c=.›`.u=.c= ›Ç=e ›=”Í=’]”Ó %L.¾}.¾ÓM TIu`
Ref No: CRBC/BM/ 215/12 Dates: July 31,
2012

TO: Engineer Zewdie Eskinder & Co PLC


Addis Ababa
Attention: Ato Gizachew Kergo, Resident Engineer

Ref: Bole Ring Road RBT to Meskel Sq. Project

Subject: Proposal for backfilling (Olympia Underpass)

Dear Sirs,

As you are well aware, the backfill work for the Olympia Underpass is
undergoing using selected material. However, due to the weather condition,
it is becoming difficult to attain the required moisture content and making
not easy to get good compaction. This has resulted slowing down the
backfilling work which was intended to be completed in short time to give
access for traffic diversion.

Thus, we propose to use rock fill for the depth under 4.0m from the top of
the road elevation and we will use the selected materials for the top part as
shown in the attached drawing.

We are quite sure the proposed method will bring advantage in completing
the work in shorter time while keeping the required quality at the same time.
Hence, we request your prompt approval to proceed the work as proposed.

Thanking you in advance for your cooperation n, we remain.

Sincerely your

Wang Yang
General Manager
Encl: detail drawing (1 page)
CC:
 Addis Ababa City Roads Authority

P.O.Box: 2509 Tel: 00251-4-391971 Fax: 00251-4-392468


Address: Kebele 10, Woreda Akaki Kaliti Sub-City, Addis Ababa, Ethiopia
 Project Manager, Mr. Peng Huan

P.O.Box: 2509 Tel: 00251-4-391971 Fax: 00251-4-392468


Address: Kebele 10, Woreda Akaki Kaliti Sub-City, Addis Ababa, Ethiopia

You might also like