Date: 3/6/2014 Requirements RAS ETA ELABORACION

Sub-Area (IC) (RS) Supply strategy GESTION DE COMPRA


Review: 01 Engineering Date Date DE RI
FECHA
DURACION HITO FECHA
PROYECTADA
A.005 V-Notch Weir Fiberglass 9''x1/4'' Pump Station- Headworks PS-HD AB96-00-S-RI-0002 8/18/2014 8/3/2014 Low low not critical 45 5/27/2014 4/12/2014
A.006 V-Notch Weir Fiberglass 9''x1/4'' PTAR PTAR AB96-03-S-RI-0302 8/27/2014 8/2/2014 Low low not critical 45 5/27/2014 4/12/2014
A.007 Decking 38 MM Deep x 1.22 MM Core Thickness (16 Ga) Stickbuilt Pump Station- Headwork PS-HD AB96-00-S-RI-0001 8/18/2014 8/7/2014 High low Laverage 30 5/17/2014 4/17/2014
A.008 Decking 38 MM Deep x 1.22 MM Core Thickness (16 Ga) Stickbuilt PTAR PTAR AB96-03-S-RI-0301 8/27/2014 8/7/2014 High low Laverage 30 5/17/2014 4/17/2014
A.009 Structural Steel XX Heavy 181 To 360 kg/m Primed w/ Paint, Field Pump Station- Headworks PS-HD AB96-00-S-RI-0001 8/18/2014 8/3/2014 Low low not critical 40 5/25/2014 4/15/2014
A.010 Structural Steel XX Heavy 181 To 360 kg/m Primed w/ Paint, Field PTAR PTAR AB96-03-S-RI-0301 8/27/2014 8/13/2014 Low low not critical 40 5/25/2014 4/15/2014
A.011 Stairs, Primed w/ Paint, Shop Pump Station- Headworks PS-HD AB96-00-S-RI-0001 7/22/2014 7/7/2014 Low low not critical 30 5/16/2014 4/16/2014
A.012 Stairs, Primed w/ Paint, Shop PTAR PTAR AB96-03-S-RI-0301 1/17/2015 12/5/2014 Low low not critical 30 10/15/2014 9/15/2014
A.013 Ladders w/o Cage, Alum Pump Station- Headworks PS-HD AB96-00-S-RI-0001 7/22/2014 7/2/2014 Low low not critical 30 5/12/2014 4/12/2014
A.014 Ladders w/o Cage, Alum PTAR PTAR AB96-03-S-RI-0301 7/9/2014 6/24/2014 Low low not critical 40 5/12/2014 4/2/2014
A.015 Ladders w/ Cage, Galv. Pump Station- Headworks PS-HD AB96-00-S-RI-0001 7/22/2014 7/2/2014 Low low not critical 30 5/12/2014 4/12/2014
A.016 Ladders w/ Cage, Galv. PTAR PTAR AB96-03-S-RI-0301 7/9/2014 6/24/2014 Low low not critical 40 5/12/2014 4/2/2014
A.017 Ladders w/ Cage, StailessSteel Pump Station- Headworks PS-HD AB96-00-S-RI-0001 7/22/2014 7/4/2014 Low low not critical 30 5/17/2014 4/17/2014
A.018 Ladders w/ Cage, StailessSteel PTAR PTAR AB96-03-S-RI-0301 7/9/2014 6/24/2014 Low low not critical 40 5/12/2014 4/2/2014
A.019 Grating 2-3/4” x 3/8” 230.3 kg/m2 Primed w/o Top Coat Plain Pump Station- Headworks PS-HD AB96-00-S-RI-0001 7/3/2014 6/23/2014 Low low not critical 30 5/19/2014 4/19/2014
A.020 Grating 2-3/4” x 3/8” 230.3 kg/m2 Primed w/o Top Coat Plain PTAR PTAR AB96-03-S-RI-0301 7/21/2014 7/3/2014 Low low not critical 30 5/19/2014 4/19/2014
A.021 Covered Fiberglass Grating 1 1/2'' (incl. cheque plate cover) Pump Station- Headworks PS-HD AB96-00-S-RI-0002 7/3/2014 6/26/2014 Low low not critical 30 5/22/2014 4/22/2014
A.022 Covered Fiberglass Grating 1 1/2'' (incl. cheque plate cover) PTAR PTAR AB96-03-S-RI-0302 7/21/2014 7/3/2014 Low low not critical 30 5/29/2014 4/29/2014
A.023 Covered Fiberglass Grating 2'' Pump Station- Headworks PS-HD AB96-00-S-RI-0002 7/3/2014 6/26/2014 Low low not critical 30 5/22/2014 4/22/2014
A.024 Covered Fiberglass Grating 2'' PTAR PTAR AB96-03-S-RI-0302 7/21/2014 7/3/2014 Low low not critical 30 5/29/2014 4/29/2014
A.025 Covered Fiberglass Grating 2 1/2'' Pump Station- Headworks PS-HD AB96-00-S-RI-0002 7/3/2014 6/26/2014 Low low not critical 30 5/22/2014 4/22/2014
A.026 Covered Fiberglass Grating 2 1/2'' PTAR PTAR AB96-03-S-RI-0302 7/21/2014 7/3/2014 Low low not critical 30 5/29/2014 4/29/2014
A.027 Alum Floor Grating, 2" Pump Station- Headworks PS-HD AB96-00-S-RI-0001 7/22/2014 7/19/2014 High low Laverage 40 5/25/2014 4/15/2014
A.028 Alum Floor Grating, 2" PTAR PTAR AB96-03-S-RI-0301 8/27/2014 8/12/2014 High low Laverage 30 6/12/2014 5/13/2014
A.029 Alum Floor Grating, 1.5" Pump Station- Headworks PS-HD AB96-00-S-RI-0001 8/18/2014 8/5/2014 Low low not critical 30 6/5/2014 5/6/2014
A.030 Alum Floor Grating, 1.5" PTAR PTAR AB96-03-S-RI-0301 8/27/2014 8/12/2014 Low low not critical 40 6/7/2014 4/28/2014
A.031 Metal Stair Tread Grating .28m x1.07m Pump Station- Headworks PS-HD AB96-00-S-RI-0001 8/18/2014 8/3/2014 Low low not critical 50 6/22/2014 5/3/2014
A.032 Metal Stair Tread Grating .28m x1.07m PTAR PTAR AB96-03-S-RI-0301 8/27/2014 8/12/2014 Low low not critical 45 6/28/2014 5/14/2014
A.033 Stainless Steel Pump Station- Headworks PS-HD AB96-00-S-RI-0003 9/13/2014 8/29/2014 Low low not critical 45 6/20/2014 5/6/2014
A.034 Stainless Steel PTAR PTAR AB96-03-S-RI-0303 7/9/2014 7/4/2014 Low low not critical 45 5/25/2014 4/10/2014
A.035 Structural Steel Light 30 kg/m And Less Primed w/ Paint, Field Pump Station- Headworks PS AB96-01-S-RI-0101 9/13/2014 8/14/2014 High low Laverage 52 A 5/23/2014 4/1/2014
A.036 Structural Steel Light 30 kg/m And Less Primed w/ Paint, Field PTAR PTAR AB96-03-S-RI-0301 7/9/2014 6/25/2014 High low Laverage 29 A 5/6/2014 4/7/2014
A.037 Structural Steel Light 30 kg/m And Less, Galv. Pump Station- Headworks PS-HD AB96-00-S-RI-0001 6/14/2014 6/11/2014 Low Low not critical 40 4/27/2014 3/18/2014
A.038 Structural Steel Light 30 kg/m And Less, Galv. PTAR PTAR AB96-03-S-RI-0301 7/9/2014 6/24/2014 Low Low not critical 28 A 5/5/2014 4/7/2014
A.039 Structural Steel Medium 31 To 60 kg/m Primed w/ Paint, Field Pump Station- Headworks PS AB96-01-S-RI-0101 6/14/2014 6/11/2014 High low Laverage 26 A 4/27/2014 4/1/2014
A.040 Structural Steel Medium 31 To 60 kg/m Primed w/ Paint, Field PTAR PTAR AB96-03-S-RI-0301 7/9/2014 6/24/2014 High low Laverage 28 A 5/5/2014 4/7/2014
A.041 Structural Steel Medium 31 to 60 kg/m, Galv Pump Station- Headworks PS-HD AB96-00-S-RI-0001 6/14/2014 6/11/2014 Low Low not critical 35 4/22/2014 3/18/2014
A.042 Structural Steel Medium 31 to 60 kg/m, Galv PTAR PTAR AB96-03-S-RI-0301 7/9/2014 6/19/2014 Low Low not critical 19 A 4/26/2014 4/7/2014
A.043 Structural Steel Miscellaneous Primed w/ Paint, Field Pump Station- Headworks PS AB96-01-S-RI-0101 6/14/2014 6/11/2014 Low Low not critical 21 A 4/22/2014 4/1/2014
A.044 Structural Steel Miscellaneous Primed w/ Paint, Field PTAR PTAR AB96-03-S-RI-0301 7/9/2014 6/19/2014 Low Low not critical 19 A 4/26/2014 4/7/2014
A.045 Structural Steel Heavy 61 To 90 kg/m Primed w/ Paint, Field Pump Station- Headworks PS AB96-01-S-RI-0101 6/14/2014 6/11/2014 High low Laverage 21 A 4/22/2014 4/1/2014
A.046 Structural Steel Heavy 61 To 90 kg/m Primed w/ Paint, Field PTAR PTAR AB96-03-S-RI-0301 7/9/2014 6/19/2014 High low Laverage 19 A 4/26/2014 4/7/2014
A.047 Aluminium Cheque Plate 3/8" w/ Stiffener Pump Station- Headworks PS-HD AB96-00-S-RI-0001 6/14/2014 6/11/2014 Low low not critical 35 4/22/2014 3/18/2014
A.048 Aluminium Cheque Plate 3/8" w/ Stiffener PTAR PTAR AB96-03-S-RI-0301 8/27/2014 8/12/2014 Low low not critical 40 6/8/2014 4/29/2014
A.049 Aluminium Cheque Plate 1/4" w/ Stiffener Pump Station- Headworks PS-HD AB96-00-S-RI-0001 8/18/2014 8/3/2014 Low low not critical 40 5/24/2014 4/14/2014
A.050 Aluminium Cheque Plate 1/4" w/ Stiffener PTAR PTAR AB96-03-S-RI-0301 8/27/2014 8/12/2014 Low low not critical 40 6/8/2014 4/29/2014
A.051 Aluminium Platform 16'x4'x4' High Pump Station- Headworks PS-HD AB96-00-S-RI-0001 8/18/2014 8/3/2014 High low Laverage 40 5/24/2014 4/14/2014
A.052 Aluminium Platform 16'x4'x4' High PTAR PTAR AB96-03-S-RI-0301 8/27/2014 8/12/2014 High low Laverage 40 6/8/2014 4/29/2014
A.053 Structural Steel Pipe / Electrical Racks Light 30 kg/m And Less Primed w/ Paint, Shop Pump PS-HD AB96-00-S-RI-0004 7/25/2014 7/23/2014 Low Low not critical 40 5/19/2014 4/9/2014
A.054 Structural Steel Pipe / Electrical Racks Light 30 kg/m And Less Primed w/ Paint, Shop PTAR PTAR AB96-03-S-RI-0304 8/6/2014 7/29/2014 Low Low not critical 40 5/25/2014 4/15/2014
A.055 Structural Steel Pipe / Electrical Racks Medium 31 To 60 kg/m Primed w/ Paint, Shop Pump PS-HD AB96-00-S-RI-0004 7/25/2014 7/23/2014 Low Low not critical 40 5/19/2014 4/9/2014
A.056 Structural Steel Pipe / Electrical Racks Medium 31 To 60 kg/m Primed w/ Paint, Shop PTAR PTAR AB96-03-S-RI-0304 8/6/2014 7/29/2014 Low Low not critical 40 5/25/2014 4/15/2014
A.057 Structural Steel Pipe / Electrical Racks Heavy 61 To 90 kg/m Primed w/ Paint, Shop Pump S PS-HD AB96-00-S-RI-0004 7/25/2014 7/23/2014 Low Low not critical 40 5/19/2014 4/9/2014
A.058 Structural Steel Pipe / Electrical Racks Heavy 61 To 90 kg/m Primed w/ Paint, Shop PTAR PTAR AB96-03-S-RI-0304 8/6/2014 7/29/2014 Low Low not critical 40 5/25/2014 4/15/2014
A.059 Structural Steel Pipe / Electrical Racks Miscellaneous Primed w/ Paint, Shop Pump Station- PS-HD AB96-00-S-RI-0004 7/25/2014 7/23/2014 Low Low not critical 40 5/19/2014 4/9/2014
A.060 Structural Steel Pipe / Electrical Racks Miscellaneous Primed w/ Paint, Shop PTAR PTAR AB96-03-S-RI-0304 8/6/2014 7/29/2014 Low Low not critical 40 5/25/2014 4/15/2014
A.061 Structural Steel Light 30 kg/m And Less Primed w/ Paint, Shop Pump Station- Headworks PS AB96-01-S-RI-0101 6/27/2014 6/25/2014 Low Low not critical 20 A 4/21/2014 4/1/2014
A.062 Structural Steel Light 30 kg/m And Less Primed w/ Paint, Shop PTAR PTAR AB96-03-S-RI-0301 7/9/2014 7/2/2014 Low Low not critical 21 A 4/28/2014 4/7/2014
A.063 Structural Steel Medium 31 To 60 kg/m Primed w/ Paint, Shop Pump Station- Headworks PS AB96-01-S-RI-0101 6/27/2014 6/25/2014 Low Low not critical 20 A 4/21/2014 4/1/2014
A.064 Structural Steel Medium 31 To 60 kg/m Primed w/ Paint, Shop PTAR PTAR AB96-03-S-RI-0301 7/9/2014 7/2/2014 Low Low not critical 21 A 4/28/2014 4/7/2014
A.065 Thermic Wall Panels ( Panels CCA-POL 50) PS-HD AB96-00-S-RI-0005 9/19/2014 9/4/2014 Low Low not critical 45 7/15/2014 5/31/2014
A.066 Roof Panels ( TCA-POL 50) PS-HD AB96-00-S-RI-0005 9/19/2014 9/5/2014 Low low not critical 45 6/22/2014 5/8/2014
A.067 Canal alum C8x6.48x8.2 Pump Station- Headworks PS-HD AB96-00-S-RI-0001 8/18/2014 8/8/2014 Low low not critical 40 5/25/2014 4/15/2014
A.068 Canal alum C8x6.48x8.2 PTAR PTAR AB96-03-S-RI-0301 8/27/2014 8/15/2014 Low low not critical 40 6/1/2014 4/22/2014
A.069 FRP Baffle Panels Pump Station- Headworks PS-HD AB96-00-S-RI-0002 8/18/2014 8/12/2014 High High Strategy 40 5/24/2014 4/14/2014
A.070 FRP Baffle Panels PTAR PTAR AB96-03-S-RI-0302 8/27/2014 8/12/2014 High High Strategy 40 5/24/2014 4/14/2014
A.071 Aluminium Cheque Plate 1/2" w/ Stiffener Pump Station- Headworks PS-HD AB96-00-S-RI-0001 8/18/2014 8/9/2014 Low low not critical 30 5/31/2014 5/1/2014
A.072 Aluminium Cheque Plate 1/2" w/ Stiffener PTAR PTAR AB96-03-S-RI-0301 8/27/2014 8/12/2014 Low low not critical 30 6/3/2014 5/4/2014
A.073 Cladding / Roofing - Standing Seam .8 mm Al w/Kynar Pump Station- Headworks PS-HD AB96-00-S-RI-0001 9/19/2014 9/4/2014 Low low not critical 40 5/30/2014 4/20/2014
A.074 Cladding / Roofing - Standing Seam .8 mm Al w/Kynar PTAR PTAR AB96-03-S-RI-0301 11/12/2014 11/6/2014 Low low not critical 40 8/13/2014 7/4/2014
B.002 Ductil iron Piping and fittings K9 (2do MTO) HD-PTAR AB96-00-P-RI-0010 7/24/2014 7/24/2014 High High Strategy 4 D 3/14/2014 3/10/2014
B.004 Welded pipe and fittings AWWA (2do MTO) HD-PTAR AB96-00-P-RI-0003 7/24/2014 7/24/2014 High High Strategy 85 D 3/14/2014 12/19/2013
B.005 HDPE piping and fittings HD-PTAR AB96-00-P-RI-0005 6/15/2014 6/15/2014 High low Laverage 12 C 4/16/2014 4/4/2014
B.006 Stainless steel piping and fittings HD-PTAR AB96-00-P-RI-0006 7/15/2014 7/5/2014 Low Low not critical 44 B 4/24/2014 3/11/2014
B.007 Piping spool fabrication Stainless steel Pump Station PS AB96-01-P-RI-0108 6/11/2014 6/11/2014 Low High Bottlenecks 35 A 5/7/2014 4/2/2014
B.008 Piping spool fabrication Stainless steel Headwork y PTAR HD-PTAR AB96-00-P-RI-0020 7/15/2014 7/9/2014 Low High Bottlenecks 25 6/4/2014 5/10/2014
B.009 PRFV piping and fittings HD-PTAR AB96-00-P-RI-0004 6/25/2014 6/22/2014 Low High Bottlenecks 28 C 4/16/2014 3/12/2014
B.010 Pre-fabrication, installing piping HDPE y PRFV HD-PTAR AB96-00-P-RI-0022 5/30/2014 5/30/2014 Low High Bottlenecks 10 C 4/21/2014 4/11/2014
B.010.1 Installing piping HDPE 32" y 63" HD-PTAR AB96-00-P-RI-0022 5/12/2014 4/16/2014 Low High Bottlenecks 10 D 4/12/2014 4/2/2014
B.011 Carbon steel piping- Fresh Water Pump Station PS AB96-01-P-RI-0101 7/10/2014 6/23/2014 High Low Laverage 42 B 4/28/2014 3/17/2014
B.012 Fittings- Fresh Water Pump Station PS AB96-01-P-RI-0102 7/10/2014 6/23/2014 High Low Laverage 38 B 4/28/2014 3/21/2014
B.013 Flange- Fresh Water Pump Station PS AB96-01-P-RI-0103 7/10/2014 6/23/2014 High Low Laverage 24 B 4/28/2014 4/4/2014
B.014 Fabricación de Spools Carbon Steel Pump Station PS AB96-01-P-RI-0107 5/29/2014 5/26/2014 High High Strategy 25 A 4/27/2014 4/2/2014
B.015 Carbon steel piping- Fresh Water Headwork y PTARHeadwork y PTAR HD-PTAR AB96-00-P-RI-0012 7/23/2014 7/13/2014 High Low Laverage 25 6/9/2014 5/15/2014
B.016 Fittings- Fresh Water Headwork y PTAR HD-PTAR AB96-00-P-RI-0013 6/23/2014 6/23/2014 High Low Laverage 25 5/20/2014 4/25/2014
B.017 Flange- Fresh Water Headwork y PTAR HD-PTAR AB96-00-P-RI-0014 6/23/2014 6/23/2014 High Low Laverage 25 5/20/2014 4/25/2014
B.018 Fabricación de Spools Carbon Steel Headwork y PTAR HD-PTAR AB96-00-P-RI-0019 7/30/2014 7/18/2014 High High Strategy 25 6/14/2014 5/20/2014
B.019 Gaskets- Fresh Water Pump Station PS AB96-01-P-RI-0104 7/10/2014 6/1/2014 Low Low not critical 24 B 4/28/2014 4/4/2014
B.020 Bolts- Fresh Water Pump Station PS AB96-01-P-RI-0105 7/10/2014 6/14/2014 Low Low not critical 33 B 5/11/2014 4/8/2014
B.021 Gaskets- Fresh Water Headwork y PTAR HD-PTAR AB96-00-P-RI-0015 6/23/2014 6/18/2014 Low Low not critical 20 5/25/2014 5/5/2014
B.022 Bolts- Fresh Water Headwork y PTAR HD-PTAR AB96-00-P-RI-0016 7/3/2014 6/28/2014 Low Low not critical 25 6/4/2014 5/10/2014
B.023 Painting for pipings and fittings. PS-HD-PTAR AB96-00-P-RI-0023 7/24/2014 7/16/2014 Low Low not critical 20 6/22/2014 6/2/2014
B.024 Gate, ball valve, Check, needle, sealing valves 1/2" - 4" Headwork y PTAR HD-PTAR AB96-00-P-RI-0017 6/23/2014 6/18/2014 High Low Laverage 25 5/25/2014 4/30/2014
B.025 Galvanized steel piping and fittings PS-HD-PTAR AB96-00-P-RI-0009 7/10/2014 6/28/2014 Low High Bottlenecks 30 5/25/2014 4/25/2014
B.026 Water sprayers Welded PS-HD-PTAR AB96-00-P-RI-0022 7/18/2014 7/9/2014 Low Low not critical 25 6/15/2014 5/21/2014
B.027 Water sprayers PS-HD-PTAR AB96-00-P-RI-0022 7/18/2014 7/9/2014 Low Low not critical 25 6/15/2014 5/21/2014
B.028 Pipe Cooper HD-PTAR AB96-00-P-RI-0011 6/23/2014 6/20/2014 Low Low not critical 25 5/27/2014 5/2/2014
B.029 Miscellaneus- Fresh Water Pump Station PS AB96-01-P-RI-0106 7/10/2014 7/5/2014 Low Low not critical 60 A 6/1/2014 4/2/2014
B.030 Miscellaneus- Fresh Water Headwork y PTAR HD-PTAR AB96-00-P-RI-0018 7/23/2014 7/18/2014 Low Low not critical 25 6/24/2014 5/30/2014
B.031 Soportería Metálica Pump Station PS AB96-01-P-RI-0110 6/21/2014 6/19/2014 Low Low not critical 58 A 5/16/2014 3/19/2014
B.032 Soportería Metálica Headwork y PTAR HD-PTAR AB96-00-P-RI-0021 7/30/2014 7/25/2014 Low Low not critical 30 6/21/2014 5/22/2014
B.033 PVC Piping and fittings HD-PTAR AB96-00-P-RI-0008 6/23/2014 5/30/2014 Low Low not critical 41 B 4/16/2014 2/27/2014
B.034 CPVC Piping and fittings HD-PTAR AB96-00-P-RI-0007 6/23/2014 6/7/2014 Low Low not critical 30 A 4/24/2014 3/25/2014
B.035 Suministro e Instalación de Aislaciones Térmicas HD-PTAR AB96-00-P-RI-0024 11/10/2014 10/2/2014 Low Low not critical 45 8/14/2014 6/30/2014
C.001 Equipment Rental Formwork PS-HD-PTAR AB96-00-C-RI-0003 3/14/2014 3/14/2014 High Low Laverage 80 D 3/3/2014 12/13/2013
C.002 Scaffolding Rental PS-HD-PTAR AB96-00-C-RI-0004 3/22/2014 3/19/2014 High Low Laverage 39 D 3/14/2014 2/3/2014
C.003 Grua torre PS-HD-PTAR AB96-00-C-RI-0005 4/23/2014 4/4/2014 High High Strategy 35 D 3/14/2014 2/7/2014
C.004 Laboratorio de Mecanica de Suelos y Concreto PS-HD-PTAR AB96-00-C-RI-0006 4/12/2014 4/12/2014 High Low Laverage 48 D 3/31/2014 2/11/2014
D.001 Recubrimiento de Pintura (Sc Coating System 108) PS-HD-PTAR AB96-00-C-RI-0021 9/20/2014 8/20/2014 High Low Laverage 30 7/16/2014 6/16/2014
D.002 Recubrimiento de Pintura (Sc Coating System 110) PS-HD-PTAR AB96-00-C-RI-0021 9/20/2014 8/20/2014 Low low not critical 30 7/16/2014 6/16/2014
D.003 Recubrimiento de Pintura (Sc Coating System 111) PS-HD-PTAR AB96-00-C-RI-0021 9/20/2014 8/20/2014 Low low not critical 30 7/16/2014 6/16/2014
D.004 Recubrimiento de Pintura (Sc Coating System 11) PS-HD-PTAR AB96-00-C-RI-0021 8/23/2014 8/20/2014 Low low not critical 30 7/16/2014 6/16/2014
D.005 Cercos metalicos PS-HD-PTAR AB96-00-C-RI-0017 9/23/2014 9/11/2014 High Low Laverage 30 6/28/2014 5/29/2014
D.006 Sc Concrete Pumping Service PS-HD-PTAR AB96-00-C-RI-0001 4/15/2014 4/8/2014 High High Strategy 30 D 2/20/2014 1/21/2014
D.007 Sc Readymix Concrete 10Mpa PS-HD-PTAR AB96-00-C-RI-0001 4/15/2014 4/8/2014 High High Strategy 30 D 2/20/2014 1/21/2014
D.008 Sc Readymix Concrete 31 Mpa PS-HD-PTAR AB96-00-C-RI-0001 4/15/2014 4/8/2014 High High Strategy 30 D 2/20/2014 1/21/2014
D.009 Sc Readymix Concrete 28 Mpa PS-HD-PTAR AB96-00-C-RI-0001 4/15/2014 4/8/2014 High High Strategy 30 D 2/20/2014 1/21/2014
D.010 Sc Readymix Concrete 20 Mpa PS-HD-PTAR AB96-00-C-RI-0001 4/15/2014 4/8/2014 High High Strategy 30 D 2/20/2014 1/21/2014
D.011 Sc Readymix Concrete 20 Mpa PS-HD-PTAR AB96-00-C-RI-0001 4/15/2014 4/8/2014 High High Strategy 30 D 2/20/2014 1/21/2014
D.012 Sc Readymix Concrete 28 Mpa PS-HD-PTAR AB96-00-C-RI-0001 4/15/2014 4/8/2014 High High Strategy 30 D 2/20/2014 1/21/2014
D.013 Bollards 200mm PS-HD-PTAR AB96-00-S-RI-0001 7/12/2014 6/25/2014 Low low not critical 30 5/11/2014 4/11/2014
D.014 Door A; N° A 060-A1, A2, B1, B4, B5, C1, C2, D1 Y D2 De 1.00Mx2.20M PS-HD-PTAR AB96-00-C-RI-0018 10/3/2014 9/18/2014 Low low not critical 30 8/4/2014 7/5/2014
D.015 Overhead Coiling Door Del Tipo B PS-HD-PTAR AB96-00-C-RI-0018 11/6/2014 10/3/2014 Low low not critical 30 8/9/2014 7/10/2014
D.016 Sc Louver Tipo L-1 De 2.40Mx1.20M PS-HD-PTAR AB96-00-C-RI-0018 10/3/2014 9/18/2014 Low low not critical 30 8/4/2014 7/5/2014
D.017 Sc Louver Tipo L-2 De 1.40Mx1.40M PS-HD-PTAR AB96-00-C-RI-0018 10/3/2014 9/18/2014 Low low not critical 30 8/4/2014 7/5/2014
D.018 Sc Access Gate 8M Tipo C - 105 PS-HD-PTAR AB96-00-C-RI-0018 10/3/2014 9/18/2014 Low low not critical 30 8/4/2014 7/5/2014
D.019 Sc Door 4M Tipo C - 102 PS-HD-PTAR AB96-00-C-RI-0018 10/3/2014 9/18/2014 Low low not critical 30 8/4/2014 7/5/2014
D.020 Sc Door 1.5M Tipo V - 103 PS-HD-PTAR AB96-00-C-RI-0018 10/3/2014 9/18/2014 Low Low not critical 30 8/4/2014 7/5/2014
D.021 Sc Louver Tipo L-5 De 1.60Mx1.60M PS-HD-PTAR AB96-00-C-RI-0018 10/3/2014 9/18/2014 Low Low not critical 30 8/4/2014 7/5/2014
D.022 Sc Door D; N° 190 - A2 De 2.00Mx2.20M PS-HD-PTAR AB96-00-C-RI-0018 10/3/2014 9/18/2014 Low Low not critical 30 8/4/2014 7/5/2014
D.023 Sc Louver Typo L-3 De 1.20Mx1.20M. PS-HD-PTAR AB96-00-C-RI-0018 10/3/2014 9/18/2014 Low Low not critical 30 8/4/2014 7/5/2014
D.024 Sidewall Panels - Steel, 0.91Mm PS-HD-PTAR AB96-00-S-RI-0005 7/7/2014 6/28/2014 Low Low not critical 30 5/24/2014 4/24/2014
D.025 Custom Counters & Cabinets - Kitchen PS-HD-PTAR AB96-00-S-RI-0001 11/6/2014 10/19/2014 Low Low not critical 30 9/14/2014 8/15/2014
D.026 Restroom - Men'S & Women'S PS-HD-PTAR AB96-00-S-RI-0001 11/6/2014 10/19/2014 Low Low not critical 30 9/14/2014 8/15/2014
D.027 Floor - Vct PS-HD-PTAR AB96-00-C-RI-0019 10/18/2014 9/30/2014 Low Low not critical 30 9/5/2014 8/6/2014
D.028 Floor - Raised Access Flooring PS-HD-PTAR AB96-00-C-RI-0020 10/18/2014 10/3/2014 Low Low not critical 30 9/8/2014 8/9/2014
D.029 Floor - Carpet PS-HD-PTAR AB96-00-C-RI-0019 10/18/2014 10/3/2014 Low Low not critical 30 9/8/2014 8/9/2014
D.030 Floor - Carpet PS-HD-PTAR AB96-00-C-RI-0019 10/18/2014 10/3/2014 Low Low not critical 30 9/8/2014 8/9/2014
D.031 Ceiling - Suspended Acoustical Tile PS-HD-PTAR AB96-00-S-RI-0005 7/7/2014 6/21/2014 Low Low not critical 30 6/1/2014 5/2/2014
D.032 Flashing - Through Wall PS-HD-PTAR AB96-00-S-RI-0005 7/7/2014 6/21/2014 Low Low not critical 30 6/1/2014 5/2/2014
D.033 Warning Sign M-832 PS-HD-PTAR AB96-00-C-RI-0022 11/3/2014 10/19/2014 Low Low not critical 30 9/24/2014 8/25/2014
D.034 Sh-1 Shower PS-HD-PTAR AB96-00-C-RI-0024 11/6/2014 10/19/2014 Low Low not critical 30 9/24/2014 8/25/2014
D.035 Sk-1 Sink PS-HD-PTAR AB96-00-C-RI-0024 11/6/2014 10/19/2014 Low Low not critical 30 9/24/2014 8/25/2014
D.036 Sk-2 Sink PS-HD-PTAR AB96-00-C-RI-0024 11/6/2014 10/19/2014 Low Low not critical 30 9/24/2014 8/25/2014
D.037 Vtr - Pvc Sched 80 (16) - 3" Roof Vent PS-HD-PTAR AB96-00-C-RI-0023 9/18/2014 9/3/2014 Low Low not critical 30 8/14/2014 7/15/2014
D.038 Vtr - Pvc Sched 80 (16) - 4" Roof Vent PS-HD-PTAR AB96-00-C-RI-0023 9/18/2014 9/3/2014 Low Low not critical 30 8/14/2014 7/15/2014
D.039 Wc-1 Tank Type Water Closet PS-HD-PTAR AB96-00-C-RI-0024 9/18/2014 9/3/2014 Low Low not critical 30 8/14/2014 7/15/2014
D.040 Wc-2 Tank Type Water Closet PS-HD-PTAR AB96-00-C-RI-0024 9/18/2014 9/3/2014 Low Low not critical 30 8/14/2014 7/15/2014
D.042 Lav-1 And 2 Lavatory PS-HD-PTAR AB96-00-C-RI-0024 11/6/2014 10/22/2014 Low Low not critical 30 9/22/2014 8/23/2014
D.043 P-900 Domestic Water Service PS-HD-PTAR AB96-00-C-RI-0024 11/6/2014 10/22/2014 Low Low not critical 30 9/22/2014 8/23/2014
D.044 Self Contained Emergency Eyewash/Shower PS-HD-PTAR AB96-00-C-RI-0024 6/7/2014 5/27/2014 Low Low not critical 25 5/12/2014 4/17/2014
D.045 Asphalt PS-HD-PTAR AB96-00-C-RI-0025 2/14/2015 1/30/2015 Low Low not critical 30 1/4/2015 12/5/2014
D.046 Mix Asphalt PS-HD-PTAR AB96-00-C-RI-0025 2/14/2015 1/30/2015 Low Low not critical 30 1/4/2015 12/5/2014
D.047 Rebar Fy = 4200 Kg/Cm2 Grado 60 PS-HD-PTAR AB96-00-C-RI-0002 3/14/2014 3/14/2014 High Low Laverage 70 D 2/20/2014 12/12/2013
D.048 Rebar Fy = 4200 Kg/Cm2 Grado 60 De 5/8" X 9 M PS-HD-PTAR AB96-00-C-RI-0002 3/14/2014 3/14/2014 High Low Laverage 70 D 2/20/2014 12/12/2013
D.049 Rebar Fy = 4200 Kg/Cm2 Grado 60 (Predimensionado) PS-HD-PTAR AB96-00-C-RI-0002 3/14/2014 3/14/2014 High Low Laverage 70 D 2/20/2014 12/12/2013
D.050 Vapor Barrier Stego Wrap 15 Mils PS-HD-PTAR AB96-00-C-RI-0009 4/26/2014 4/26/2014 Low low not critical 23 C 4/14/2014 3/14/2014
D.051 Water Stop 6" Flat Strip PS-HD-PTAR AB96-00-C-RI-0010 4/22/2014 4/22/2014 High Low Laverage 1 D 4/9/2014 4/8/2014
D.052 Water Stop 230Mm With Central Bulb PS-HD-PTAR AB96-00-C-RI-0010 4/22/2014 4/22/2014 Low Low not critical 1 D 4/9/2014 4/8/2014
D.053 Sikagrout 212 (Bag 30 Kg) PS-HD-PTAR AB96-00-C-RI-0014 5/15/2014 5/10/2014 Low Low not critical 60 B 5/5/2014 3/6/2014
D.054 Backer Rod De 1/2" Cja X 762M PS-HD-PTAR AB96-00-C-RI-0014 6/7/2014 5/19/2014 Low Low not critical 69 A 5/14/2014 3/6/2014
D.055 Sikaflex 2C Ns Ez Mix X 600Mm PS-HD-PTAR AB96-00-C-RI-0014 6/7/2014 5/19/2014 Low Low not critical 69 A 5/14/2014 3/6/2014
D.056 Vulkem 227 O Similar X 5Gln PS-HD-PTAR AB96-00-C-RI-0014 6/7/2014 5/19/2014 Low Low not critical 69 A 5/14/2014 3/6/2014
D.057 Rubber Tape PS-HD-PTAR AB96-00-C-RI-0014 6/7/2014 5/28/2014 Low Low not critical 48 A 4/23/2014 3/6/2014
Rubber
D.058 PS-HD-PTAR AB96-00-C-RI-0014 6/7/2014 5/28/2014 Low Low not critical 48 A 4/23/2014 3/6/2014
D.059 Floor Door - Bilco Vault, 3'X3' PS-HD-PTAR AB96-00-C-RI-0018 10/18/2014 10/5/2014 Low Low not critical 30 8/31/2014 8/1/2014
D.060 Floor Door - Bilco Vault, 2.5'X2.5' PS-HD-PTAR AB96-00-C-RI-0018 10/18/2014 10/5/2014 Low Low not critical 30 8/31/2014 8/1/2014
D.061 Floor Door - Bilco Vault, 5'X5' PS-HD-PTAR AB96-00-C-RI-0018 10/18/2014 10/5/2014 Low Low not critical 30 8/31/2014 8/1/2014
D.062 Floor Paint PS-HD-PTAR AB96-00-C-RI-0018 10/18/2014 10/5/2014 Low Low not critical 30 8/31/2014 8/1/2014
D.063 Urinary PS-HD-PTAR AB96-00-C-RI-0016 11/6/2014 10/22/2014 Low Low not critical 35 9/17/2014 8/13/2014
D.064 Flushvalve PS-HD-PTAR AB96-00-C-RI-0016 11/6/2014 10/22/2014 Low Low not critical 35 9/17/2014 8/13/2014
D.065 Filter PS-HD-PTAR AB96-00-C-RI-0016 11/6/2014 10/22/2014 Low Low not critical 35 9/17/2014 8/13/2014
D.066 Waterproofing Layer PS-HD-PTAR AB96-00-C-RI-0018 6/15/2014 5/31/2014 Low Low not critical 30 5/11/2014 4/11/2014
D.067 Wall Isolation PS-HD-PTAR AB96-00-C-RI-0018 6/15/2014 5/31/2014 Low Low not critical 30 5/11/2014 4/11/2014
D.068 Mall Mesh PS-HD-PTAR AB96-00-C-RI-0015 6/15/2014 5/31/2014 Low Low not critical 30 5/11/2014 4/11/2014
D.069 Reinforcement Tape For Joints PS-HD-PTAR AB96-00-C-RI-0014 6/7/2014 5/23/2014 Low Low not critical 58 A 5/3/2014 3/6/2014
D.070 Anchor Bolts Pump Station PS AB96-01-C-RI-0101 4/25/2014 4/7/2014 Low low not critical 1 D 3/18/2014 3/17/2014
D.071 Anchor Bolts HEADWORK y PTAR 1RA PRIORIDAD HD-PTAR AB96-00-C-RI-0007 6/10/2014 5/28/2014 Low Low not critical 30 4/23/2014 3/24/2014
D.072 Anchor Bolts HEADWORK y PTAR 2DA PRIORIDAD HD-PTAR AB96-00-C-RI-0012 7/9/2014 6/24/2014 Low Low not critical 30 5/15/2014 4/15/2014
D.073 Embedments PUMP STATION PS AB96-01-C-RI-0102 4/25/2014 4/17/2014 Low Low not critical 20 D 3/18/2014 2/26/2014
D.074 Embedments HEADWORK y PTAR 1RA PARTE HD-PTAR AB96-00-C-RI-0008 6/10/2014 6/7/2014 Low Low not critical 26 B 4/28/2014 4/2/2014
D.075 Embedments HEADWORK y PTAR 2DA PARTE HD-PTAR AB96-00-C-RI-0013 7/11/2014 6/26/2014 Low Low not critical 48 A 5/20/2014 4/2/2014
D.076 Concrete Blocks (Cmu) 0.20X0.20X0.40M PS-HD-PTAR AB96-00-C-RI-0016 5/13/2014 5/13/2014 Low Low not critical 25 B 4/16/2014 3/19/2014
D.077 Concrete Blocks (Cmu) 0.30X0.20X0.40M PS-HD-PTAR AB96-00-C-RI-0016 5/13/2014 5/13/2014 Low Low not critical 25 B 4/16/2014 3/19/2014
D.078 Concrete Blocks (Cmu) 0.39X0.19X0.09M PS-HD-PTAR AB96-00-C-RI-0016 5/13/2014 5/13/2014 Low Low not critical 25 B 4/16/2014 3/19/2014
D.079 Steel Dowel 13Mm X 1.2M - 1era Parte PS-HD-PTAR AB96-00-C-RI-0011 4/27/2014 4/27/2014 Low Low not critical 15 A 4/14/2014 3/27/2014
D.080 Steel Dowel 13Mm X 1.2M - 2da Parte HD-PTAR AB96-00-C-RI-0026 5/10/2014 5/10/2014 Low Low not critical 20 A 4/20/2014 3/31/2014
D.081 Coiling Gate Type B (3.60X4.50 ) PS-HD-PTAR AB96-00-C-RI-0018 10/3/2014 9/18/2014 Low Low not critical 35 8/14/2014 7/10/2014
D.082 Coiling Gate Type B (4.00X4.00) PS-HD-PTAR AB96-00-C-RI-0018 10/3/2014 9/18/2014 Low Low not critical 35 8/14/2014 7/10/2014
D.083 Coiling Gate Type B (4.20X4.20) PS-HD-PTAR AB96-00-C-RI-0018 10/3/2014 9/18/2014 Low low not critical 35 8/14/2014 7/10/2014
D.084 Acoustics Panels PS-HD-PTAR AB96-00-S-RI-0005 7/7/2014 6/28/2014 Low low not critical 30 5/24/2014 4/24/2014
D.085 Fire Rated Wall, 1 Hour PS-HD-PTAR AB96-00-C-RI-0018 6/7/2014 5/27/2014 Low low not critical 30 5/7/2014 4/7/2014
E.001 Copper EPR/XLP Power Cable 5kV #350 - Pump station PS AB96-01-E-RI-0104 6/26/2014 6/23/2014 High High Strategy 19 A 4/28/2014 4/9/2014
E.002 Copper EPR/XLP Power Cable 5kV #350 - PTAR PTAR AB96-03-E-RI-0304 4/8/2014 4/18/1900 High High Strategy 30 1/29/1900
E.003 #250 - #500 Wire Termination 5KV (32,614 EA) - Pump station PS AB96-01-E-RI-0104 5/19/2014 5/7/2014 Low Low not critical 23 A 5/2/2014 4/9/2014
E.004 #250 - #500 Wire Termination 5KV (32,614 EA) - PTAR PTAR AB96-03-E-RI-0304 4/8/2014 2/3/1900 Low Low not critical 30 1/29/1900
E.005 Copper Wire Bare Stranded (#6 - #4/0) - Pump station/Headworks PS-HD AB96-01-E-RI-0101 5/9/2014 3/28/2014 Low Low not critical 27 D 3/24/2014 2/25/2014
E.006 Copper Wire Bare Stranded (#6 - #4/0) - PTAR PTAR AB96-03-E-RI-0301 4/8/2014 2/3/1900 Low Low not critical 30 1/29/1900
E.007 Copper Wire XHHW Stranded (#1 - #500) - Pump station PS AB96-01-E-RI-0104 6/22/2014 6/19/2014 High Low Laverage 20 A 4/29/2014 4/9/2014
E.008 Copper Wire XHHW Stranded (#1 - #500) - PTAR PTAR AB96-03-E-RI-0304 4/8/2014 5/21/1900 High Low Laverage 60 2/28/1900
E.009 Strand fiber optic cable -Pump station/Headworks PS-HD AB96-01-E-RI-0109 9/11/2014 9/4/2014 High High Strategy 30 8/3/2014 7/4/2014
E.010 Telephone cable- Pump station/Headworks PS-HD AB96-01-E-RI-0109 9/11/2014 8/25/2014 High High Strategy 30 8/3/2014 7/4/2014
E.011 UTP cable- Pump station/Headworks PS-HD AB96-01-E-RI-0109 9/11/2014 9/4/2014 High High Strategy 30 8/3/2014 7/4/2014
E.012 Strand fiber optic cable-PTAR PTAR AB96-03-E-RI-0309 10/2/2014 3/30/1900 High High Strategy 30 1/29/1900
E.013 Telephone cable-PTAR PTAR AB96-03-E-RI-0309 10/2/2014 3/30/1900 High High Strategy 30 1/29/1900
E.014 UTP cable-PTAR PTAR AB96-03-E-RI-0309 10/2/2014 3/30/1900 High High Strategy 30 1/29/1900
E.015 GRC and accessories - Pump station/Headworks PS-HD AB96-01-E-RI-0107 9/16/2014 9/6/2014 High High Strategy 30 6/29/2014 5/30/2014
E.016 GRC and accessories - PTAR PTAR AB96-03-E-RI-0307 9/13/2014 4/19/1900 High High Strategy 30 1/29/1900
E.017 Plastic Coated Rigid Steel Conduit 3/4" - 4" and accessories - Pump station/Headworks PS-HD AB96-01-E-RI-0107 9/16/2014 9/9/2014 High Low Laverage 30 6/29/2014 5/30/2014
E.018 Plastic Coated Rigid Steel Conduit 3/4" - 4" and accessories - PTAR PTAR AB96-03-E-RI-0307 9/13/2014 5/11/1900 High Low Laverage 60 2/28/1900
E.019 Miscelaneous PS-HD-PTAR AB96-00-E-RI-0007 6/18/2014 6/14/2014 High Low Laverage 30 5/28/2014 4/28/2014
E.020 ARC and accessories - Pump station/Headworks PS-HD AB96-01-E-RI-0107 9/24/2014 9/7/2014 Low High Bottlenecks 30 7/14/2014 6/14/2014
E.021 ARC and accessories - PTAR PTAR AB96-03-E-RI-0307 9/13/2014 4/4/1900 Low High Bottlenecks 30 1/29/1900
E.022 Sch 40 PVC Conduit 1" - 4" + acc. - Pump station/Headworks PS-HD AB96-01-E-RI-0106 8/19/2014 8/9/2014 High Low Laverage 30 6/1/2014 5/2/2014
E.023 Sch 40 PVC Conduit 1" - 4" + acc. - PTAR PTAR AB96-03-E-RI-0306 9/13/2014 5/11/1900 High Low Laverage 30 1/29/1900
E.024 Sch 80 PVC Conduit 1" - 3" + acc. - Pump station/Headworks PS-HD AB96-01-E-RI-0106 7/31/2014 7/16/2014 Low Low not critical 30 6/11/2014 5/12/2014
E.025 Sch 80 PVC Conduit 1" - 3" + acc. - PTAR PTAR AB96-03-E-RI-0306 9/13/2014 2/3/1900 Low Low not critical 30 1/29/1900
E.026 Explosion Proof Flexible Conduit- Pump station/Headworks PS-HD AB96-01-E-RI-0108 8/29/2014 8/24/2014 Low High Bottlenecks 30 7/10/2014 6/10/2014
E.027 Explosion Proof Receptacle Feed Through- Pump station/Headworks PS-HD AB96-01-E-RI-0108 8/29/2014 8/24/2014 Low High Bottlenecks 30 7/10/2014 6/10/2014
E.028 Explosion Proof Lever Operated Switch- Pump station/Headworks PS-HD AB96-01-E-RI-0108 8/29/2014 8/24/2014 Low High Bottlenecks 30 7/10/2014 6/10/2014
E.029 Explosion Proof Sealing Cement- Pump station/Headworks PS-HD AB96-01-E-RI-0108 8/29/2014 8/24/2014 Low High Bottlenecks 30 7/10/2014 6/10/2014
E.030 Explosion Proof Sealing Fibre- Pump station/Headworks PS-HD AB96-01-E-RI-0108 8/29/2014 8/24/2014 Low High Bottlenecks 30 7/10/2014 6/10/2014
E.031 Explosion Proof Flexible Conduit- PTAR PTAR AB96-03-E-RI-0308 10/2/2014 4/4/1900 Low High Bottlenecks 30 1/29/1900
E.032 Explosion Proof Receptacle Feed Through- PTAR PTAR AB96-03-E-RI-0308 10/2/2014 4/4/1900 Low High Bottlenecks 30 1/29/1900
E.033 Explosion Proof Lever Operated Switch- PTAR PTAR AB96-03-E-RI-0308 10/2/2014 4/4/1900 Low High Bottlenecks 30 1/29/1900
E.034 Explosion Proof Sealing Cement- PTAR PTAR AB96-03-E-RI-0308 10/2/2014 4/4/1900 Low High Bottlenecks 30 1/29/1900
E.035 Explosion Proof Sealing Fibre- PTAR PTAR AB96-03-E-RI-0308 10/2/2014 4/4/1900 Low High Bottlenecks 30 1/29/1900
E.036 Sealtite Flexible Conduit 3/4" - 3" - Pump station/Headworks PS-HD AB96-01-E-RI-0108 9/8/2014 8/24/2014 Low Low not critical 30 7/20/2014 6/20/2014
E.037 Sealtite Flexible Conduit 3/4" - 3" - PTAR PTAR AB96-03-E-RI-0308 9/13/2014 2/3/1900 Low Low not critical 30 1/29/1900
E.038 Insulated Grounding Metal Bushing PTAR AB96-00-E-RI-0007 7/31/2014 7/16/2014 Low Low not critical 30 6/29/2014 5/30/2014
E.039 Varrilla de cobre Pump station/Headworks PS-HD AB96-01-E-RI-0101 7/22/2014 3/28/2014 Low Low not critical 27 D 3/24/2014 2/25/2014
E.040 Connectors Pump station/Headworks PS-HD AB96-01-E-RI-0101 7/22/2014 3/28/2014 Low Low not critical 27 D 3/24/2014 2/25/2014
E.041 Terminals Pump station/Headworks PS-HD AB96-01-E-RI-0101 7/22/2014 3/28/2014 Low Low not critical 27 D 3/24/2014 2/25/2014
E.042 Welding Pump station/Headworks PS-HD AB96-01-E-RI-0101 7/22/2014 3/28/2014 Low Low not critical 27 D 3/24/2014 2/25/2014
E.043 Varrilla de cobre-PTAR PTAR AB96-03-E-RI-0301 10/2/2014 2/3/1900 Low Low not critical 30 1/29/1900
E.044 Connectors -PTAR PTAR AB96-03-E-RI-0301 10/2/2014 2/3/1900 Low Low not critical 30 1/29/1900
E.045 Terminals -PTAR PTAR AB96-03-E-RI-0301 10/2/2014 2/3/1900 Low Low not critical 30 1/29/1900
E.046 Welding -PTAR PTAR AB96-03-E-RI-0301 10/2/2014 2/3/1900 Low Low not critical 30 1/29/1900
E.047 Cajas de conexiones- Pump station/Headworks PS-HD AB96-01-E-RI-0109 9/28/2014 9/21/2014 Low High Bottlenecks 30 8/17/2014 7/18/2014
E.048 Pulsadores- Pump station/Headworks PS-HD AB96-01-E-RI-0109 9/28/2014 9/21/2014 Low High Bottlenecks 30 8/17/2014 7/18/2014
E.049 Interruptores y tomacorrientes - Pump station/Headworks PS-HD AB96-01-E-RI-0109 9/28/2014 9/21/2014 Low High Bottlenecks 30 8/17/2014 7/18/2014
E.050 Cajas de conexiones-PTAR PTAR AB96-03-E-RI-0309 10/2/2014 4/4/1900 Low High Bottlenecks 30 1/29/1900
E.051 Pulsadores -PTAR PTAR AB96-03-E-RI-0309 10/2/2014 4/4/1900 Low High Bottlenecks 30 1/29/1900
E.052 Interruptores y tomacorrientes -PTAR PTAR AB96-03-E-RI-0309 10/2/2014 2/28/1900 Low High Bottlenecks 30 1/29/1900
E.053 Lighting (556A) - Pump station/Headworks PS-HD AB96-01-E-RI-0105 12/17/2014 12/2/2014 High High Strategy 30 9/21/2014 8/22/2014
E.054 Lighting (556A) - PTAR PTAR AB96-03-E-RI-0305 9/20/2014 4/11/1900 High High Strategy 30 1/29/1900
E.055 Panel Lighting, Power and Instrumentation - Pump station/Headworks PS-HD AB96-01-E-RI-0105 12/17/2014 12/2/2014 High High Strategy 30 9/21/2014 8/22/2014
E.056 Panel Lighting, Power and Instrumentation - PTAR PTAR AB96-03-E-RI-0305 9/20/2014 4/11/1900 High High Strategy 30 1/29/1900
E.057 Conductor ACSR - Pump station/Headworks PS-HD AB96-01-E-RI-0109 12/3/2014 11/18/2014 High High Strategy 30 9/7/2014 8/8/2014
E.058 Soft Drawn Bare Copper - Pump station/Headworks PS-HD AB96-01-E-RI-0109 12/3/2014 11/18/2014 High High Strategy 30 9/7/2014 8/8/2014
E.059 Conductor AAC - Pump station/Headworks PS-HD AB96-01-E-RI-0109 12/3/2014 11/18/2014 High High Strategy 30 9/7/2014 8/8/2014
E.060 Connectors - Pump station/Headworks PS-HD AB96-01-E-RI-0109 12/3/2014 11/18/2014 High High Strategy 30 9/7/2014 8/8/2014
E.061 Terminals - Pump station/Headworks PS-HD AB96-01-E-RI-0109 12/3/2014 11/18/2014 High High Strategy 30 9/7/2014 8/8/2014
E.062 Conductor ACSR- PTAR PTAR AB96-03-E-RI-0309 10/2/2014 4/11/1900 High High Strategy 30 1/29/1900
E.063 Soft Drawn Bare Copper- PTAR PTAR AB96-03-E-RI-0309 10/2/2014 4/11/1900 High High Strategy 30 1/29/1900
E.064 Conductor AAC- PTAR PTAR AB96-03-E-RI-0309 10/2/2014 4/4/1900 High High Strategy 30 1/29/1900
E.065 Connectors- PTAR PTAR AB96-03-E-RI-0309 10/2/2014 4/4/1900 High High Strategy 30 1/29/1900
E.066 Terminals- PTAR PTAR AB96-03-E-RI-0309 10/2/2014 4/4/1900 High High Strategy 30 1/29/1900
E.067 Teck 90, 5 kV, 133 % Insulator level 350MCM - 500MCM - Pump station/Headworks PS-HD AB96-01-E-RI-0103 9/28/2014 9/14/2014 High High Strategy 60 7/4/2014 5/5/2014
E.068 Teck 90, 5 kV, 133 % Insulator level 350MCM - 500MCM - PTAR PTAR AB96-03-E-RI-0303 10/2/2014 4/4/1900 High High Strategy 30 1/29/1900
E.069 Cable Teck 90, 1 kV, 12AWG - 250MCM - Pump station/Headworks PS-HD AB96-01-E-RI-0103 7/22/2014 7/9/2014 Low Low not critical 30 6/4/2014 5/5/2014
E.070 Cable Teck 90, 1 kV, 12AWG - 250MCM - PTAR PTAR AB96-03-E-RI-0303 10/2/2014 2/3/1900 Low Low not critical 30 1/29/1900
E.071 Cable Tray - Pump station/Headworks PS-HD AB96-01-E-RI-0102 7/19/2014 7/4/2014 Low Low not critical 28 6/2/2014 5/5/2014