Hosan 1 EWOR Final Check
Hosan 1 EWOR Final Check
CONTENTS
1 WELL PARAMETERS
2 WELL SUMMARY
4 TIME ANALYSIS
7 BIT RECORD
8 MATERIAL CONSUMPTION
9 WELL SCHEMATIC
SIGNATORIES
Drilling Engineer
Head Drilling
Operation Manager
WELL PARAMETERS
WELL NAME /WELL TYPE : HOSAN-1 / Exploration/ Vertical Well
BLOCK / STATE : Block 8 / Dindir
WELL CLASSIFICATION / AFE MANAGER : Exploration
LATITUDE / LONGITUDE : 13º 26' 19.4N 34º 06' 28.4" E
UTM ( ZONE 36 ) : 1485929.56 m N 619933.78 m E
SEISMIC LINE : SD8PC-2D-04-94
OBJECTIVE : DINDER-3 & LOWER DINDER -2 SANDS / BLUE NILE SANDS
OFFSET WELL(S) : Dindir-1
MOVING DISTANCE : 1020 km from TJ-11
CASING SCHEME : TYPE SIZE (in) DEPTH (mRKB) GRADE/WEIGHT (ppf) CONN.
CONDUCTOR : 20 18 K-55 94 BT &C
SURFACE : 13.375 552 L-80 68 BT &C
INTERMEDIATE : 9.625 1735 L-80 47 BT &C
PERFORMANCE INDICATORS
11-Nov-04 18 Moving In & Rigging Up DT 103 5.00 5.00 4,292 4,292 Wait on Dailylight
12-Nov-04 18 Moving In & Rigging Up DT 103 12.00 17.00 10,302 14,594 Wait on Dailylight
13-Nov-04 18 Moving In & Rigging Up DT 103 12.00 29.00 10,302 24,895 Wait on Dailylight
14-Nov-04 18 Moving In & Rigging Up DT 103 12.00 41.00 10,302 35,197 Wait on Dailylight
15-Nov-04 18 Moving In & Rigging Up DT 103 12.00 53.00 10,302 45,498 Wait on Dailylight
16-Nov-04 18 Moving In & Rigging Up DT 103 12.00 65.00 10,302 55,800 Wait on Dailylight
17-Nov-04 18 Moving In & Rigging Up DT 103 12.00 77.00 10,302 66,101 Wait on Dailylight
18-Nov-04 18 Moving In & Rigging Up DT 103 12.00 89.00 10,302 76,403 Wait on Dailylight
19-Nov-04 18 Moving In & Rigging Up DT 103 12.00 101.00 10,302 86,704 Wait on Dailylight
20-Nov-04 18 Moving In & Rigging Up DT 103 12.00 113.00 10,302 97,006 Wait on Dailylight
21-Nov-04 18 Moving In & Rigging Up DT 103 12.00 125.00 10,302 107,307 Wait on Dailylight
22-Nov-04 18 Moving In & Rigging Up DT 103 12.00 137.00 10,302 117,609 Wait on Dailylight
23-Nov-04 18 Moving In & Rigging Up DT 103 12.00 149.00 10,302 127,910 Wait on Dailylight
24-Nov-04 18 Moving In & Rigging Up DT 103 12.00 161.00 10,302 138,212 Wait on Dailylight
25-Nov-04 18 Moving In & Rigging Up DT 103 12.00 173.00 10,302 148,513 Wait on Dailylight
26-Nov-04 18 Moving In & Rigging Up DT 103 12.00 185.00 10,302 158,815 Wait on Dailylight
27-Nov-04 18 Moving In & Rigging Up DT 103 12.00 197.00 10,302 169,116 Wait on Dailylight
28-Nov-04 18 Moving In & Rigging Up DT 103 12.00 209.00 10,302 179,418 Wait on Dailylight
29-Nov-04 18 Moving In & Rigging Up DT 103 7.00 216.00 7,160 186,578 Wait on Dailylight
Rig Equipment - change out
9-Dec-04 693 Drilling 12 1/4" hole DT 201 2.00 218.00 5,314 191,892
main compound chain.
Rig Equipment, Service
16-Dec-04 1364 Drilling 12 1/4" hole DT 201 0.50 218.50 1,017 192,909
Drawwork.
Rig Equipment - Repair
18-Dec-04 1675 Drilling 12 1/4" hole DT 201 1.00 219.50 2,000 194,909
broken drawworks chain
Rig Equipment - Repair
30-Dec-04 1925 Drilling 8 1/2" hole DT 201 2.00 221.50 3,484 198,393
rotary chain
Rig Equipment - Replace
31-Dec-04 1964 Drilling 8 1/2" hole DT 201 0.50 222.00 961 199,354
rotary drive chain
Rig Equipment -Kelly
3-Jan-05 2021 Drilling 8 1/2" hole DT 201 4.50 226.50 7,703 207,057
changed out due to leaking
Rig Equipment - Replace
17-Jan-05 2751 Drilling 8 1/2" hole DT 201 1.00 227.50 2,090 209,148
rotary input line.
Rig Equipment - Replace
18-Jan-05 2793 Drilling 8 1/2" hole DT 201 0.50 228.00 1,055 210,203
swivel wash pipe
Rig Equipment - Replace
20-Jan-05 2894 Drilling 8 1/2" hole DT 201 1.00 229.00 1,930 212,133
rotary chain
31-Jan-05 2911 (TD) Rigging Down & Moving Out DT 103 5.00 234.00 6,388 218,521 Wait on Dailylight
Time Analysis
Net Actual
Details Interval UOM Start time Actual Days Cum NPT Cum dptm
Days
PLAN COST
Code Description
(USD)
4A Site Survey 25,000
4B Tangible Materials 323,000
4C,4E Mobilisation/Demobilisation 780,000
4D Rig Costs 946,180
4G Consultants 168,500
4I Other Materials and Services 1,686,877
4J Construction 350,000
4K Security 2,700
4M Air Support 318,750
4N Communications 19,200
4P Well Testing 1,048,645
Total well costs 5,668,852
AL
ACTUAL COST
(USD)
16,000
234,268
580,000
1,021,437
211,412
1,971,077
300,000
-
345,895
15,688
413,750
5,109,527
DAYS VS DEPTH
1000
12-1/4 "
Depth (m-MDRKB)
2500
3500
BIT RECORD
Bit Run Bit Dia. Bit Mfur. Bit Type Serial IADC Jets Depth
No. No. (inch) No. Code (inch) In
/ 32" (m)
552 22.65 23.58 2 - 33 25-140 350 - 840 125 - 1450 9.0 - 9.4
381 22.20 16.35 1 - 30 30-130 335 - 880 55 - 930 9.4 - 9.5
552 6.17 27.71 2 - 30 125-130 835 - 890 960 - 1520 9.5
701 12.55 11.87 1 - 26 60-135 665 - 855 965 - 1660 9.7
1018 34.82 9.10 4 - 32 60-125 700 - 840 930 - 1340 9.8 -10.2
1364 57.95 5.97 17 - 33.5 85 - 135 725 - 840 1255 - 2080 10.2 - 10.6
1735 42.38 8.75 9.5 - 31.5 70 - 135 765 - 860 1680 - 2250 10.6 - 11.2
1780 25.50 1.76 3.5 - 24.5 70 - 140 415 - 510 1135 - 1655 11.5
1959 53.53 3.34 2.5 - 12.5 60 - 140 465 - 505 1320 - 2010 10.5 -12.1
1986 33.80 0.80 4.5 - 10.5 120 - 140 485 - 505 1360 - 1970 12 - 12.1
2117 51.05 2.57 9 - 34 135 - 140 480 - 500 1175 - 1815 12
2355 74.35 3.20 20 - 33 135 - 140 485 - 500 1410 - 1955 12 - 12.1
2551 77.05 2.54 26 - 31.5 135 - 140 485 - 495 1625 - 2005 12 - 12.1
2777 49.60 4.56 23 - 31.5 120 - 135 410 - 490 1835 - 2260 12 - 12.1
2849 42.55 1.69 25 - 35.5 130 - 140 370 - 435 1190 - 1805 11.7 - 11.8
2884 16.60 2.11 21 - 42.5 130 - 135 410 - 435 1500 - 1845 11.7
2911 21.00 1.29 25 - 45 70 - 115 425 - 430 1675 - 1920 11.7
DRILLING FLUIDS CONSUMPTION
Materials 13-3/8" & 9-5/8" Csg Six (6) Cement Plugs Total
Chemicals Price UOM QTY Cost QTY Cost QTY
D907 426.3 MT 105 44,761.50 59 25,151.70 164.00
D175 33.77 LT 248 8,374.96 139 4,694.03 387.00
D970 (WellClean) 110 BBL 102 11,220.00 0 - 102.00
D122A 9.01 LT 247 2,225.47 0 - 247.00
D080 7.8 LT 398 3,104.40 228 1,778.40 626.00
D081 6.29 LT 0 - 0 - -
D300 5.11 LT 0 - 0 - -
D112 25.51 KG 200 5,102.00 0 - 200.00
D145A 7.12 LT 0 - 0 - -
D168 16.64 LT 0 - 0 - -
D177 8.24 LT 151 1,244.24 142 1,170.08 293.00
D600G 10.96 LT 4088 44,804.48 5913 64,806.48 10,001.00
Total 120,837.05 97,600.69
D081 Liquid retarder D81 D600G D600G GASBLOK* gas migration control
additive
D300 C-FLAC D300
Total
Cost
69,913.20
13,068.99
11,220.00
2,225.47
4,882.80
-
-
5,102.00
-
-
2,414.32
109,610.96
218,437.74
WELL SCHEMATIC
CASING DEPTH
17 1/2" Hole
13 3/8" Csg, 68 ppf, L-80, BTC, 48 Joints 552
234 bbls of Lead Slurry @12 ppg ,155 bbls of
Class G slurry at 15.8 ppg slurry.
Cement
Plug
#6
1688 m
BP Bridge Plug @ 1690
12 -1/4" Hole
Cement 1700 m
9-5/8" Csg, 47 ppf, L-80, BTC, 151 Joints Plug 1735
#5 1830 m
216 bbls of Lead slurry at 12 ppg,420 bbls of
cement slurry at 15.8 ppg of cement class G
1860 m
Cement
Plug
#4
2050 m
2060 m
Cement
Plug
#3
2251 m
2510 m
Cement
Plug
#2
2700 m
Cement
Plug
#1
2890 m
2911 (TD)
Note: All the Cement plugs is 55 bbls of Tail slurry at 15.8 ppg of cement class G
CODE DETAILS / DATE 10-Nov-04 11-Nov-04 12-Nov-04 13-Nov-04 14-Nov-04 15-Nov-04 16-Nov-04 17-Nov-04 18-Nov-04 19-Nov-04
PT 101 Moving In & Rigging Up 6.00 19.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00
PT 102 Conductor
PT 103 Inspection & Modification
PT 104 Rigging Down & Moving Out
PT 201 Drilling & Deviation Survey
PT 202 Trips & Circulation
PT 203 Cementing, Grouting & WOC
PT 204 Run casing & Wellhead
PT 205 BOP equipment
PT 206 Abandonment
PT 207 Others
PT 301 Logging & RFT
Cement Log
PT 302 Coring
Scraper Run
Hole openning
Prepare Well for Testing
Run Liner Screen
Production Test
Run Competion String
Rig Release
DT 101 Wait on Location/ Road
DT 102 Wait on Truck
DT 103 Wait on Daylight 5.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00
DT 104 Wait on Weather
DT 105 Wait on Other Dept.
DT 106 Wait on Order
DT 107 Wait on Supplies
DT 108 Wait on Other
DT 201 Rig Equipment
DT 202 Cementing
DT 203 Drillpipe, Drill Collar & HWDP
CODE DETAILS / DATE 10-Nov-04 11-Nov-04 12-Nov-04 13-Nov-04 14-Nov-04 15-Nov-04 16-Nov-04 17-Nov-04 18-Nov-04 19-Nov-04
PT 101 Moving In & Rigging Up 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00 17.00
PT 102 Conductor
PT 103 Inspection & Modification
PT 104 Rigging Down & Moving Out
PT 201 Drilling & Deviation Survey
PT 202 Trips & Circulation
PT 203 Cementing, Grouting & WOC
PT 204 Run casing & Wellhead
PT 205 BOP equipment
PT 206 Abandonment
PT 207 Others
PT 301 Logging & RFT
Cement Log
PT 302 Coring
Scraper Run
Hole openning
Prepare Well for Testing
Run Liner Screen
Production Test
Run Competion String
Rig Release
DT 101 Wait on Location/ Road
DT 102 Wait on Truck
DT 103 Wait on Daylight 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00 7.00
DT 104 Wait on Weather
DT 105 Wait on Other Dept.
DT 106 Wait on Order
DT 107 Wait on Supplies
DT 108 Wait on Other
DT 201 Rig Equipment
DT 202 Cementing
DT 203 Drillpipe, Drill Collar & HWDP
CODE DETAILS / DATE 20-Nov-04 21-Nov-04 22-Nov-04 23-Nov-04 24-Nov-04 25-Nov-04 26-Nov-04 27-Nov-04 28-Nov-04 29-Nov-04
13-3/8" Surface Csg 9-5/8" Intemediate Csg Cement Plug-1 Cement Plug-2 Cement Plug-3 Cement Plug-4
Chemicals Price UOM QTY Cost QTY Cost QTY Cost QTY Cost QTY Cost QTY
D907 426.3 MT 62 26,430.60 43 18,330.90 12 5,115.60 12 5,115.60 12 5,115.60 13
D175 33.77 LT 121 4,086.17 127 4,288.79 27 911.79 27 911.79 31 1,046.87 31
D970 (WellClean) 110 BBL 47 5,170.00 55 6,050.00 - - -
D122A 9.01 LT 114 1,027.14 133 1,198.33 - - -
D080 7.8 LT 178 1,388.40 220 1,716.00 46 358.80 46 358.80 49 382.20 49
D081 6.29 LT - - - - -
D300 5.11 LT - - - - -
D112 25.51 KG - 200 5,102.00 - - -
D145A 7.12 LT - - - - -
D168 16.64 LT - - - - -
D177 8.24 LT 57 469.68 94 774.56 40 329.60 40 329.60 24 197.76 24
D600G 10.96 LT 4088 44,804.48 1764 19,333.44 1764 19,333.44 867 9,502.32 867
38,571.99 82,265.06 26,049.23 26,049.23 16,244.75
Well: Hosan-1
Job Cost
218,437.74
DAYS VS DEPTH
0.0 0.0 0.00 0.00 0.00 0.00 Rig move from TJ -11 toHosan 1
22.0 18.0 0.15 0.60 0.15 0.60 N/up 21 1/4" diverter, Test and Spud Well
550.0 552.0 4.00 2.00 4.15 2.60 Drill 12 1/4" pilot Hole to 550mRKB ( actual 552 m)
550.0 552.0 1.50 0.60 5.65 3.20 Run Open hole log ( including Circ. & POOH pirior to logging)
550.0 552.0 2.00 2.29 7.65 5.50 Open 12 1/4" pilot hole to 17 1/2" hole
550.0 552.0 1.00 1.50 8.65 7.00 Run & Cement 13 3/8"Csg
550.0 552.0 2.00 0.96 10.65 7.95 N/D diverter ,Cut Csg, Install Section A, N/UP BOP & Test.
550.0 552.0 0.50 0.35 11.15 8.31 RIH W/12 1/4" BHA, drill cement & float eqpmts
2000.0 1735.0 8.75 10.17 19.90 18.48 Continue Drill 12 1/4"Hole To SECTION TD @2000m (1735 m actual)
2000.0 1735.0 5.00 3.92 24.90 22.39 Open hole log ( including Circ. & POOH pirior to logging)
2000.0 1735.0 1.50 1.56 26.40 23.95 Run & cement 9 5/8" csg
2000.0 1735.0 2.00 0.65 28.40 24.60 N/D BOP, install sectionm B, N/U BOP AND TEST
2000.0 1735.0 1.00 0.71 29.40 25.31 RIH W/8 1/2"" BHA, drill cement & float eqpmts
3200.0 2911.0 11.00 28.27 40.40 53.58 Continue Drill 8 1/2"Hole To FTD @ 3200m ( 2911m actual TD)
3200.0 2911.0 5.00 5.21 45.40 58.79 Open hole log ( including Circ. & POOH pirior to logging)
3200.0 2911.0 1.70 2.50 47.10 61.29 Run & cement 7" liner / Actual: Abandonment & Scraper run
3200.0 2911.0 0.30 0.00 47.40 61.29 Cement LOG
3200.0 2911.0 15.00 0.00 62.40 61.29 Teat well as per testing program
3200.0 2911.0 1.50 0.58 63.90 61.88 L/D Pipes, R/D BOP AND SUSPEND WELL
3200.0 2911.0 0.50 0.00 64.40 61.88 Release the Rig
Hours & Days Calculator
FROM TO Hrs Days Cum. Days
14.40 0.60 0.60
12/1/04 11:30 12/3/04 11:30 48.00 2.00 2.60
12/3/04 11:30 12/3/04 22:30 11.00 0.46 3.06
12/3/04 22:30 12/4/04 2:00 3.50 0.15 3.20
12/4/04 2:00 12/6/04 9:00 55.00 2.29 5.50
12/6/04 9:00 12/6/04 23:00 14.00 0.58 6.08
12/6/04 23:00 12/7/04 21:00 22.00 0.92 7.00
12/7/04 21:00 12/8/04 20:00 23.00 0.96 7.95
12/8/04 20:00 12/9/04 4:30 8.50 0.35 8.31
12/9/04 4:30 12/19/04 8:30 244.00 10.17 18.48
12/19/04 8:30 12/20/04 8:00 23.50 0.98 19.45
12/20/04 8:00 12/23/04 6:30 70.50 2.94 22.39
12/23/04 6:30 12/23/04 21:00 14.50 0.60 23.00
12/23/04 21:00 12/24/04 20:00 23.00 0.96 23.95
12/24/04 20:00 12/25/04 11:30 15.50 0.65 24.60
12/25/04 11:30 12/26/04 4:30 17.00 0.71 25.31
12/26/04 4:30 1/23/05 11:00 678.50 28.27 53.58
1/23/05 11:00 1/23/05 22:30 11.50 0.48 54.06
1/23/05 22:30 1/28/05 16:00 113.50 4.73 58.79
1/28/05 16:00 1/31/05 4:00 60.00 2.50 61.29
1/31/05 4:00 1/31/05 18:00 14.00 0.58 61.87
1/31/05 18:00 1/31/05 18:00 0.00 0.00 61.87
ator
NPT Hrs Description For Chart Logging
N/Up Diverter & Spud the well 0.60 7.81
Drill 12-1/4" pilot hole to 552 2.00
Circulate, Wireline Survey & POOH
0.60
Open Hole Logging
Make up 17-1/2" hole opener and open hole
2.29
to 552m
Ream / Circulate, Wireline Survey & POOH
1.50
Run & Cement 13 3/8"Csg
N/D diverter ,Cut Csg, Install Section A,
0.96
N/UP BOP & Test.
M/up 12-1/4" BHA , tag and drill cement 0.35
3.00 Drill 12 1/4"Hole To SECTION TD (1735 m) 10.17
Circulate, Wireline Survey & POOH
3.92
Open Hole Logging + CST
Circulate & POOH for Casing
1.56
Run & Cement 9 5/8"Csg
N/D BOP,Cut Csg, Install Section B, N/UP
0.65
BOP & Test.
M/up 8-1/2" BHA , tag and drill cement 0.71
9.50 Drill 8 1/2" Hole To TD (2911 m) 28.27
Wiper trip / Circulate & POOH for Logging
5.21
Open Hole Logging + CST
Abandonment (Plugs & Scraper run) 2.50
Lay down D.P. & Nipple down B.O.P. 0.58
Rig Release 0.00