Daily Activity Plan and Progress
Daily Activity Plan and Progress
Daily Activity Plan and Progress
PROCUREMENT OF PLANT, DESIGN, MANUFACTURING, SUPPLY, INSTALLATION, TESTING & COMMISSIONING OF 500KV DOUBLE CIRCUIT QUAD BUNDLE T/LINE FROM SUKI KINARI HYDRO POWER STATION TO INTERCONNECTION
POINT OF EXISTING NEELUM JHELUM 500KV DOUBLE CIRCUIT
DAILY ACTIVITY PLAN AND PROGRESS
Date of Submission : 29-09-2021 Date of Activity : 30-09-2021
Attention: NESPAK Site Office Garhi Habibullah
Section # 1 : Tower # 1-73
Assigned Duty Engr.
Assigned Duty Engr. Name (NEPC II Assigned Duty Engr. Assigned Duty Engr.
Sr.No Activity Tower # TIME REMARKS
Name (NEPC-II) Constrcution Team & Name (NESPAK) Name (NTDC)
CPM)
1 Survey for Tower Staking
2 Tower Staking with NESPAK
Mr. Athar
Mr. Sajjad
3 Access Road Construction 9,34,35/36,40,44 8:00 Mr. Shaheer Mr. Adnan In Progress
Mr. Bilal
Mr. Mehfooz
4 Excavation 38 (1), 47 (3) & 48 (1, 4) 8:00 Mr. Adnan Mr. Ajmal In Progress
5 preparation for Concrete 45 (2) 8:00 Mr. Ashfaq In Progress
6 Concrete 38 (4) 11:00 Mr. Talha Ishtiaq Mr. Ajmal
7 Form work Opening & Bitumen Applying
8 Backfilling 45 (4) 8:00 Mr. Arshad
9 Layout
10 Steel Sample Collection with NESPAK
Cylinder Testing
11 Enumeration of Trees 19-A to Onwards 8:00 Mr. Ameer Abbas
7 to 11, 40, 41 to 43 &
12 Row Clearence for Access Road 9:00 Mr. Abbas
50/51 to 54,56
Section # 2 : Tower # 74-147
Assigned Duty Engr. Assigned Duty Engr. Assigned Duty Engr. Assigned Duty Engr.
Sr.No Activity Tower # TIME REMARKS
Name (NEPC-II) Name (NHC) Name (NESPAK) Name (NTDC)
1 Survey for Tower Staking
2 Tower Staking with NESPAK 146 to 148 11:00 Mr. Izharulhaq