Professional Documents
Culture Documents
1994 - Avise Tunnel Revisited
1994 - Avise Tunnel Revisited
A. Da Via,
Tomo, Milan, Italy
S.Pelizza
Politecnico of Turin, Italy
ABSTRACT: A comparison between the choice of "a pilot bore plus enlargement and a full face bore" using
TBM was discussed previously by the authors for the case of the 3 km-long, twin-bore Avise tunnel. The Avise
tunnel is now revisited for information on the performance of the TBM reaming machine from 4.5 m pilot hole
to 11.4 m fmal (right) bore compared with the drill and blast excavation of part of the left bore and drill and blast
enlargement of the remainder of the left bore.
1.1 Project Description The Avise tunnel traverses the S. Bemardo formation,
mainly consituted by intensely fractured and faulted
The Avise Tunnel is one of the 10 tunnels along the gneiss and micaschist with intercalations of chlorite
section of the Italian motorway AS that connects the and phyllite. Except for the portal sections, which are
town of Aosta (100 km N of Turin) to the French constituted by detritus or moraines under a cover upto
border through the Monte Bianco Tunnel. The twin 40m, the 2.7 km long section through rock is under a
bore Avise tunnel is 3 km long and lies under a cover cover of 180-330m.
of 40 to 330m. The two bores are separated by 1Om, The principal source of the geological information
each has a diameter of 11.4 and will house 2 traffic is the 4.5m diameter pilot bore. This information was
lanes. coupled with some seismic measurements in the field
The construction of Avise tunnel was begun in late and mechanical property tests in the laboratory. For
1989 and is expected to be completed in early 1994. example, the geomechanical properties of the gneiss
The owner of the motorway is RAV of Rome; the were obtained from one series of tests as follows:
Contractor is a consortium of Tomo (Milan) and Density: 2.7 kg/cm3
Fioroni (Perugia), assisted by Geodata as engineering Unconfined compressive strength Co: 80MPa
consultant, Murer Italia as tunnel boring contractor, Brazilian tensile strength: 9 MPa
and Consonda as consolidation contractor. Youngs modulus: 10-17 GPa
The tunnel provides an interesting opportunity to Comp. wave velocity: 4452 m/s
compare the following situations (see Fig. 1.1) which A longitudinal section through the tunnel is given
are discussed in Sec. 2: in Fig. 1.2. The most significant and, by experience,
(1) pilot bore plus TBM enlargement (TBE) vs. drill the most critical geologic feature encountered during
and blastexcavation (DBExc) of theentire section excavation was the Vertosan fault. The fault is located
(without a pilot bore), about half way through the tunnel and is associated
(2) TBE vs. drill and blast enlargement (DBEnl) after with a 60m wide fault zone. The negative influence of
a pilot bore, and tre Vertosan fault on rock quality and advance rate (by
(3) the expected vs. actual performance of the TBE. TBM or drill and blast excavation) is discussed in
The third situation, the performance of TBE, is a Sec.2.
follow-up on the previous article about Avise tunnel The RMR and classification system of Bieniawski
(Da Via et al., 1992) and has provided the title of this (1979) is used for comparing the advance rate between
paper. the various excavation schemes. For convenience,
Artificial Artificial
tunnel Detritic material tunnel
2.7km
LEFT BORE
RIGHT BORE
Fig. 1.1 Plan view of 2 bores of Avise Tunnel showin the excavation scheme:
1 Left pilot bore, 1.5km, from Aosta (AO) toward Monte Bianco (M.B.); 2 Right pilot bore, 2.7km AO toward M.B.; 3 TBE, 2.7km M.B. to AO; 4 D&B
from M.B. to AO
1200
1100
900
700
os 10 15 20 25
0
600
LEGEND
Longitudinal section
2. EXCAVATION METHODOLOGY Depth
of round
(a)
2.1.2 TBM enlargement ofpilot hole (TBE)
Table 2.3 Type of support used in the DBExc sec tion of left bore
E
"'
,...:
E
CX)
TBE bore=86m2
2.3 Cross-section of Avise tunnel showing the drill-and-blast excavation (Left Bore) and TBE (Right Bore)
The left bore of the tunnel had been explored by a 4.5m 3. COMPARATIVE ANALYSIS
diameter pilot hole for about half of its length (see Fig.
1.1) from AO portal to the Vertosan fault This section 3.1 TBE v�rsus DBExc
was enlarged using drill and blast excavation (DBEnl)
As mentionedearlier,the approximately 1340m section
advancing both from the Vertosan fault and AOportal.
of the tunnel between the M.B. portal and V ertosan
The remaining section was excavated by drill and
fault was excavated usign TBE (in the right bore) and
blast (DBExc) proceeding from M.B. Portal toVertosan
DBExc (in the left bore). The daily advance rates for
fault.
the two operations are given in Figs. 3.1 and 3.2,
respectively. The advance as function of rock class is
2.2.1. Drill & blast excavation (DBExc) given in Table 3 .1 for this (M.B.) section of the tunnel.
The TBE advance from M.B. portal to Vertosan
Drill and blast excavation (DBExc) was used to fault(1336m) was made in 181 days using 1 shift for
excavate 13 43 m of the left bore at an average advance 62 days, 2 shifts for 20 days, and 3 shifts for 99 days.
rate of 5.4m/day. Controlled excavation was made to The average advance of7.3 8m/d was influenced by
avoid any damage to the rock around the right bore. organizational factors (machine operation, services,
Two-step excavation was used (with heading and personnel). Almost 50% of the total period was used
benching, see Fig. 2.2), limiting the advance per for bringing the job site operations to an optimum
blasting round to 2.0m for controlling the peak particle level. Note, however, that the average rate achieved
velocity. The support provided was a function of the here falls within the range of experience of large
rock class as shown in Table 2.3. The bolts are 24mm TBM's (Kovari et al., 1993).
diameter, 4.5m, injection-grouted steel or friction The DBExc advance in the 1343m of the M.B.
bolts. The final lining of cast concrete varied in section reached an average of 5.4 m/d over a period of
thickness from 50cm to 60cm. The DBExc cycle is 249 days. The lower advance (compared to TBE)
given in Table 2.4. reflects the effect of controlled blasting to minimize
the damage to the already excavated right bore, that
was separated by a lOm-wide pillar. It can be assumed
2.2.2 Pilot lwle and drill & blast enlargement(DBEnl)
that, in the absence of controlled blasting, the advance
As shown in Fig. 1.1, the 4.5m diameter pilot hole was rate will increase, but with the probable increase of
made at the center of the left bore from AO portal to overbreak of the tunnel section by a % that is
the Vertosan fault for about 1340m. The rock mass significantly more than the present 3.5 to 4%.
classification and support requirements were similar
to those observed in the parallel pilot hole in the right
bore. The DBEnl was made from two faces (Fig. 1.1)
with support provided in a manner similar to that given
-,------
so
! I !
i I
; ---
!
i !
I i
45
i i
I
i I I
i
I
I
40
! I
l
35
"0
E.30 -
(!)
(ii
�
0
25
c
�20
"0
<
15
11111
10
5
11 I I
0
Ill 11 il 11 I 111••1 lit 11 Ill 11
�
5i
0
Fig. 2.4 Daily advance of the 4.5m diameter TBM in the pilot hole for the entire length of the right
bore
Table 3.1 Rock class and advance rates in the section of Avise tunnel from M.B. portal to Vertosan
fault using DBExc (left bore) and TBE (right bore).
Va 3.5 2.7 0 -
Table 3.2 Reduction in advance rate as a function of decreasing rock quality, assuming 100%
advance for class lli.
Ill 0 0
IVa 9 19
IVb 30 62
Va 55 88
Advance rate, mid Advance rate, mid
.. w ..
0 0\ 0 u; � � l5 � I> "' � 0 "' 0 u; � � l5 "' I> "' �
'"T1
..... .
C:OQ
;-o::n
- · 10102192 07/01192
....... �
V.>
V.>
iv ...... 21/01192
24102192
0 0
e:. 04102/92
- e:.
'<
09/03192 -
'<
P' 18102/92
0.. P'
< 26103192 0..
P' < 03/03192
::l P'
() ::l
(1) 09/04192 ()
(1) 24/03/92
......
0
....... ......
0
28104192 07/04192
::r
(1) @ 24/04192
0 13/05/92 .trl
Re
11/05192
.td ...,
0'
05106/92
=- g.
(1) 20/07192
P'
(1)
0.. 3/06192 -i
::i 2 03/08192
::l
..... . g 3'
(IQ 3
('!)
(1) ('!) 09/07192
-
�·
>< - "(;' 11/09192
() ('!)
><
::l
(1)
(IQ
><
2. 23107192 g. 26/09192
P' c
�
9- a.
:::l 12/10192
a. a.
::l 28108/92 ......
0
lO
0 tE
...... 9-
::l :::r 18101/93
(1) Q:
14/09/92
� ;:l.
�
� a. (IQ 13/02193
Q) ::r
fr
0" ..... <
29/09
/92 (/l
0 -
'U'i I 0" - 26102193
@ 0
14/10192 @
12/03/93
a
28/10/92 06/05/93
9
-T I
�
b;J 11/11/92
---= I I I I 20/05193
03/06/93
'"Cl
0 I I I I I I I I
25/11192
§. I I I I I I I I I 17106/93
.....
0 12/01/93
I I I I I I I I I 02/07/93
<
..., 26101/93
(1)
8 I I I I I I 19/07193
(/)
09/02193 02108193
§
02/09/93
ilf? I I I I I I I I
....
23102/93
3.2 TEE versus DBEnl TBErequires a stable pilot hole and good anchoring
capacity of the ground. In poor ground (rock class V),
The comparison between the enlargement of the pilot the grippers may not be properly anchored. As a result,
hole by the reaming machine (TBE) and by the the pistons, instead of pulling the head forward, can
conventional means (DBEnl) refers to the AO-section pull the ground into the pilot hole
of the tunnel, from Vertosan fault to AO portal.
The TBE advance in the AO-section averaged
13.2m/d, over a period of 85 days and peaked at 4. CONCLUSION
AKNOWLEDGMENT
3.3 Expected vs. Actual Performance ofTBE