Daily Activity Plan and Progress

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

ADB-401A-2019:

PROCUREMENT OF PLANT, DESIGN, MANUFACTURING, SUPPLY, INSTALLATION, TESTING & COMMISSIONING OF 500KV DOUBLE CIRCUIT QUAD BUNDLE T/LINE FROM SUKI KINARI HYDRO POWER STATION TO INTERCONNECTION
POINT OF EXISTING NEELUM JHELUM 500KV DOUBLE CIRCUIT
DAILY ACTIVITY PLAN AND PROGRESS
Date of Submission : 29-09-2021 Date of Activity : 30-09-2021
Attention: NESPAK Site Office Garhi Habibullah
Section # 1 : Tower # 1-73
Assigned Duty Engr.
Assigned Duty Engr. Name (NEPC II Assigned Duty Engr. Assigned Duty Engr.
Sr.No Activity Tower # TIME REMARKS
Name (NEPC-II) Constrcution Team & Name (NESPAK) Name (NTDC)
CPM)
1 Survey for Tower Staking
2 Tower Staking with NESPAK
Mr. Athar
Mr. Sajjad
3 Access Road Construction 9,34,35/36,40,44 8:00 Mr. Shaheer Mr. Adnan In Progress
Mr. Bilal
Mr. Mehfooz
4 Excavation 38 (1), 47 (3) & 48 (1, 4) 8:00 Mr. Adnan Mr. Ajmal In Progress
5 preparation for Concrete 45 (2) 8:00 Mr. Ashfaq In Progress
6 Concrete 38 (4) 11:00 Mr. Talha Ishtiaq Mr. Ajmal
7 Form work Opening & Bitumen Applying
8 Backfilling 45 (4) 8:00 Mr. Arshad
9 Layout
10 Steel Sample Collection with NESPAK
Cylinder Testing
11 Enumeration of Trees 19-A to Onwards 8:00 Mr. Ameer Abbas
7 to 11, 40, 41 to 43 &
12 Row Clearence for Access Road 9:00 Mr. Abbas
50/51 to 54,56
Section # 2 : Tower # 74-147

Assigned Duty Engr. Assigned Duty Engr. Assigned Duty Engr. Assigned Duty Engr.
Sr.No Activity Tower # TIME REMARKS
Name (NEPC-II) Name (NHC) Name (NESPAK) Name (NTDC)
1 Survey for Tower Staking
2 Tower Staking with NESPAK 146 to 148 11:00 Mr. Izharulhaq

3 Access Road Construction 116/117 & 121 8:00 In Progress


91 (2), 101-A (3), 114 (3), Mr. Afzaal
4 Excavation 8:00 Mr. Ashraf Bhatti In Progress
118, 120 (2)
5 Preparation for Concrete
6 Concrete 90 (3) 13:00
Mr. Shaoor Mr. Junaid Lakho
7 Form work Opening & Bitumen Applying 89 (1) 17:00
8 Backfilling 89 10:00
10 Measurement of Access roads with NESPAK
11 Row for Tower and Access Road
12 Cylinder Testing
13 Enumeration of Trees with NTDC & Forest Dept. 140 to Onwards 9:00 Mr. Ahsanulhaq
Section # 3 : Tower # 148 -196
Assigned Duty Engr.
Assigned Duty Engr. Assigned Duty Engr. Assigned Duty Engr.
Sr.No Activity Tower # TIME NEPCII Construction REMARKS
Name (NEPC-II) Name (NESPAK) Name (NTDC)
Team
1 Survey for Tower Staking
2 Tower Staking with NESPAK 154 to Onwards 9:00 Mr. Waseem
3 Access Road Construction
4 Excavation 174 (4) & 181 (2) 8:00 Mr. Khalid Mr. Sheraz ` In Progress
5 Preparation for Concrete
6 Concrete
7 Form work Opening & Bitumen Applying 170 (3) 17:00 Mr. Khalid
8 Backfilling 170 (2 & 4) 8:00 In Progress
9 Row for Tower and Access Road 173 & 175
10 T & P Inspection of Crew-III With NESPAK
11 Access Road inspection with NESPAK
12 Numeration of Trees
13 Foundation Layout with NESPAK
Today’s Progress:
1. Tower Staking Completed with NESPAK:
Tower # 141 to 145, 153 & 153-A.
2. Preparation for Concrete Complted:
Tower # 38 (4).
3.Form Work Opening & Bitumen Applied:
Tower # 45 (4) & 89 (2).
4. Access Road Construction Completed:
Tower # 118.
5. Excavation Completed:
Tower # 90 (3) & 101-A (1).
6. Concrete Completed:
Tower # 89 (1) & 170 (3).
7. Cylinder Testing Completed:
Tower # 73 (2 & 3).
8. Steel Sample Collection completed in the presence of NESPAK at Section-I.
9. T & P Inspection Completed in the presence of NESPAK for Crew No. 03 (Section-III).
10. Access Road Construction:
Tower # 9,34,35/36,40,44, 116/117 & 121 (In progress).
11.Excavation Work Pending subject to NOC regarding Pine Trees.
Tower # 98,99,102,103,105.
12. Access Road Construction Pending due to pine trees:
Tower # 74 to 85,92 to 97,100,101,106,107.
13. Enumeration of Trees Completed with NTDC and Forest Departmnet:
Tower # 126 to 127.
14. Row at Tower Location & Access Road:
Tower # 7 t0 11, 40, 41 to 43, 50/51 to 54,56, 173 & 175.

Site Manager NEPCII


Mr. Muhammad Ashraf Bhatti