Professional Documents
Culture Documents
Lifting Plan Procedure 25 Ton
Lifting Plan Procedure 25 Ton
Lifting Plan Procedure 25 Ton
1. Scope
Works include Lifting Barriers for Loading, Unloading and Shifting (relocation/positioning)
Jersey Barriers
2. Loading, Unloading and Shifting Lifting Plan
a) A 25T capacity Mobile crane (with valid certificates) shall be used for the activity
b) Lifting sling shall be used. (No use of Jib).
c) Crane and Flatbed carrying Cable drum shall be positioned as per the attached plan
while erection/relocation of jersey barriers.
d) Outriggers shall be fully extended.
e) Crane shall be properly leveled on compacted ground.
f) Lifting area shall be barricaded using warning tapes.
g) Signage showing “LIFTING IN PROGRESS” shall be placed prior to lifting.
h) Working radius shall be 08 meters.
i) Boom length=10 meters
j) Lifting angle=40 degrees
k) Crane capacity as mentioned in points (h), (i), (j) = 8650kgs (8.65 Tons)
l) Load Lifting Load= A + B = 6 + 0.5 = 6.5 Tons
m) Actual Capacity of crane = 75.14 % (Safe to lift)