Professional Documents
Culture Documents
Upper Mast Section Lifting Plan
Upper Mast Section Lifting Plan
Step 1: All persons must visit the actual site and “walk the job” before starting any preparations.
Step 2: Decide what lifting equipment is needed and gather together slings shackles, tag lines,
safety harness & a High Visibility jacket for banksman.
Step 3: Organize the People and equipment and plan the lift using the check list below.
Category of lift –indicate with an X
Simple Routine Complicated Complex: x
Description of lifting operation
Raising the second section of mast using 200t crane and 120t crane
Weight of load: 30t
1
QAF5246 Rev.0
Lifting Plan and Check list
Method Statement
Lifting Method statement (Step by Step)
Steps 1-9 are compulsory
1 Rig manager to delegate preparation & check of lift area: free from unnecessary equipment, obstacles and
debris.
2 Crane Op to verify pre start and dropped object inspection of crane has been completed
3 HSE Officer to verify valid certification of crane Operator, crane and lifting accessories -slings shackles
including color coding and that all lifting accessories have suitable SWL / WLL
4 Rig manager to hold Pre job safety meeting/TBT, assign duties for lifting ops.
5 Rig manager to appoint duty banksman (to wear Hi-vis jacket) and load handlers, agree communications
method between Crane operator and Banksman e.g., hand signals. Verify hand signals including stop and
emergency hold.
Agreed communications will be radios, hand signals
6 Banksman to clear area of all person not involved in the lifting: sign and barrier area as required, maintain
an escape route at all times.
7 Crane Op to Spot crane as per lift drawing and planned lift radius, deploy outriggers fully on spreader
blocks, set crane “off rubber”.
8 Crane Operator to carry out configuration safety and computer checks, implementing any specific
operational requirements as per lift drawings.
9 Check wind speed is not exceeding 9.8 meters per second (22 mph /35kph / 19 knots)
10 Attach the lifting gears to the top of the mast
- Assistant driller and night pusher to wear safety harnesses and use man lift basket to attach web
slings to lifting place (mast supporting beams the 3rd one from the crown block) and check crane
hook is vertical or not.
- Inform commander to slowly pick up hook till web sling get tension by radios (radio will be secured
by safety rope). When crane tension confirmed on upper section by 10 tons
- Disconnect safety pin of beam seat and relative cable while Assistant Driller lowering man lift
basket down
11 Continue tension on sling while lifting, until full raise of the mast
12 Ensure the mast securing pins is connected
13 Derrick man to release the lifting gears after finish the mast raise
The job is not complete until the housekeeping is done: ensure the location is left clean and tidy and return
all slings and shackles to the lifting store.
Close the lifting permit
2
QAF5246 Rev.0
Lifting Plan and Check list
STEP 4
Sketch out the lift
3
QAF5246 Rev.0
Lifting Plan and Check list
6 Steps to Check
Step 4: Note the maximum lift capacity from the Crane chart:
Including boom length, angle and the maximum lift radius.
Step 5: Cross check: Ask Crane operator to check on his crane screen the maximum
weight he can lift: it should match step 4! - If not Stop and take advice
4
QAF5246 Rev.0
Lifting Plan and Check list
Notes
Do you know what the load weighs?
All outrigger must be fully extended and counterweigh must be in place
All block sheaves must be reeved with crane wire for maximum lifts
Always ask HSE / Maintenance to cross check.
Ask the Crane operator to do a final verification check.
5
QAF5246 Rev.0
Lifting Plan and Check list
6
QAF5246 Rev.0
Lifting Plan and Check list
No Sequence of basic job steps Potential accident or hazard Recommendation to eliminate or reduce potential
hazard
1. Preparation - Dropped objects. - Pre-Job visit by lifting team to the site where lifting
- Stuck/crush by equipment, will take place
- Working at height - Verify weather conditions are satisfactory and wind
- Striking object in or above load speed acceptable
path - Valid PTW
- Restricted work areas, - Prepare Lifting plan
- Pinch point, hand injuries. - Pre job meeting
- Authorized and competent personnel only for work.
- Proper Supervision for lifting tasks
- Exclude all persons form lifting work area except for
lifting team.
2. Selection of lifting gears - Crane Failure - Use certified and colour coded lifting gears with
- Dropped objects. sufficient SWL for the purpose.
- Ensure no physical damage available on lifting gears
3. Preparation for lift - Collapse of crane and load - Verify the suitability of lifting gears & crane for the
- Failure of equipment loads to be handled.
- Ensure the area is free from obstacles for crane
operations and ground is properly compacted.
- Spot crane correctly using spreader pads under fully
extended outriggers.
- Conduct safety check of the crane prior to start
lifting.
- Ensure that the load is secured and is free of all
dropped objects.
-
4. Lifting activities - Falling objects from lifted load - Banksman is in charge of the lifting operation
- Electrocution due to work near - Only banksman to signal crane operator
power lines. - Tag lines MUST BE USED to control loads.
- Injury due to crush points - Equipment should not be operated where any of
- load shifting due to incorrect the loads will come within 6.4m of any electrical
rigging, distribution or power line.
- failure due to overloading - All lift to be done in 2 stages the sage 1 is lifting
- high wind until load id 25 cm from ground and banksman to
- poor visibility stop and ensure load is stable, and verify with crane
- Injury to workers operator actual weight. STOP lift if weigh is different
to expected weight and investigate
- Banks man to wear high visible vest during lifting
operation
- Continue tension on sling while lifting
5. Post job House keeping - Remove, slings shackles and return to safe storage
- Make the area clean and tidy.
7
QAF5246 Rev.0