Professional Documents
Culture Documents
Gammon Engineers and Contractors PVT LTD V National Highways Authority of India
Gammon Engineers and Contractors PVT LTD V National Highways Authority of India
Gammon Engineers and Contractors PVT LTD V National Highways Authority of India
Judgement Held
In the facts of this case, the fee schedule was fixed by the agreement as amended by the
Circular between the parties which will be operative and the Arbitral Tribunal will be entitled
to charge their fees in accordance with it and not in accordance with the Fourth Schedule to
the 2015 Amendment Act.
However, the application to remove the arbitrators stating that their mandate must
terminate, is wholly disingenuous and would not lie for the simple reason that an arbitrator
does not become de jure unable to perform his functions if, by an order passed by such
arbitrator(s), all that they have done is to state that, in point of fact, the agreement does
govern the arbitral fees to be charged, but that they were bound to follow the Delhi High
Court in Gayatri Jhansi Roadways Limited case which clearly mandated that the Fourth
Schedule and not the agreement would govern.
The arbitrators merely followed the law laid down by the Court and cannot, on that count,
be said to have done anything wrong so that their mandate may be terminated as if they
have now become de jure unable to perform their functions. Therefore, the decision of the
High Court qua termination of the mandate of the Arbitration Tribunal is set aside.
The change in language of section 31(8) read with Section 31A of the Act deals only with the
costs generally and not with arbitrator’s fees.
It is true that the arbitrator’s fees may be a component of costs to be paid but it is a far cry
thereafter to state that section 31(8) and 31A would directly govern contracts in which a fee
structure has already been laid down by the parties.
The declaration of law by the Delhi High Court in National Highways Authority of India vs.
Gayatri Jhansi Roadways Limited, 2017 SCC OnLine Del 10285 is not a correct view of the
law.
Sections mentioned:
(1) In relation to any arbitration proceeding or a proceeding under any of the provisions of this Act
pertaining to the arbitration, the Court or arbitral tribunal, notwithstanding anything contained in
the Code of Civil Procedure, 1908 (5 of 1908), shall have the discretion to determine—
Explanation.—For the purpose of this sub-section, “costs” means reasonable costs relating to—
(i) the fees and expenses of the arbitrators, Courts and witnesses;
(iii) any administration fees of the institution supervising the arbitration; and
(iv) any other expenses incurred in connection with the arbitral or Court proceedings and the
arbitral award.
(2) If the Court or arbitral tribunal decides to make an order as to payment of costs,—
(a) the general rule is that the unsuccessful party shall be ordered to pay the costs of the
successful party; or
(b) the Court or arbitral tribunal may make a different order for reasons to be recorded in
writing.
(3) In determining the costs, the Court or arbitral tribunal shall have regard to all the circumstances,
including—
(c) whether the party had made a frivolous counterclaim leading to delay in the disposal of the
arbitral proceedings; and
(d) whether any reasonable offer to settle the dispute is made by a party and refused by the
other party.
(4) The Court or arbitral tribunal may make any order under this section including the order that a
party shall pay—
(5) An agreement which has the effect that a party is to pay the whole or part of the costs of the
arbitration in any event shall be only valid if such agreement is made after the dispute in question
has arisen.]