Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

3CC SYSTEM

Technical Specification
SHORT SPECIFICATION - 3CC SYSTEM:
(To appear in Main Specification & on Drawings)
The responsibility for ensuring that the correct minimum
All concrete (specify areas) to be produced by an approved cement content is contained in the concrete always rests
supplier and constructed in accordance with the Main with the Contractor. Cement contents shall be recorded
Specifications and drawings and strictly in accordance with by the concrete producer on each concrete docket.
current Cementaid 3CC SYSTEM Detailed Technical
Specifications, using only Cementaid added ingredients and 1.2 Admixtures:
concrete containing not less than 350kgs of cement per cubic All concrete shall contain Cementaid Superplastet (F, SR or G),
metre, and having a W:C ratio not in excess of 0.45, in high range water reducing agent at a rate of 0.8 - 1.5 % by
conjunction with structural reinforcement of hard rib weight of cement, (or cement plus ggBFS, PFA etc.). The level
deformed bar and top steel reinforcement grid and other and type of Superplastet will be according to ambient
details conforming to current recommendations and temperature or as recommended by Cementaid. The concrete
requirements of Cementaid. shall further contain Cementaid 3CC, Structural Damproofing
Ingredient, at the rate of 15 litres per cu. m. of concrete. Water
contents are to be reduced accordingly to allow for the effects of
the ingredients on the concrete slump, and the concrete is to be
DETAILED SPECIFICATION - 3CC SYSTEM: mixed thoroughly. In all cases, the free water : cement ratio
(To be included in full in Main Specification)
shall not exceed 0.45. No other admixtures or ingredients are
to be included or allowed for in the concrete unless
1. CONCRETE:
specifically authorised by Cementaid in writing.
All concrete must comform to current National Standard
Specifications and be designed, WITHOUT ADDITIVES, for
1.3 Concrete Suppliers:
F’c of at least 30N.mm2 or greater if required by the
Not all premixed concrete producers are automatically
Engineer, at slumps not less than 50mm and not greater than
approved for 3CC SYSTEM quality concrete. The Contractor
150mm.
should contact Cementaid’s local Manager to confirm
approval of proposed concrete producers before ordering
1.1 Cement Content:
concrete.
From considerations of heat development or durability or for
other reasons, the specifier will decide whether to use
Cementaid approval does not remove responsibility for basic
Portland Cement (PC) only, Portland cement and ground
concrete quality and minimum cement contents stated here,
granulated Blast Furnace Slag (ggBFS), [recommended for
from the concrete producer or the Contractor ordering the
slabs > 400mm thick] or Portland cement and fly ash (PFA).
concrete. The premix supplier must be able to ensure
continuity of supply to avoid colds joints, etc.
When ggBFS is used, it can present up to a maximum of 65%
of the total cementitious content. When PFA is used, the 1.4 Trial Mixes:
corresponding maximum percentage is up to 30%. The concrete producer, with Cementaid present, shall mix and
test a trial mix of concrete(s) containing the 3CC System
The minimum contents of cementitious material (in kg/m3) ingredients, to satisfy the Engineer that the enhanced concrete
shall be: conforms to strength, water : cement ratio, slump, and other
performance requirements. The trial mix concrete shall
Mix Total Cementitious PC Content furthermore have a corrected 30 minute absorption of no greater
than 1.5% (one and one-half percent) as measured by BS 1881:
PC only 350 350 Part 122: 1983, except that the age at test shall be 7 days.
PC / ggBFS 400 160 1.4 Trial Mixes (..Continued.)
The trial mixes should endeavour to minimise the fine aggregate
PC / PFA 380 300 percentage and shrinkage potential as well as optimise other
properties of the concrete. After satisfactory completion and

pg1/3
approval of the trial mixes, compliance of the concrete with the with current Codes of Practice and Cementaid
mix description, slump and absorption requirements shall be the recommendations. Care shall be taken to fill every part of the
responsibility of the Main Contractor and / or concrete forms, to force concrete under and around reinforcing without
producer. displacing it, to work back coarse aggregate from the face and
to remove all air bubbles and voids. Concrete which cannot be
1.5 Testing: placed free from honeycombs, or segregation, shall be
The Engineer reserves the right to require the concrete as placed rejected by the contractor. Compaction shall be assisted by
and cured in the actual structure, to conform with the absorption sufficient number of approved immersion type vibrators. They
requirement within 7 days of placement. The Contractor shall shall provide sufficient intensity to cause the concrete to
provide costings for absorption testing by an approved compact rapidly into place. The number of internal vibrators
Laboratory, and if so required, absorption samples shall be provided shall be sufficient to consolidate the incoming
taken during construction as directed by the Engineer. These concrete within 15 minutes. Vibrators shall not be held
samples shall be tested as above and shall conform with the against forms or reinforcing steel, nor used for flowing the
absorption requirement. Care shall be taken to prevent early concrete or spreading into place. Vibrators shall not be held
moisture loss from all 3CC System concrete test samples, in one position so long as to result in segregation of concrete
including those for compressive strength, by immediate materials or formation of laitance on the surface.
covering with polythene sheet and protection from direct sun
and wind prior to water immersion. 2.2 Troweling:
Concrete shall be brought to a fine, dense finish using a
1.6 Slump: mechanical trowel. The steel trowelled finish may then be
Concrete must not be placed with slump greater than 150mm roughened if required, by broom or wood float, for subsequent
or less than 50mm. Flowing concretes with slump greater than applied finishes or traction, etc.
150mm are only allowed when the mix design is altered to
accommodate such flowing slumps and with the approval of 2.3 Curing & Cooling:
the Engineer and Cementaid. Wind-breaks, sun-shades and other protection shall be
installed as required, to protect against early loss of moisture
Where required, SUPERPLASTET F, (non-retarding), may be from the concrete. Cementaid CALVAP, Evaporation
used for re-dosing at site to attain workable slump and to Retardant, can be used to reduce early moisture loss.
prevent excessive retardation.
Immediately after trowelling and as soon as the concrete is
For such re-tempering, the level of addition of hard enough to withstand a man’s weight without marking,
SUPERPLASTET F to the concrete will depend on the slump apply a sprayed application of Cementaid CALCURE CR or
at the time of addition and the desired workability. Generally, D, membrane curing compound, at a minimum rate of
a dosage of between 0.1 and 0.3 litres per 100kg of cement 1 litre / 5m², followed by light water ponding or water spray
would suffice. After SUPERPLASTET addition, the for at least 7 days. Sections greater than 400mm thickness
workability would be enhanced for approx. 30-45 minutes shall further be covered with min. 1000 gauge polythene sheet
depending on temperature and age of concrete. for a minimum of 7 days to minimise temperature differential
within section.
SUPERPLASTET F can be safely re-dosed several times
provided there is no segregation. However, with each addition 2.4 Formwork
the zeta potential of the concrete will continue to increase Formwork shall be left in place for a minimum of three days,
making it more sticky and difficult to place. Therefore more or if removed befor 3 days, Cementaid CALCURE B shall be
that two re-dosages of SUPERPLASTET should be avoided. applied at the minimum rate of 5m2 per litre.
Re-tempering if the concrete is more than 4 hours old in
temperate climates or 3 hours in tropical climates is not 2.5 Loading on Slabs
recommended. During the construction phase, the age and level of loading on
slabs shall be approved by the Engineer. Removal of propping
2. CONSTRUCTION PROCEDURES: for 3CC System suspended slabs shall be approved in writing
2.1 Placing: by the Engineer.
Concrete shall not be placed with air temperature below 4°C
or above 35°C without the approval of the Engineer and
suitable modification of admixture dosage according to
Cementaid recommendations. 2.6 Finishes, etc.
Refer to current Code requirement for hot weather Completed sections or surfaces of 3CC System concrete shall
concreting. be inspected and approved for water-tightness in reasonable
time before application of, or obstruction by applied finishes,
During and immediately after placing in the forms, the renders, landscaping, permanent plant and equipment etc.
concrete shall be thoroughly compacted by means of
continuous tamping, spading and slicing, and be consistent 3. GENERAL DESIGN CONSIDERATIONS:

pg2/3
3.1Reinforcement: Immediately prior to continuing casting, the joint surface is to
All structural reinforcement shall be hard ribbed deformed be liberally and thoroughly brushed with Cementaid
(h.r.d) bar to Engineer’s detail drawings. WELDCRETE / cement slurry (1 part : 2 parts), taking care to
avoid coating of the Everdure Waterstop strip. New concrete
3.2 Special Temperature Reinforcement: (Roof Slabs & is to be placed directly against the prepared step
Jointless Ground Floor Slabs) joint, and properly compacted into the wet Weldcrete /cement
Minimum top steel requirement shall be hard rib deformed slurry. Do not allow the WELDCRETE slurry to dry out,
(h.r.d) bar or mesh, 12mm diameter, continuous both ways, at otherwise bond failure may occur. If drying occurs, re-apply
300mm centres, with concrete cover to steel not less than WELDCRETE slurry before proceeding
25mm, nor greater than 40mm. Equivalent steel of 10mm bars
or mesh, at 200mm centres is recommended to be used if 3.6 Expansion Joints:
available. This minimum temperature “grid” steel may be Expansion joints will be permitted in the slab but must
included in the Engineer’s structural requirements, but must conform to the details provided by the Engineer.
be continuous in both directions.
3.7 Projections:
3.3 Re-entrant Angles: • For cast in place projections, Cementaid Everdure
Where re-entrant angles occur, three 10mm h.r.d bars, spaced Waterstop is firmly affixed around the middle or “waist”
100mm apart must be placed top and bottom, at 90 degrees of the projection and protected from wetting prior to
across the angles. casting the 3CC concrete.

3.4 Slab / Beam Interface: • For projections which have been positioned through
Lapping bars, minimum Y12, shall be used to provide prepared openings, the surfaces of the opening are to be
continuous reinforcement for bottom slab reinforcing over thoroughly roughened, cleaned and primed with
beam supports, to prevent cracking due to sectional change. WELDCRETE/cement slurry, then the space is filled with
Cementaid CALGROUT NO. 7, Non-shrink Grout
3.5 Section Thickness: containing 3CC at the rate of 5ml. per kilo of
Concrete thickness to be as specified and not less than CALGROUT.
150mm. Variation in thickness would be subject to
Cementaid approval and discussion with the Engineer. 4. FIELD SERVICE
4.1 All works shall be subject to supervision by a
3.6 Construction Joints: representative of the Client.
All construction joints and penetrations in the concrete must
be formed and constructed strictly in accordance with current 4.2 Site monitoring / attendance by a representative of
Cementaid recommended details and materials, attached and Cementaid shall be provided during all 3CC System concrete
available from your Cementaid Representative. pours, this company being notified at least 48 hours before
a pour commences, and at each stage of the proceedings.
Construction joints in slabs shall be formed as “step” or “key” Cementaid attendance does not constitute supervision, which
joints. All joint formwork to be treated with Cementaid remains the responsibility of the Contractor.
CALSTRIP Surface Retarding Form Release Agent. END.
Immediately upon removal of joint form, the retarded mortar
is to be thoroughly washed away to produce a clean,
roughened surface. CONTACT & SERVICE DETAILS;
Cementaid Everdure Waterstop to be firmly affixed by
contact adhesive to the angle of the clean step joint prior to The Sales Manager,
casting, and protected from premature wetting. (Alternatively, CEMENTAID (SEA) Pte. Ltd.
use Everdure Grout Pipe)
12 Neythal Road,
Jurong,
Singapore 628578.
Phone; 65 6896 9801 to 3
Fax; 65 6896 9807

pg3/3

You might also like