Professional Documents
Culture Documents
Industrial Training Report 1
Industrial Training Report 1
DESIGN AND BUILD OF MASINDI (KISANJA) - PARK JUNCTION AND TANGI JUNCTION - PARAA - BULIISA ROADS
UPGRADING PROJECT (159 KM)
BY
July 2019
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE TO AUGUST 2019
DECLARATION
I, Ssentongo Mansoor, hereby declare that this Report is an authentic record of my industrial
training that I did with Abuljabein Engineering Consulting Office (AECO) as a requirement of a
Bachelor of Science degree in Construction Management from 3rd -June-2019 to 2nd -August-2019,
Makerere University, College of Engineering Design, Art and Technology, under the guidance of
Mr. Lubwama Ibrahim. It has never been presented or submitted in any other university, institution
or an organization and it fully shows the knowledge and skills learnt throughout the training
session.
Signature: …………………………
Date : …………………………
i|Page
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE TO AUGUST 2019
APPROVAL
This is to certify that the bearer, SSENTONGO MANSOOR, carried out his industrial training
with our company fully participating in all the works. Therefore, this serves to approve his
industrial training report for submission to the Department of Construction Economics and
Management under the School of Built Environment, College of Engineering, Design, Art and
Technology, Makerere University.
1. Training Supervisor
Name : ENG. MOSES KISEMBO MUYONJO
Signature: ……………………….
Date : ………………………
2. University Supervisor
Name : MR. LUBWAMA IBRAHIM
Signature: ………………………
Date : ……………………...
ii | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE TO AUGUST 2019
ABSTARCT
The Industrial training was undertaken for the period of two months, from 3rd – June – 2019 to 2nd
– August – 2019 at the Design and Build project of Masindi (Kisanja) – Park Junction and Tangi
Junction – Paraa – Buliisa Roads Upgrading project with Abuljebain Engineering Consulting
Office (AECO).
This report explains the activities that were participated in during the course of the training in
different departments that included Soils, Material and Laboratory, Structures Construction,
Earthworks and Pavement Layers Construction, Surveying, Highway Design and Measurements,
Project Management and Planning and lastly Environmental, Social, Healthy and Safety. This
report shows the challenges that were faced during the training and the proposed recommendations
to overcome these challenges.
iii | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE TO AUGUST 2019
ACKNOWLEDGEMENT
I extend my humble appreciation towards the efforts put by the following who led to the success
of my industrial training.
First and foremost, my special thanks go to Allah who has seen me through this training period for
He has kept me alive to date.
Let me also express my sincere appreciation to the Department of Construction Economics and
Management, College of Engineering, Design, Art and Technology and Makerere University for
availing such a time schedule to carry out my industrial training and other services provided. I also
express my gratitude to the university supervisor, Mr. Lubwama Ibrahim, who spared his time to
inspect me and later on inspired and encouraged me.
I extend my gratitude towards Higher Education Students Financing Board (HESFB) for financing
my Higher Education.
I would like to thank the entire organization of Abuljebain Engineering Consulting Office and
China Communications Construction Company for the heartily welcome I received and allowed
me carryout my industrial training. Furthermore, I also express heartwarming thanks to my field
Supervisors, Engineer Ronald Ssebirumbi, Engineer Moses Kisembo Muyonjo and the entire staff
for the tireless hard work that they have expressed to see that the project attains its quality standards
desired for its sustainability.
iv | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE TO AUGUST 2019
DEDICATION
I dedicate this report to my family which has been there for every kind of support needed during
my education.
v|Page
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE TO AUGUST 2019
Table of Contents
1 CHAPTER ONE: INTRODUCTION ..................................................................................... 1
1.1 Overview .......................................................................................................................... 1
1.2 Objectives of the training ................................................................................................. 1
1.3 Background of the Project ................................................................................................ 2
1.4 The Engineer’s History .................................................................................................... 2
1.5 The contractor’s Brief History. ........................................................................................ 2
1.6 Project Details .................................................................................................................. 3
1.7 Project Location ............................................................................................................... 4
1.8 Site Administration and organizational layout for the supervising Engineer (AECO) .... 5
1.9 Project Headquarters ........................................................................................................ 6
1.10 Site Meetings ................................................................................................................ 7
1.11 Working schedule ......................................................................................................... 8
2 CHAPTER TWO: SOILS, MATERIALS AND LABORATORY ........................................ 9
2.1 Soil tests ......................................................................................................................... 10
2.1.1 Borrow pit sampling ............................................................................................... 11
2.1.2 Maximum Dry Density of Soil ............................................................................... 11
2.1.3 California Bearing Ratio of the Soil ....................................................................... 11
2.1.4 UCS for Stabilized materials .................................................................................. 13
2.2 Tests on Aggregates ....................................................................................................... 14
2.2.1 Grading and Flakiness Index .................................................................................. 14
2.2.2 Aggregate crushing Value and Ten Percent Fine Value of Aggregates ................. 15
2.2.3 Aggregate Impact Value ......................................................................................... 16
2.2.4 Water absorption Test ............................................................................................. 18
2.2.5 Sand Equivalent (JTG -T0334 - 2005).................................................................... 18
2.3 Tests on Concrete ........................................................................................................... 20
2.3.1 Slump Test .............................................................................................................. 20
2.4 Tests on bitumen ............................................................................................................ 20
2.4.1 Ductility Test .......................................................................................................... 21
2.4.2 Penetration Test ...................................................................................................... 22
2.4.3 Flash and Fire point test by Cleveland Open Cup .................................................. 23
vi | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE TO AUGUST 2019
vii | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE TO AUGUST 2019
viii | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE TO AUGUST 2019
ix | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE TO AUGUST 2019
LIST OF FIGURES
Figure 1.1 : Shows project location and all its Lots ........................................................................ 4
Figure 1.2 : Organization structure of the Engineer, AECO........................................................... 5
Figure 1.3 : Engineer’s structures at the project headquarters ........................................................ 6
Figure 1.4 : Contractor’s Main Campsite ....................................................................................... 7
Figure 2.1 : Engineer’s Laboratory Equipment. ............................................................................. 9
Figure 2.2 : Test Procedure for CBR Test .................................................................................... 12
Figure 2.3 : Test Procedure for Aggregate Crushing Value and Ten Percent Fines Value .......... 15
Figure 2.4 : Ductility Test Procedure ............................................................................................ 21
Figure 2.5 : Flash and Fire test Procedure for the Bitumen point ................................................. 24
Figure 4.1: Project Location - Bridge Overview .......................................................................... 32
Figure 4.2 : Cement concrete being loaded in a truck at the Cement Concrete Batching Plant ... 33
Figure 4.3 : Drilling for piles at Emmi River Bridge Lot 8A Km 21 + 120 ................................. 34
Figure 4.4 : Lowering reinforcement at Emmi River Bridge Lot 8A Km 21 + 120 ................... 35
Figure 4.5: Pile casting at Sambiya River Bridge Lot 7A Km 55 + 071.6 ................................... 35
Figure 4.6 : Pile cap casting at Zoliya River Bridge Lot 7A Km 51+528.6 ................................. 36
Figure 4.7 : Abutment Construction at Waiga River Bridge Lot 7A Km 40 + 950.6 .................. 37
Figure 4.8 : Mud Density Test at Emmi River Bridge Lot 8A Km 21 +120 ................................ 38
Figure 4.9 : Percentage of sand in slurry test at Emmi River Bridge Lot 8A Km 21+120 ........... 39
Figure 4.10 : Concrete Slump test at the Main Cement Concrete Batching Plant ........................ 40
Figure 5.1 : A Grader shaping a layer to be compacted.............................................................. 42
Figure 5.2 : An excavator loading material onto the truck ........................................................... 43
Figure 5.3 : A steel drum roller compacting ................................................................................. 43
Figure 5.4 : Inspection of the finished G7 Top layer at Lot 7A Km 3 + 100 - Km 3 + 400 ......... 44
Figure 5.5 : Carrying out DCP Test .............................................................................................. 45
Figure 5.6 : Carrying out filed density using Sand cone method.................................................. 48
Figure 5.7 : Dipping during processing of G7 Top layer at Lot 7A Km 4 + 755 - Km 4 + 855 .. 49
Figure 5.8 : Showing laminations along Lot 7B ........................................................................... 49
Figure 5.9 : Cracks along G7 Top finished, Lot 7A ..................................................................... 50
Figure 5.10 : Cement Stabilized subbase ...................................................................................... 52
x|Page
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE TO AUGUST 2019
Appendix 5 - Figure 1: Environmental, social, health and safety measures during construction..79
xi | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE TO AUGUST 2019
LIST OF TABLES
Table 1.1 : Lots of the project and their length ............................................................................... 3
Table 1.2: Bridges and their locations at the project ...................................................................... 3
Table 2.1 : Tests carried out .......................................................................................................... 10
Table 2.2 : CBR Requirements for fill and Subgrade Layers ....................................................... 13
Table 2.3: UCS results after Crushing .......................................................................................... 14
Table 2.4 : Test Results of Aggregate Impact Value Test (Dry Condition) ................................. 17
Table 2.5: Reagents used for Sand Equivalent test ....................................................................... 19
Table 2.6 : Penetration Test Results ............................................................................................. 22
Table 2.7 : Flash and Fire Point of Bitumen Results .................................................................... 24
Table 2.8 : Specific gravity test results ......................................................................................... 25
Table 3.1 : Traffic Classes ............................................................................................................ 28
Table 3.2 : Subgrade Classification .............................................................................................. 28
Table 4.1 : Bridges of the Project ................................................................................................ 31
Table 5.1 : Testing frequencies for Filed Density......................................................................... 46
Table 5.2 : Required degree of compactness for Earthworks ....................................................... 47
Table 6.1 : Excavation levels of a Pipe Culvert at Lot 7A Km 25+710 ....................................... 58
Table 6.2: Results for the concrete bedding levels of a Pipe Culvert at Lot 7A Km29+895 ....... 59
Table 6.3: Levels of formwork for the pile Cap setting out of Zoliya Bridge Lot 7A Km 51+529
....................................................................................................................................................... 60
Table 6.4 : Bearers levels at Waiga River Bridge Lot 7A Km 40+956 ........................................ 61
Table 6.5: Height of crossing wires at Lot 7A .............................................................................. 65
Table 6.6: Setting out details of Emmi River Bridge Lot 7B Km 21+120, Pile A1-P6-5 ............ 66
xii | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE TO AUGUST 2019
LIST OF ACRONYMS
ACV – Aggregate Crushing Value
AECO – Abuljebain Engineering Consulting Office
AIV – Aggregate Impact Value
BS - British Standards
CCCC – China Communications Construction Company
CBR – California Bearing Ratio
FI – Flakiness Index
G7 – Natural gravel with CBR value min 7
G15 – Natural gravel with CBR value min 15
G30 – Natural gravel with CBR value min 30
L.H.S – Left Hand Side
LL – Liquid Limit
MDD – Maximum Dry Density
MoWT – Ministry of Works and Transport
MTP – Masindi (Kisanja) – Park Junction and Tangi Junction – Paraa – Buliisa Roads Upgrading
Project
NEMA - National Environmental Management Authority
OMC – Optimum Moisture Content
PI – Plasticity Index
PL – Plastic Limit
RFI – Request For Inspection
R.H.S – Right Hand Side
TFV – Ten percent Fines Value
UNRA – Uganda National Roads Authority
xiii | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE TO AUGUST 2019
1.1 Overview
The Department of Construction Economics and Management under the College of
Engineering, Design, Art and Technology, Makerere University attaches 2nd year students of
Bachelor of Science in Construction Management, Bachelor of Science in Quantity Surveying and
Bachelor of Science in Land Economics to various engineering, construction, consultancy and
valuation firms respectively during the first holiday of the academic year for industrial training
because it is a requirement.
This exposes a student to the practical skills while at the same time enhancing the theoretical
knowledge of the student. At the end of the training, students are expected to write a report
regarding their field experience. I was honored to train with Abuljebain Engineering Consulting
Office for the period of two months from 3rd – June – 2019 to 2nd – August – 2019 under the
supervision of the company supervisor and university supervisor.
1|Page
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE TO AUGUST 2019
Due to UNRA’s new policy of 30% local content, three local contractors that include; Mukoda
Engineering Works, Rodo Contractors Limited and Greystone Investments Limited were
subcontracted to carry out earthworks and pipe culverts construction at different lots of the Project
as assigned. These had contracts with the Main Contractor, CCCC.
The project was estimated to cost USD 218millions, and expected to be executed for the period of
36 months. The first 15 months being a pre-finance period where the Contractor, CCCC had to
finance himself.
2|Page
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE TO AUGUST 2019
include, Entebbe Express Way and the expansion of the Entebbe International Airport among
others.
The project was divided into the following four (4) lots as shown in Table 1.1:
During the period of training, there were ongoing activities at all the four (4) lots, especially on
Lot 7A and 7B. Six bridges were being constructed simultaneously, apart from Wairingo River
Bridge at Lot 7A Km 45 + 281.6 which was finished first since it required a shallow foundation.
3|Page
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE TO AUGUST 2019
4|Page
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019
1.8 Site Administration and organizational layout for the supervising Engineer (AECO)
5|Page
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
6|Page
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
The project meetings were held every month. They could occur for the period of one week referred
to as the inspection week. The client (UNRA) used to visit the project to check on the overall
progress of the project. The first day used to be for inspection of works going on, the second day
used to be a meeting between the Engineer and the client and then the last day used to be a meeting
7|Page
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
between the Engineer, client and the Contractor. During the period of training, there were two
inspection weeks, 10th-June – 2019 to 14th-June-2019 and 8th July-2019 to 12th July-2019.
8|Page
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
9|Page
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
The tests were carried out in accordance to the International Standards as indicated in the Table
2.1.
10 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
The following tests on soil(s) were carried out during the course of training.
Objective
To determine the strength of soil sample in order to assess whether it meets the required
specifications to be used for construction of a particular layer of the pavement.
11 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Apparatus
Balance, Moulds, Scoop, Metal trays, Straight edge, Oven, CBR-Test Compression Machine and
Filter papers.
Procedure
The test was conducted in accordance with BS1377: Part 4:1990 and TMH1: method A8:1986
Sample details
The soil sample was Original Ground Soil (0GS), picked from Lot 7B Km 20 + 000 Centre Line
(C.L) at a depth of 0.8 – 2.2 m, sieved through a 20mm sieve.
1. Mixing the soil with optimum moisture 2. Put the sample in 5 layers 3. Compacting each layer, 10 , 30 & 62 blows
4. Putting filter papers on the samples 5. Soaking the samples for 4 days 6. Penetration of the samples in the CBR Machine
12 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
The higher the CBR Value, the stronger the material is.
The following table below shows the CBR requirements of a material to be used for the subgrade
or a fill according to The Republic of Uganda – Ministry of Works and Transport (MoWT) General
Specifications for Road and Bridge Works, Series 3000, Page 16 - Table 3602/1 and Page 28 -
Table 3702/5
Materials Class
G15 G7 G3 G30
CBR (%) Minimum 15, after Minimum 7, after 4 3 after 4 days soaking, Minimum 30, after
4 days soaking days soaking measured at 90% of MDD of 4 days soaking
BS-Heavy compaction
Usage Upper improved Lower improved Fill only Subbase
Subgrade layers subgrade layers
and fill and fill
Limitations: Because of the size of the sample and of the plunger the test is appropriate only for
materials having a maximum particle size not exceeding 20 mm
Conclusion
According to our results, the material with the CBR value of 10% can be used at the lower
improved subgrade layers and a G7 fill material.
2.1.4 UCS for Stabilized materials
Objective
To determine the strength of stabilized material compared to non-stabilized material.
Test Procedure
The test was carried out in accordance with THMI: method A14: 1986
13 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Results
Laboratory results of mixture with Cement
Cement (%) MDD OMC
4 2.12 8.8
Conclusion
Since all the samples had a strength greater than 1.5 MPa, the results are satisfactory.
14 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
2.2.2 Aggregate crushing Value and Ten Percent Fine Value of Aggregates
Objective
To determine the strength of the coarse aggregates to resist crushing on a gradually applied load.
Assess suitability of coarse aggregates for use in different types of road
Apparatus
• A steel cylinder 15cm diameter with plunger and base plate.
• A straight metal tamping rod 16mm diameter and 45 to 60cm long rounded at one end.
• A balance of capacity 3 kg readable and accurate to one gram.
• IS sieves of sizes 14mm, 10mm and 2.36mm.
• A compression testing machine.
• Cylindrical metal measure of sufficient rigidity to retain its from under rough usage and of
11.5cm diameter and 18cm height.
• Dial gauge.
Test procedure
The tests were carried out in accordance with BS812: Part 110:1990 & BS812: Part 111:1990
1.Prepare the sample in the mold in 3 layers 2. Set the Peak and the rate in the Crusching Machine
3. Place the mold with the sample in the machine 4. Control the Machine and stop it after 10 mins
Figure 2.3 : Test Procedure for Aggregate Crushing Value and Ten Percent Fines Value
15 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Results
A.C.V = 8.5%
Analysis and discussion of results
The aggregates used in roads and pavement construction must be strong enough to withstand
crushing under roller and traffic. If aggregates are weak, the integrity of the pavement structure is
likely to be adversely affected. The A.C.V test helps to check on this strength.
Crushing value of aggregates indicates its strength. Lower crushing value is recommended for
roads and pavements as it indicates a lower crushed fraction under load and would give a longer
service life and a more economical performance.
If the aggregate crushing value is 30% or higher’ the result may be anomalous and in such cases
the ten percent fines value should be determined instead.
According to The Republic of Uganda, MoWT Specifications Series 4000, Sub Clause 4202(c),
the Ten Percent Fines Value of the coarse aggregate used in asphalt concrete surfacing, when
determined in accordance with BS 812-111: 1990 or equivalent shall not be less than 110 kN.
Additionally, in Sub clause 4202 (g) (ii), the TFV of the coarse aggregate used in cold mixed
bituminous base course, when determined dry in accordance with BS 812-111: 1990 or
equivalent, shall not be less than:
- 110 kN for Traffic Load greater than 1 x 106 esa's.
- 80 kN for Traffic Load less than 1 x 106 esa's.
Conclusion
16 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Objective
To determine the resistance of an aggregate on a shock or impact Load.
Apparatus
Aggregate impact testing machine, tamping rod, 2.36mm sieve, balance.
Sample Details
It was carried out on aggregates passing the 14mm sieve and retaining on the 10mm sieve. The
test sample consisted of 22kg aggregates sized 12.0mm - 16.0mm picked from Quarry 1. 11kg
Aggregates were dried by heating at 100-110° C for a period of 4 hours and cooled and other 11kg
soaked in water for the wet condition test.
Test Procedure
The test was carried out in accordance to BS812: Part 112:1990
Following completion of the series of blows the material passing the 2.36mm sieve was expressed
as a percentage of the sample and recorded as the aggregate impact value.
Results
Table 2.4 : Test Results of Aggregate Impact Value Test (Dry Condition)
Test No. 1 2 3
Mass of aggregates + Cylinder (g) 1351 1340 1339
Mass of Cylinder (g) 974 974 974
Mass of oven dried sample (g) 377 366 365
17 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
18 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Apparatus
Reagent needed;
Table 2.5: Reagents used for Sand Equivalent test
Procedure
• 500g of dry sample and 15g of water were measured.
• The sample was mixed with water to make it saturated
• Take some sample to confirm the moisture
• Two samples were used.
• The mix was poured into the cylinder. It was levelled but without compacting it.
• 10ml of the solution were added into the cylinder.
• It was left to settle for 10 minutes
• The height of aggregates and dust, H2 was recorded.
• The cylinder was then filled with the solution up to the height level.
• The mixture was then shaken with the mechanical shaker for 90s.
• It was then left to settle for 20 minutes
• The height of aggregates only, H1 was measured and recorded.
• Sand equivalent was calculated from the formula;
𝐻1
𝑆𝐸 = 𝑥 100
𝐻2
Where,
SE is the Sand Equivalent
H1 is height of aggregates only
H2 is height of aggregates and dust
Results
19 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
SE = 9.1 %
Analysis and discussion of results
Sand Equivalence indicates the content of sand in the aggregate. The test was carried out on quarry
dust which was intended to be used at the base layer. A high percentage of sand content was
required, so the results were satisfactory
20 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
In road construction, bitumen is used as the binder in asphalt concrete. Before using it, it has to be
tested for its properties. The following tests were carried during the training to check for the
properties of bitumen.
Objective
To describe the ductile and tensile behavior of the bituminous binders. It reflects the homogeneity
of the binder and its ability to flow.
Apparatus
Standardized brass molds, Water bath, Ductility machine, Straight edge knife and a thermometer.
Procedure
The test was conducted in accordance with ASTM D113-86.
1. Pouring the Bitumen into the Mold 2. Leave it to settle for 30 minutes 3. Put it in the Water bath of 25'C for 30 minutes
4. Trim the excess and take it to the bath for 1.5hrs 5. Attch the 3 samples into the Ductility Machine 6. Start the Ductitlity machine and record the distances
21 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Conclusion
According to the specifications and with reference to the penetration grade of the bitumen (60-70),
the ductility of 1394.96mm is satisfactory.
22 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Apparatus
Cleveland open cup Apparatus, Thermometer (-6 to 400℃), Gas Supply for test flame and
Barometer.
Procedure
The test was conducted in accordance to ASTM D92-90
23 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
1. Pour the Bitumen in the cap 2. Boil the bitumen and introduce frame
Figure 2.5 : Flash and Fire test Procedure for the Bitumen point
Test Results
Table 2.7 : Flash and Fire Point of Bitumen Results
24 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Procedure
The test was done with accordance to ASTM D4402-91
Results
201.4 seconds
Calculations
𝑀3 −𝑀1
Specific gravity = (𝑀
2 −𝑀1 )−(𝑀4 −𝑀3 )
Results
Table 2.8 : Specific gravity test results
25 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
26 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
The traffic studies involve the collection and analysis of traffic data through manual and automated
traffic counts. The manual traffic counts involve using individuals to carry out manual traffic
counts for different categories of vehicles that are using the existing road. Origin-destination (O-
D) Surveys are also carried out to analyze the traffic movement. The traffic studies help to generate
traffic class that is one of the parameters in the determination of the pavement design layers
thicknesses and materials to be used.
The traffic classes range from Class 1 for instance T1, to Class 8 for instance T8, Ranging from
traffic volume of 0.3 to 30 million
27 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Subgrade strength is determined according to the CBR Value of the original ground soil.
28 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
rendering 3D Models. At the project, it was used to review the detailed drawings submitted by the
contractor to be approved by the Engineer.
Civil 3D is a Civil Engineering design software that supports Building Information Modelling with
integrated features to improve drafting, design and construction documentation of infrastructure
projects including rail, roads, airports, highways, land development, airports, drainage and civil
structures. For this particular project, the software was used by the Engineer to review the
geometric design drawing for the road submitted by the contractor.
The training for the Civil 3D Software was given for the period of 3 days and it covered the
following;
29 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
3.2.2 Measurements
Measurements involve calculation of the amount of work that has been executed by the contractor
in order to prepare their payments. The engineer of the project on behalf of the client does
measurements but the client has to first review and approve them.
The contractor prepares an Interim Payment Statement detailing the works done and it must have
been approved by the engineer who reviews the prepared document and approves the works done.
The Engineer later on prepares an Interim Payment Certificate that is to be reviewed by the client
and approved. The payments are then done according to the contract terms and conditions. 10% of
the amount is retained as a retention. The 50% of the total retention is given back to the contractor
as he is receiving the Substantial Completion Certificate. The remaining amount is given back
after the completion of the project and the contractor is receiving the Certificate of Completion.
30 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
4.1 BRIDGES
According to MoWT General Specifications, a bridge is a structure for carrying motor, railways,
pedestrians or other traffic or services over a river, watercourse, or any other gap, with a single
span length, or sum of span lengths, of 4.0 meters or more. The length is measured between the
abutment faces, or pier head faces respectively, along the centerline of the bridge deck
Six bridges have pile foundations and its only Wairingo River Bridge Lot 7A Km 45 + 282 with a
shallow foundation.
Figure 4.1 shows different locations of Bridges at the Project.
31 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
4.1.1 MATERIALS
There were different materials that were used on the structures that were being constructed. All
these materials were first tested to ensure that they qualify to be used. They are explained a below.
4.1.1.1 Concrete
Concrete is a mixture of aggregates, sand, cement and water plus admixtures. Structural cement of
42.5 MPa, class C25 was used on structures. The concrete was self-compacting concrete and the
admixtures that included water reducer, set retarder and air entrainer. All this was to ensure that
the concrete produced serves its purpose.
The concrete was mixed at the cement concrete batching plant located at Lot 8A Km 22 + 500
with a capacity of 1.5m3 and could fill the truck in 30 minutes.
32 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Figure 4.2 : Cement concrete being loaded in a truck at the Cement Concrete Batching Plant
4.1.1.2 Reinforcement bars
The reinforcement bars help improve on the strength of concrete. These bars had different
diameters according to the design drawings. The bar bending schedule shows the different sizes
and shapes of bars to be used. The jointing method was welding due to Chinese standards being
used by the Contractor. The overlapping distance depends on diameter of the bars and whether you
are doing single side welding or double side welding. For single sided, the overlapping distance is
got from 10D, D being the diameter. For double sided welding, the lap would be 5D.
4.1.2.1 Method
The methodology used by the contractor to carry out the construction of structures was explained
in the method statement. It was with this method statement that the Engineer could use to inspect
to ensure that the works were done according to the approved methodology.
33 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Figure 4.3 : Drilling for piles at Emmi River Bridge Lot 8A Km 21 + 120
34 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
35 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
4.1.2.5 Chipping
Chipping is the practice of removing the excess concrete that is beyond the pile cut off level. A
hammer was used to chip off the concrete. After the pile cut off level has been reached, surveyors
had to check and approve. The pile integrity test was done after chipping to check on the continuity
of the pile.
Figure 4.6 : Pile cap casting at Zoliya River Bridge Lot 7A Km 51+528.6
36 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Apparatus
Mud balance.
Procedure
• The slurry was poured into the container.
• The container was closed and the exterior washed with clean water.
• The container with slurry was put on one side of the mud balance with the other side having
1g of water.
37 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
• The mud balance was balanced and the value was read off from calibrated ruler.
• The slurry had a density of 1.01g/cm3 which is closer to the density of water.
Figure 4.8 : Mud Density Test at Emmi River Bridge Lot 8A Km 21 +120
4.1.3.2 Amount of Sand in slurry
The test is carried out during the washing of slurry from the drilled hole. The slurry should have
very less content of sand or clay since sand tend to reduce the depth of the drilled hole. The
percentage sand in the slurry should be less than 2%.
Procedure
• Slurry is poured into the glass.
• It is sieved to let all the water out and left with only sand.
• The sand is then poured back into the glass and left to settle.
• The percentage of sand is then read off.
It was found that that the percentage of sand in the slurry at the bore for pile A1-P6-5 at Emmi
Bridge Lot 8A Km 21 + 120 was 1% which passes the test.
38 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Figure 4.9 : Percentage of sand in slurry test at Emmi River Bridge Lot 8A Km 21+120
39 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Figure 4.10 : Concrete Slump test at the Main Cement Concrete Batching Plant
Results
The slump required was between 180mm and 220mm. The slump measured was 190mm which
falls within the required range.
40 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
5.1 EARTHWORKS
According to the MoWT General Specifications, earthworks are described as all soil’s material
placed below the formation level including improved subgrade layers, fill and prepared roadbed.
When the road bed level is reached, tests have to be carried out to ensure that the existing material
meets the requirements as prescribed by the Engineer in terms of California Bearing Ratio of the
material for instance above 5% and other measures.
In case of expansive soils, a thick layer of about 350mm can be used and acts as the roadbed.
5.1.2 Fill layers/ Common fills / embankment fills
A fill is defined as the portion of the road prism consisting of approved imported material, which
lies above the roadbed and is bounded by the side slopes, on which improved subgrade layers,
pavement and shoulders are to be constructed. Material imported to replace unsuitable material in
the roadbed shall also be classified as fill when placed below the improved subgrade layers.
41 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
The fill is done in layers of thickness of between 100mm – 250mm. Compacting a layer less than
100mm will lead to cracking of the layer and compacting a layer thicker than 250mm will limit
the roller from achieving maximum compaction.
42 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
43 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
In this department, the inspection of works was carried on finished layers to check if they meet
requirements, for example, to ensure that the layer is free from the defects that include,
laminations, shoving and corrugations, heave spots, cracks, wheel rutting among others. The layer
would either be rejected or approved. If it is rejected, the contractor has to make repairs on the
pavement and request for inspection again. After the approval of the layer by the department,
surveyors visit the layers and ensures that the required levels and thickness were achieved. It is
later handed over to the laboratory department and tested for compactness.
Figure 5.4 : Inspection of the finished G7 Top layer at Lot 7A Km 3 + 100 - Km 3 + 400
5.1.5.2 Dynamic Cone Penetrometer (DCP) Test
The DCP test is carried out to measure the strength of the in-situ soil and thickness and location
of underlying soil layers using a simple hand held device called a Dynamic cone penetrometer.
44 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Test procedure
• A DCP was set up at the Lot 7A Km 46 + 200 were the test was required to be carried out
• The hammer was raised and left to free fall, letting the cone on the lower shaft to enter into
the ground.
• After every 5 blows, the penetration on was measured using a ruler and recorded.
• This was done until the cone was totally driven into the soil approximately 1m deep.
Results
Blows 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
Penetration 75 141 192 245 312 380 443 510 578 639 702 791 860 927 982
(mm)
45 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
The Dynamic Cone Penetrometer Index (DPI) is calculated and expressed in mm/blows. Soft soils
give a low DPI and hard soils give a high DPI.
46 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
The test was used for determining the in-place density for subgrade, sub base, and base layers.
Volume of hole = mass of sand in hole / bulk density of sand.
Wet density of soil = mass of soil from hole / volume of hole.
Then the in-situ dry density was calculated from the wet density and the in-situ moisture content;
100 ρ
Dry density, ρd = 100+𝑤 Where w is the moisture content of the soil as expressed as a percentage
in−situ dry density
Relative compaction = maximum dry density × 100
The test was carried out on the G7 Top finished layer and gave a 95% compaction degree which
meets the set standards
47 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Figure 5.6 : Carrying out filed density using Sand cone method
5.1.5.4 Dipping
Dipping is a method used to control levels of layers during their construction. Levels were
controlled starting from G7 Top layer. A string with marked offsets was made to stretch from one
metal bar to another above the pavement layer at different elevations to form a required slope. A
tape measure was used to measure the distance between the string and the material being spread
putting into consideration, the compaction factor of 15%. A grader would shape the layer
according to the adjustments required.
48 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Figure 5.7 : Dipping during processing of G7 Top layer at Lot 7A Km 4 + 755 - Km 4 + 855
5.1.6 Road Defects
Road defects indicate structural failures within the road pavement. They are caused by poor
methodology like using unqualified materials among others.
5.1.6.1 Laminations
Laminations are small scale sequence of fine layers. It is formed due to compaction of thin layers
less than 100mm on top of a hard-thick layer. Figure 5.8 shows laminations.
49 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
5.1.6.3 Cracks
Cracks on the layer are indicators of other defects. Longitudinal cracks are caused by having
moisture below the layer, as it tries to evaporate away, the layer expands and ends up cracking.
The other cracks are caused by having clay content dominating the material. The remedy to this is
to use a suitable material and avoid compaction a layer with high moisture content.
50 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
5.2.1 Subgrade
This is the top surface of a roadbed on which the pavement structure and shoulders including kerbs
are constructed. Generally the top soil portion up to 500mm of the embankment or cut section is
referred to as the subgrade. It may be undisturbed local material or may be soil excavated
elsewhere and placed as fill. The loads on the pavement are ultimately received by the subgrade
layer.
5.2.3 Sub-base
This is the secondary load-spreading layer underlying the road base. It will normally consist of a
material of lower quality than that used in the roadbase (but of higher quality than the subgrade)
such as unprocessed natural gravel, gravel-sand, or gravel-sand-clay. The functions of this layer
are to: distribute stresses to the subgrade, act as a drainage layer in case the subgrade is poor,
prevent capillary attraction effect, serve as a separating layer preventing contamination of the
roadbase by the subgrade material, and protect the subgrade from damage by construction traffic
especially under wet conditions. The sub-base is omitted when the subgrade is a hard intact rock
or if it is granular and has a CBR greater than 30% and without a high water table.
The subbase of this particular was cement stabilized with 4% cement to make a G30 material with
a thickness of 175mm.
51 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
The roadbase of the MTP project was made up of Crushed stones and quarry dust and designed at
a thickness of 150mm.
52 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
During the time of training, there was no section that had reached surfacing.
Wearing course: The uppermost layer of asphalt concrete that acts as the riding surface.
53 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Binder course: This is a layer below asphalt wearing course and above the base course.
The wearing course for the road was Asphalt concrete, AC 20. By the time the training ended, the
road had not reached the wearing course layer.
The road being an oil road for instance will be used to transport heavy equipmet that is required to
extract oil, the Class of pavement is Class 2(a) paved. In addition to that, the client made some
modifications in the design to meet the requirements for the traffic of the heavy equipment that is
expected, for example, making the subbase to be stabilised with 4% cement content.
54 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Figure 6.1 : Shows some of the Surveying equipment that was used in the Department
The following activities were carried out while in the Department of Surveying during the
Industrial Training using.
Procedure
• On a relatively flat area, two points A and B, 30m apart were marked.
• A dumpy level was set up at point O, 15m from point A (midpoint)
• A staff was held at point A and B, readings A1 and B1 were recorded respectively.
• A difference in height d1 = B1 – A1, was calculated.
• An instrument was then set up 22.5m away from point A.
55 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
• A staff reading at point A and B was taken and recorded as A2 and B2 respectively.
• A difference in heights d2 = B2 – A2, was calculated.
• The final difference d = d2 – d1 was calculated.
• It was found out that d=0.001m, which falls below 0.005m
Conclusion
The dumpy level was in correct adjustment.
6.2 Verification of setting out of culverts
Culverts are drainage structures of the pavement. On the project, the culverts serve two purposes
for instance as a drainage structure and also as a crossing way for the national park wildlife.
Objective
To ensure that the culvert was set out in the co-ordinates as indicated in the design drawings.
Instruments used
Real-time kinematic (RTK).
Location
The setting out of pipe culverts along Lot 7A at Km 29 + 528, Km 30+371, Km 35+136, Km
34+79, Km 34+564, Km 33+680 were checked and verified.
Procedure
• A GPS was set up.
• Co-ordinates of the inlet, center and the outlet were recorded and compared to the
coordinates in the design drawings.
• Deviations were computed and decision was made accordingly.
• Approved when the deviations fall within the acceptable tolerance.
56 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Figure 6.2 : Shows Coordinates checking for the setting out of a pipe culvert at Lot 7A Km
30+371 using a GPS
Objective
To ensure that the excavation was done up to the prescribed level, not below and not above.
Instruments used
Dumpy Level and a levelling staff.
Procedure
• The dumpy level was set up.
• Reading were taken by holding the staff at the inlet, center and outlet of the culvert in
reference to a benchmark.
• Computations were carried out and levels were computed.
57 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
• The design levels were compared to the measured levels and decisions were made
accordingly.
Figure 6.3 : Shows setting up of a dumpy level to check on pipe culvert excavation levels at Lot
7A Km25+710
Results
Table 6.1 : Excavation levels of a Pipe Culvert at Lot 7A Km 25+710
BS IS FS HOC RL Remarks
0.324 961.516 961.192 BM(KP-1086)
0.280 3.307 958.489 958.209 CP
2.748 955.741 Inlet Level
2.888 955.601 Center Level
3.000 955.489 Outlet Level
58 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Instruments used
Dumpy level, levelling staff and a tape measure.
Procedure
• The dumpy level was set up.
• Reading were taken by holding the staff at the inlet, center and outlet of the culvert in
reference to a benchmark.
• Computations were carried out and levels were computed.
• The design levels were compared to the measured levels and decision were made
accordingly.
Results
Table 6.2: Results for the concrete bedding levels of a Pipe Culvert at Lot 7A Km29+895
BS IS FS HOC RL Remarks
1.509 940.995 939.486 BM (KP-101)
2.884 938.111 Inlet Level
3.077 937.918 Center Level
3.274 937.721 Outlet Level
59 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
• Readings were taken at the edges and center of the bridge pile cap on top of the formwork.
• Computations were carried out.
• Measured levels were compared to design levels.
• The levels of formwork were approved.
Figure 6.4 : Shows a staff being held at the formwork level to take a reading at Zoliya River
Bridge Lot 7A Km 51+529
Results
Table 6.3: Levels of formwork for the pile Cap setting out of Zoliya Bridge Lot 7A Km 51+529
BS IS FS HOC RL Remarks
0.244 730.146 729.902 BM
1.231 1.661 729.716 728.485 CP
3.671 726.045
3.613 726.103 Left 1
3.618 726.098 Right 1
3.618 726.098
3.618 726.098
3.618 726.098
60 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
To ensure that the bearers are at the levels as shown in design drawings.
Instruments used
Dumpy level, levelling staff and a tape measure.
Procedure
• The dumpy level was set up next to the Bridge.
• Readings were taken by placing the levelling staff on top of bearers.
• Levels were computed.
• The measured levels were compared to the design levels.
Results
Table 6.4 : Bearers levels at Waiga River Bridge Lot 7A Km 40+956
BS IS FS HOC RL Remarks
1.635 687.306 685.671 BM (PKT1)
0.437 686.869
0.301 687.005
0.430 686.876
0.257 687.049
0.351 686.955
0.233 687.073
0.356 686.950
0.162 687.144
0.352 686.954
0.229 687.077
0.429 686.877
0.255 687.051
0.436 686.570
0.301 687.005
61 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Instruments used
Dumpy level, levelling Staff and a tape measure.
Procedure
• A dumpy level was set up near the temporary benchmark and a Back-sight reading was
taken.
• The Inter Sight readings were taken at different points on the bridge, both on the right- and
left-hand side.
• Measured levels were computed and compared to the previous levels to check for
settlement.
Figure 6.5 : Taking reading to check Settlement for Paraa Bridge Lot 8A Km 21 + 580
62 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Location
G7 layer levels at section, Lot 7A Km 38+960 – Km 39+500 were checked and verified.
Instrument used
Real-time kinematic – GPS.
Dumpy Level.
Levelling Staff.
Procedure
• A GPS was set up.
• Points where levels were to be taken were marked. These include offsets of -6.1m, -5m, -
3m, C.L, 3m, 5m and 6.1m as shown in figure 6.6.
• A levelling staff was held at the marked points and readings were taken.
• The field data was exported to the computer.
• Computations were carried out to compare the design levels and measured levels.
Deviations were analyzed whether the follow under acceptable range.
Figure 6.6 : Section showing Points where Levels are taken, at Lot 7A Km 38+980
Results
Refer to the Appendix 4 for the results.
6.9 Checking of G30 Subbase Layer Levels
A subbase is the second layer of a pavement structure above the subgrade. On this particular project
the subbase was of a G30 Cement Stabilized material and with a thickness of 175mm.The
surveying department had to ensure that this thickness is achieved and at a designed level.
Location
Lot 7A Km 44+330 – Km 44+700 Left Hand Side (L.H.S).
63 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Instruments used
Real-time kinematic.
Dumpy Level.
Levelling Staff.
Procedure
• A GPS was set up.
• Points were levels were to be taken were marked. These include offsets of, C.L, 3m, 5m
and 6.1m.
• A levelling staff was held at the marked points and readings were taken.
• The field data was exported to the computer.
• Computations were carried out to compare the design levels and measured levels.
Deviations were analyzed whether the follow under acceptable range
6.10 Checking the Height of crossing electric lines from ground, Lot 7A
Objective
To ensure that the there is no obstacle for instance crossing wires within the required vertical
clearance for smooth traffic floor.
Instruments used
Real-time kinematic.
Total Station.
Tape Measure.
Procedure
• A GPS was set.
• A machine station in the middle of centerline of the new road was marked using a GPS and
a total Station was set on the marked point.
• The chainage of the Machine station was recorded.
• A reflector was put vertical below the crossing wire and the horizontal distance and vertical
angles were taken.
• The total heights of the wires were calculated and compared to the designed vertical height.
64 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Results
Table 6.5: Height of crossing wires at Lot 7A
Machine Prism Measured Set Turning Difference Prism Calculated Total
Station Station Distance Angle Angle in Angle Height Height Height Description
14+280 14+235 45 90°00'00" 81°32'48" 8°27'12" 0.42 6.69 7.11 DL
14+327 47 90°00'00" 80°46'24" 9°13'36" 2.49 7.64 10.13 SP
14+620 14+667 47 90°00'00" 84°25'33" 5°34'27" 1.62 4.59 6.21 DL
65 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Figure 6.7 : Checking for setting out of Pile, A1-P6-5 Emmi Bridge Lot 8A Km 21+120
Results
Table 6.6: Setting out details of Emmi River Bridge Lot 7B Km 21+120, Pile A1-P6-5
Coordinate
Pile No. Easting Northing Radius (m)
A1-P6-5 340306.871 253417.543 1.2
The coordinates and the radius were matching with the design drawings and the pile was approved.
66 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Project management is done using different tools for instance Project Management Information
Systems. On the project, Microsoft Project was used as the tool for scheduling of activities. This
would help in tracking progress for the overall project.
During the course of the training, an assignment was given to model the program of works for the
project from a portable document format to a Microsoft Project file format indicating the start,
finish and the floats of an activities.
Figure 7.1 : A caption of program of works for the project in MS Project 2016
67 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
8.1 Environment
With the project having a biggest percentage into the Murchison Falls National Park, its impact to
the environment required a smart matrix to help in the mitigation of the negative impacts. A
certificate from NEMA permitting the project to pass through the national park was obtained. This
also detailed how works should be done to minimize the negative impacts. Different permits had
to be acquired, for example, borrow pit permits, blasting permits, water abstraction permits and
petroleum permits.
The plans were developed to be followed in ensuring so. These were formed to handle areas of
borrow pit management, campsite management, noise management, dust management, quarry site
management among others.
68 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
8.2 Social
Any development comes with an impact on the people living in the society where the development
is taking place. With this, the social impacts have to be put into consideration during the execution
of works.
The project had Grievance Management Committees at every Local Council to ensure that the
complaints of the local people are addressed accordingly. These committees had the responsibility
to ensure that all the citizens that had to be compensated are paid in time and to organize meetings
to consult the community during the Environmental and social impact assessment. During the
course of the training, a meeting was held with the Katodio community in Wanseko to sensitize
the people about the benefits and opportunities of the project in their area.
8.3 Health
The health of workers was crucial that the project had a Nominated Service Provider to be in
charge of health in terms of controlling the spread of HIV/AIDS through sensitization and
provision of condoms. On addition, all the active working sections had mobile toilets, dust bins,
drinking water and first aid kits. It was the role of the Engineer to ensure that all of this is provided
and ensured through the supervision of works.
8.4 Safety
Mr. Ramadan was the Safety Officer of the Project. Toolbox talks especially at Bridge works used
to happen every evening to ensure that all workers have full Personal Protective Equipment and
69 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
are using it well. The Paraa Bridge being part of the project, safety measures were put in place to
ensure safety of workers during the bridge works. These included falling nets, Safety rings, life
jackets, rescue team boat and ensuring use of full protective equipment during works.
70 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
9.2 CHALLENGES
There were many problems experience during the industrial training period and below are some of
the problems/challenges experienced:
• The industrial training period was so short that I was hindered from learning all the
construction processes. In fact, I had no chance of witnessing the wearing coarse of the
asphalt concrete being constructed.
• Bad weather conditions especially rainfall which gave a lot bottle neck during the
construction process.
• Insecurity since the project was located in Murchison Falls National Park, which brought
fear for animals during the execution of work
• Tsetse flies could bite us especially at Lot 7B towards Murchison Falls.
9.3 RECOMMENDATIONS
To the University;
The industrial training period should be extended so that the students can follow the construction
process. Instead of workshop practice, students can have Industrial Training. This will increase on
their confidence in execution of projects.
To the Engineer;
I recommend the Engineer to admit more students for the next Internship program so that skills
are transferred to the next generation.
71 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
To the Student;
I recommend AECO as one of the best Engineer firm in Uganda because of their organization in
the execution of their Supervision. I therefore call upon students to apply to have Industrial training
with this company.
To the Client;
I recommend UNRA to give the laboratory equipments after the project completion to universities’
materials laboratories.
9.4 CONCLUSIONS
Most of the objectives of the industrial training were achieved making me to say, Engineering is
actually in the field where you see, do and feel the triumph of the work. I was able to learn a lot
about Highway Engineering through exposure to different activities that happens during road
construction.
72 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
References
Central Materials Laboratory. (2000). Laboratory Testing Manual.
MoWT. (2005). Road Design Manual .
MoWT. (2010). General Specifications for Road and Bridge Works.
73 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
APPENDICES
74 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Appendix 1 - Figure 1 : Different tests that were carried out from the Laboratory
75 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
76 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
77 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
78 | P a g e
INDUSTRIAL TRAINING REPORT, JUNE TO AUGUST 2019, JUNE – AUGUST 2019
Appendix 5 - Figure 1: Environmental, social, health and safety measures during construction
79 | P a g e