility area. To ensure no air ingress into the flare This flare gas recovery approach is
The case study included here ex- headers, a minimum flowrate of purge possible based on the fact that there is
plains how the unconventional FGRS gas must be continuously maintained enough room in the boiler utility area
was applied at Saudi Aramco’s Yanbu for each flare system at the plant. One to accommodate the flared gas volume.
NGL fractionation plant to continuous- 100% ethane tank flare system is in use. Flare gas recovery at the plant requires
ly recover approximately 1.1 MMsft3d The system has a flare header of 12 in.–
of valuable C2+, which is equivalent to 16-in. diameter; therefore, the maxi-
1,961 MMBtu/d in fuel energy savings. mum continuous load of ethane boiloff
The proposed FGRS scheme will also to flare system is 1.1 MMsft3d. The total
minimize greenhouse gas emissions and flared gas is available to be continuously V85-F-196 Flare
provide positive environmental benefits. collected and routed back to the boiler stack
utility area.
Project introduction. Flare systems are The study revealed that it is feasible to
PCV-002
essential parts of any oil and gas process- recover the continuous flared gas by con-
Knockout
ing plant. These systems, which essen- necting new piping from the flare system drum
tially consist of flare headers and laterals, upstream of the flare knockout drum to
liquid knockout drums and flare stacks, the boiler utility area, to allow continu- Ethane
serve as one of the last layers of protec- ous boiloff and utilize it as fuel for the tank (T-501)
tion for the plant to safely relieve pres- boilers. FIG. 1 shows a schematic of the
sure from plant equipment during an ethane tank flare system arrangement at FIG. 1. Schematic of ethane tank flare system
overpressure condition. As part of safety the Yanbu NGL processing facility. at the Yanbu NGL processing plant.
requirements, flare headers are normally The unconventional FGRS scheme
provided with continuous purging to was established and carefully evaluated Collected gas
prevent vacuums within the system, keep through hydraulic and process simula- from ethane tank
air out of the system and prevent possi- tions, using both in-house programs and 0.48 psig, Gas to boilers
HP motive gas 1.1 MMsft3d utility area
ble explosions. proprietary software,a as described in the 380 psig, 0.95 MMsft3d 8 psig, 2.05 MMsft3d
The major component of any conven- following section.
tional FGRS is the gas compressor. It is Ejector
required to compress the low-pressure Ejector-based FGRS. The scheme
flare boiloff gas to a pressure that can re- was developed by utilizing a suitable FIG. 2. Calculated flowrates and pressures
for the Yanbu FGRS ejector.
turn the gas to the process. The recovery ejector to collect the 1.15 MMsft3d of
Gas Processing & LNG | MARCH/APRIL 202115
SPECIAL FOCUS: GREEN TECHNOLOGIES

psig. The simulation results also validate


the pressure drop calculation performed
by a third party.

Takeaway. The established FGRS


scheme has multiple economic ben-
efits. First, it will recover approximately
1.1 MMsft3d of valuable C2+, which is
equivalent to 1,961 MMBtu/d in fuel
energy savings.
Second, the system will operate with-
out any energy consumption or rotating
FIG. 3. Flow scheme of ejector-based FGRS at the Yanbu facility.
equipment (all installations are static
equipment—i.e., no moving parts). The
system will utilize energy that would
otherwise have been wasted or flared
since plant startup.
Third, the flare gas recovery system
will improve the reliability and life span
of the flare tip, thereby reducing the re-
curring cost of flare tip replacements.
The proposed system will minimize
greenhouse gas emissions and provide a
positive environmental impact.
Finally, operation of the established
FGRS at the Yanbu NGL fractionation
plant will provide an operating experi-
FIG. 4. Ethane recovery system simulation. ence base within Saudi Aramco for oth-
er facilities to adopt. GP
only the means to transport the gas Simulation results. The ethane recov-
from the ethane tank flare system site to ery system is designed to take ethane NOTE
the boiler utility area at the gas plant (a from the ethane storage tanks and com- a
HYSYS
total distance of approximately 1.7 km) press it for firing at 1.5 psig–2 psig and
within the limited differential pressure. for delivery at approximately 3.7 psig to ABDULAZIZ H. AL-TIJANI is
Appropriate pipe sizes within the avail- the two boiler skids. an Engineering Specialist at
Saudi Aramco’s Process and
able differential pressures were deter- The ethane recovery system was Control Systems Department in
mined by careful analysis of the hydrau- simulated, using proprietary softwarea Dhahran, Saudi Arabia. He holds a
lic simulation results. The results show to perform the hydraulic analysis and BS degree in chemical engineering
that 2.05 MMsft3d of mixed high-pres- predict the process conditions (FIG. 4). from King Fahd University of
Petroleum and Minerals (KFUPM) and a MS degree
sure fuel gas and ethane at 17.5 psig will Actual pipe lengths for the existing and in oil and gas surface facilities from KFUPM
arrive at 8 psig at the utility area, using new pipes are taken from an isomet- (in partnership with IFP). Mr. Al-Tijani supports
6-in. piping. ric drawing, to account for the pres- company operations and project design, mainly in
In the proposed recovery system, sure losses from the ethane tank to the flare and relief systems and flare gas recovery
applications. He supports Saudi Aramco and joint-
the pressure control valve already exists boilers at the utility unit. The design
venture oil and gas operational facilities, pipelines,
between the flare gas offtake points and flow used to size the recovery system is process simulations and various phases of projects.
the flare knockout drum. This design 0.4 MMsft3d–1.1 MMsft3d, with an eth-
maintains a slight positive pressure in ane composition of 98%. IRFAN ASHIQ is a Senior
Operations Engineer for Saudi
the flare header and prevents both an The results of the hydraulic analysis
Aramco at the Yanbu NGL
undesirable opening condition for the indicated that new and existing pipes are fractionation plant. He has more
control valve and the release of eth- of adequate size to avoid backpressure on than 22 yr of professional
ane to the flare system. Whenever the the ethane tank under normal operation, experience in process design,
amount of gas released into the flare and they are able to deliver the mixed operation and commissioning
for upstream oil and gas, heavy oil and
system exceeds the capacity of the re- gas stream at a pressure of 3.7 psig to the petrochemicals. Prior to joining Saudi Aramco,
covery system (1.1 MMsft3d), a pres- boiler skids. A sensitivity analysis, in- he was the Lead Process Engineer at SNC Lavalin
sure control valve on the flare recov- cluding summer and winter conditions, in Canada and a Senior Process Engineer at
ery line will act to maintain the flow at was also run to calculate the system pres- Propak Systems Ltd. in Canada. He holds an
MS degree in chemical engineering from the
1.1 MMsft3d. The proposed recovery sure drop. The calculated pressure drop University of Calgary in Canada and a professional
scheme is illustrated by the flow scheme for the 8-in. ethane line from the tank certification from the Association of Professional
shown in FIG. 3. vapor line to the ejector skid inlet is 0.1 Engineers and Geoscientists of Alberta (APEGA).

16MARCH/APRIL 2021 | GasProcessingNews.com

You might also like