HM-100C

SYSTEM:___________________

FAT
Version 1.0
19/09/19

RESTRICTION ON USE, DUPLICATION, OR DISCLOSURE OF PROPRIETARY


INFORMATION

This document contains proprietary information, which is the sole property of Sky Sapience Ltd.
The document is submitted to the recipient for his use only. By receiving this document, the
recipient undertakes not to duplicate the document or to disclose in part of, or the whole or any
part of the information contained herein to any third party without receiving before hard, written
permission from Sky Sapience Ltd.

Sky Sapience LTD 2013


Page 2 of 11 OP-FAT-20190919 Confidential
HM-100C FAT Rev 1.0

Sky Sapience LTD Tel: +972-4-9591777


Tavor Building Fax: +972-73 -7051380
Yokneam Hi-Tech Park info@skysapience.com
POB 170, Yokneam www.skysapience.com
2069203
ISRAEL

DOCUMENT VERSION HISTORY

Version Implemented Revision Approved Approval Description


# By Date By Date
1.0 Zvika Yaniv 19/09/19 Ronen Keidar 19/09/19 New Release

 Copyright Sky Sapience Ltd.; All rights reserved.


No part of this publication may be reproduced in any form without prior written consent by Sky Sapience
Ltd.

Disclaimer
Specifications are subjected to change without notice. The warranties under a signed order and
contract will prevail.

Page 2 of 11 SKY SAPIENCE LTD; P.O.B.170 Tavor Building; Yokneam 20692 www.skysapience.com
Page 3 of 11 OP-FAT-20190919 Confidential
HM-100C FAT Rev 1.0

TABLE OF CONTENTS
1 DOCUMENT OVERVIEW .................................................................................................... 4
1.1 SCOPE OF DOCUMENTS ...................................................................................... 4
1.2 GLOSSARY .............................................................................................................. 4
1.2.1 DEFINITION OF TERMS .................................................................................. 4
1.2.2 LIST OF ABBREVIATIONS .............................................................................. 4
2 APPLICABLE DOCUMENTS ............................................................................................... 4
3 TEST PROCEDURE ............................................................................................................... 5
3.1 Preparations ............................................................................................................... 5
3.2 Test Equipment ......................................................................................................... 5
3.3 Test Setup .................................................................................................................. 6
3.3.1 Connections.......................................................................................................... 6
3.4 Environmental Conditions......................................................................................... 6
4 DETAILED TEST RESULTS ................................................................................................ 7
4.1 initial Visual Inspection ............................................................................................ 7
4.2 Visual Inspection At T.O.P ....................................................................................... 7
4.3 System modes, BIT and HMI .................................................................................... 8
4.4 Monitor cameras ........................................................................................................ 8
4.5 UHMI and payload .................................................................................................... 8
4.6 Flight Test ............................................................................................................... 10
4.7 General .................................................................................................................... 10
4.8 ETh port UHMI ....................................................................................................... 10
4.9 System shotdown..................................................................................................... 10
Note: 11

LIST OF TABLES
Table 1 - Definition of Terms ...................................................................................................................... 4
Table 2: List of Abbreviations ..................................................................................................................... 4
Table 3: Test Equipment .............................................................................................................................. 5

LIST OF FIGURES
Figure 1: Test setup Connections ................................................................................................................. 6

Page 3 of 11 SKY SAPIENCE LTD; P.O.B.170 Tavor Building; Yokneam 20692 www.skysapience.com
Page 4 of 11 OP-FAT-20190919 Confidential
HM-100C FAT Rev 1.0

1 DOCUMENT OVERVIEW
1.1 SCOPE OF DOCUMENTS
The document lists the factory acceptance test procedure and results of the HM-100C
system.
The acceptance tests verify that the system works as required and specified.

1.2 GLOSSARY

1.2.1 DEFINITION OF TERMS

Definition of Terms
HM-100C Civilian hovering tethered platform system
developed and produced by Sky Sapience Ltd.

Table 1 - Definition of Terms

1.2.2 LIST OF ABBREVIATIONS

List of Abbreviations
AU Aerial Unit
FAT Factory Acceptence Test
UUT Unit Under Test
GU Ground Unit
UHMI Unified Human-Machine Interface
T.O.P Take-Off Position
PL Payload
E.S. Emergency Switch

Table 2: List of Abbreviations

2 APPLICABLE DOCUMENTS
a. N/A

Page 4 of 11 SKY SAPIENCE LTD; P.O.B.170 Tavor Building; Yokneam 20692 www.skysapience.com
Page 5 of 11 OP-FAT-20190919 Confidential
HM-100C FAT Rev 1.0

3 TEST PROCEDURE
3.1 PREPARATIONS
 Set up the system as illustrated in the test setup below.
 Pay special attention to clearance zone as described in the user manual.
 During flight tests make sure no unauthorized and unprotected personnel are within 100m
radius from the UUT.
 Make sure to operate the UUT and specially the generator at open and ventilated area.
 Operation of the UUT will be performed by trained and qualified personnel.
 Make sure all connectors are connected and tight.
 Test should be conducted in open area away from buildings, trees, power lines, bridges and
other overhead interferences.

3.2 TEST EQUIPMENT


The following table summarizes the test equipment:

Equipment Specification Preciseness Tolerance Remarks

Laptop N\A N\A N\A IP: 10.0.0.99


SN: 255.255.255.0

Table 3: Test Equipment

Page 5 of 11 SKY SAPIENCE LTD; P.O.B.170 Tavor Building; Yokneam 20692 www.skysapience.com
Page 6 of 11 OP-FAT-20190919 Confidential
HM-100C FAT Rev 1.0

3.3 TEST SETUP

3.3.1 Connections

Connect the HM-100C system as describe below:

Figure 1: Test setup Connections

3.4 ENVIRONMENTAL CONDITIONS


Temperature Low: Within system spec.
Temperature High: Within system spec.
Weather: Clear
GU Height AMSL: 0-500m
Wind Limit: Within system spec.
Terrain: Flat and paved

Page 6 of 11 SKY SAPIENCE LTD; P.O.B.170 Tavor Building; Yokneam 20692 www.skysapience.com
Page 7 of 11 OP-FAT-20190919 Confidential
HM-100C FAT Rev 1.0

4 DETAILED TEST RESULTS


Test: FAT
System:____________________
Test Owner: ____________________
Project: _______________________
UUT Configuration:
# Description P\N S\N Remarks
1 Ground Unit
2 Aerial Unit
3 UHMI
4 Generator
5 Payload
6 Autotransformer
7 Emergency Switch
8 Anemometer
Test Date: ______________________
Ambient Temperature: ___________ Average Wind Speed: ____________
GU Height AMSL: ________

4.1 INITIAL VISUAL INSPECTION


Carefully inspect the UUT for visual damage, cracks and loose bolts.
# Item Check Item Pass/Fail Remarks
1 Overall system Visual Damage
2 Ground Unit and generator Visual Damage
station
3 UHMI unit and cables Visual damage

Note: This inspection should be done with system power down

4.2 VISUAL INSPECTION AT T.O.P


Carefully inspect the UUT for visual damage, cracks and loose bolts.
# Item Check Item Pass/Fail Remarks
1 Overall system Visual Damage

3 Rotors Visual damage

4 Main duct assembly Cracks or visual damage

6 Main cable Cracks, bulb effect or visual


damage
7 Landing platform Cracks or visual damage

Page 7 of 11 SKY SAPIENCE LTD; P.O.B.170 Tavor Building; Yokneam 20692 www.skysapience.com
Page 8 of 11 OP-FAT-20190919 Confidential
HM-100C FAT Rev 1.0

# Item Check Item Pass/Fail Remarks


8 Payload Visual damage

9 Payload interface and Visual damage


cable
Note: This inspection should be done with system power down

4.3 SYSTEM MODES, BIT AND HMI


# Item Pass/Fail Remarks
1 Turn the system on step by step up to T.O.P N/A
state:
1.2 “On” state confirmed without Warnings/Errors

1.3 “T.O.P” state confirmed without Warnings/Errors

1.4 “System Ready To Fly” confirmation

2 N/A Can be perforemd as


Turn system off step by step: part of shutdown
procedure
2.1 “On” state confirmed without Warnings/Errors

2.3 Full "Off" executed without Errors

4.4 MONITOR CAMERAS


With system power on check the video from the monitor camera
# Item Pass/Fail Remarks
1 Winch camera

2 Upwords camera

4.5 UHMI AND PAYLOAD (IF APPLICABLE)


These tests should be done at flight as part of the flight tests.
# Item Pass/Fail Remarks
1 Day video
2 Night video
3 Auto Focus operation
4 Zoom operation
5 Pan/Tilt
6 Night/Day mode operation
7 Night Manual Focus operation

Page 8 of 11 SKY SAPIENCE LTD; P.O.B.170 Tavor Building; Yokneam 20692 www.skysapience.com
Page 9 of 11 OP-FAT-20190919 Confidential
HM-100C FAT Rev 1.0

# Item Pass/Fail Remarks


8 Night Zoom operation
9 Night Gain tuning operation
10 Video recording

Notes:
1. Make sure payload 1 is enabled
2. In case no payload is present, 8Kg weight should be used

Page 9 of 11 SKY SAPIENCE LTD; P.O.B.170 Tavor Building; Yokneam 20692 www.skysapience.com
Page 10 of 11 OP-FAT-20190919 Confidential
HM-100C FAT Rev 1.0

4.6 FLIGHT TEST


From T.O.P, hold the height lever "UP" for more than 2sec and keep holding till maximum
height and no lower than 90m.
Let the system fly for 10 minutes minimum
Perform AU offset up to 45 deg
Turn on visual strobes
Keep the system at 15 deg offset
Land the system by holding the height lever till safe landing and motors shot down
# Item Pass/Fail Remarks
1 Test completion

2 Maximum Height (Above 90m – Pass)

3 Flight duration (10 min – Pass)

4 AU offset

5 Visual strobes

6 AU automaticly recovers from manual offset

4.7 GENERAL
After landing perform the following tests:
Download system logs
 Download monitor cameras and payload videos
# Item Pass/Fail Remarks
1 System logs

2 Monitor cameras video

3 Payload video

4.8 ETH PORT UHMI


Connect the laptop to UHMI’s ETH port and ping address 10.0.0.30
# Item Pass/Fail Remarks
1 Ping succesful

Note: Laptop should have ETH adaptor set to IP configuration 10.0.0.99 and subnet set to
255.255.255.0

4.9 SYSTEM SHOTDOWN


Turn main selector all the way to OFF position.
Page 10 of 11 SKY SAPIENCE LTD; P.O.B.170 Tavor Building; Yokneam 20692 www.skysapience.com
Page 11 of 11 OP-FAT-20190919 Confidential
HM-100C FAT Rev 1.0

# Item Pass/Fail Remarks


1 System full shut down with no error messages

NOTE:
Tests 4.5-4.6 can be performed in a single flight per test owner decision.

Test Notes:
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________

Date: ____________ Name: ______________Title:____________Signature:______________