Professional Documents
Culture Documents
226
226
226
Main Form
General
Record Number: CS-00945 Creator: karim hassan
Title
Title: Sa & Prequ Raktherm PolyPropylene GateValve
Submittal Details
Planned Submission Planned Finish Date: 04/26/2021
Date:
Origin: Specialist Supplier /
Integrator:
Description: Sample and
Prequalification of
Raktherm
PolyPropylene Gate
Valve Material
Submittal.
Consultant Comments
Consultant Code: C
Comments: As per attached comments.
Consultant Status Not Approved – Resubmit
on Form:
Page 1 of 3
PMC Comments
PMC Comments: Forward to resubmit as requested.
Cost Consultant Comments
Cost Consultant
Comments:
Other Consultant Comments
Comments:
Emaar Project Director Comments
EMAAR Project
Director Comments:
Emaar MEP Comments
Emaar MEP
Comments:
Emaar FM Comments
EMAAR FM:
Emaar IT Comments
EMAAR IT:
Task Details
From: Task Due Not Applicable Task Notes (0)
Date:
Cc: ahmed fouad
Sent For: End (CA)
Workflow Progress
Page 2 of 3
Step Name Assignee Company Status Action Completion Date
Contractor karim hassan FORW_MSA Completed Send for 04/26/2021 10:01 AM
Supervision
consltant
Review
Submittal Details
0 Item(s)
Document Document
No. File Name Status Revision Revision Date
Type Number.
Page 3 of 3
Contract Submittals
Main Form
General
Record Number: CS-01076 Creator: karim hassan
Title
Title: Sample Gate Valve for water meter32mm of RAK therm
Submittal Details
Planned Submission Planned Finish Date: 05/23/2021
Date:
Origin: Specialist Supplier /
Integrator:
Description: Sample for Gate Valve
for water meter:32mm
of (RAK therm)
Consultant Comments
Consultant Code: B
Comments: submit warranty certificate with supply.
Consultant Status Approved as Noted
on Form:
PMC Comments
PMC Comments: Forward to cover SC comments.
Page 1 of 3
Cost Consultant Comments
Cost Consultant
Comments:
Other Consultant Comments
Comments:
Emaar Project Director Comments
EMAAR Project
Director Comments:
Emaar MEP Comments
Emaar MEP
Comments:
Emaar FM Comments
EMAAR FM:
Emaar IT Comments
EMAAR IT:
Task Details
From: Task Due Not Applicable Task Notes (0)
Date:
Cc: ahmed fouad
Sent For: End (CA)
Workflow Progress
Page 2 of 3
Step Name Assignee Company Status Action Completion Date
Contractor karim hassan FORW_MSA Completed Send for 05/23/2021 03:59 PM
Supervision
consltant
Review
Submittal Details
0 Item(s)
Document Document
No. File Name Status Revision Revision Date
Type Number.
Page 3 of 3
Confirmation of Verbal Instructions
Main Form
General
Record Number: CVI-00002 Creator: Osama Saadawi
Reference Number: 02 CC To:
Title
Title: modifications of paths for mechanical systems B24
Description: As per verbal instructions, please confirm the modifications of paths for water supply
system, drainage system and firefighting system between Retail 7 and building 24
Response from the Consultant
Consultant To be coordinated with tenant shop drawing.
Comments: To be coordinated with existing site condition.
To be coordinated with Arch. and landscape works.
To be coordinated with other trades.
Response from the PMC
PMC Comments: Forward to cover SC comments.
Response from the Client
Comments: Approve
Submittal Information
Submittal Type: Document Submittal Spec Section:
Submittal For Closeout: Drawing No:
Revision:
Page 1 of 3
Delivered Via
Delivered Via: Tracking No:
Date Shipped: Expected Delivery:
Remarks
Remarks:
Task Details
From: Task Due Not Applicable Task Notes (0)
Date:
Cc: Osama Saadawi; ahmed fouad
Sent For: End (CA)
Workflow Progress
Step Name Assignee Company Status Action Completion Date
Initiation Osama Saada FORW_MSA Completed Send for 06/30/2021 04:47 PM
wi Confirmation
Page 2 of 3
Page 3 of 3
Confirmation of Verbal Instructions
Main Form
General
Record Number: CVI-00003 Creator: Osama Saadawi
Reference Number: 03 CC To:
Title
Title: New Fire Alarm Devices for all Retails
Description: Please check this CVI for new fire alarm devices for all retails
(As per consultant verbal instruction and emaar meeting held at 11, June,2021 it’s
required to :
-Supply and install all fire alarm devices for all retails according to the quantities
required for each retail as per owner requirements, and the attached files contains
the fire alarm quantities required for retails (Damas,Pinko,Twinset and Eli french).
please confirm.)
Response from the Consultant
Consultant - Confirm
Comments:
Response from the PMC
PMC Comments:
Response from the Client
Comments:
Submittal Information
Submittal Type: Spec Section:
Submittal For Closeout: Drawing No:
Discipline: Reference ID:
Revision:
Page 1 of 2
Delivered Via
Delivered Via: Tracking No:
Date Shipped: Expected Delivery:
Remarks
Remarks:
Task Details
From: Task Due Not Applicable Task Notes (0)
Date:
Cc:
Sent For: PMC Confirmation
Workflow Progress
Step Name Assignee Company Status Action Completion Date
Initiation Osama Saada FORW_MSA Completed Send for 07/03/2021 10:48 AM
wi Confirmation
Page 2 of 2
Confirmation of Verbal Instructions
Main Form
General
Record Number: CVI-00004 Creator: Osama Saadawi
Reference Number: 04 CC To:
Title
Title: Add the Cable Tray in Retails
Description: Please check this CVI for add the cable tray in retails
(as per consultant verbal instruction it's required to add cable tray for retails feeders
size 15 cm for each retail from top of panel board to false ceiling.
please confirm.)
Response from the Consultant
Consultant - Confirm
Comments:
Response from the PMC
PMC Comments:
Response from the Client
Comments:
Submittal Information
Submittal Type: Spec Section:
Submittal For Closeout: Drawing No:
Discipline: Reference ID:
Revision:
Page 1 of 2
Delivered Via
Delivered Via: Tracking No:
Date Shipped: Expected Delivery:
Remarks
Remarks:
Task Details
From: Task Due Not Applicable Task Notes (0)
Date:
Cc:
Sent For: PMC Confirmation
Workflow Progress
Step Name Assignee Company Status Action Completion Date
Initiation Osama Saada FORW_MSA Completed Send for 07/03/2021 10:50 AM
wi Confirmation
Page 2 of 2
Confirmation of Verbal Instructions
Main Form
General
Record Number: CVI-00009 Creator: Osama Saadawi
Reference Number: 09 CC To:
Title
Title: Increasing Elec Routes Under SOG all Buildings
Description: As per consultant verbal instruction it’s required to :
Increasing the electrical Routes (Power and Low current Feeders) Under Slab on
Grade for all Buildings ,result of changing the electrical Routes Under SOG to
another side in the buildings To match the path of infrastructure cable feeders, please
confirm.)
Response from the Consultant
Consultant Not accepted, any change for routing required to coordinate with infra package.
Comments:
Response from the PMC
PMC Comments:
Response from the Client
Comments:
Submittal Information
Submittal Type: Spec Section:
Submittal For Closeout: Drawing No:
Revision:
Page 1 of 2
Delivered Via
Delivered Via: Tracking No:
Date Shipped: Expected Delivery:
Remarks
Remarks:
Task Details
From: Task Due Not Applicable Task Notes (0)
Date:
Cc:
Sent For: PMC Confirmation
Workflow Progress
Step Name Assignee Company Status Action Completion Date
Initiation Osama Saada FORW_MSA Completed Send for 08/01/2021 10:40 AM
wi Confirmation
Page 2 of 2
Request for Information (RFI)
Main Form
General
Record Number: RFI-00007 Creator: karim hassan
Title
Title: Facade lighting Drawings Conflict PKG#154
RFI Information
Location: General Priority:
Others (Specify):
RFI Description
RFI Description: Facade lighting Drawings Conflict PKG#154
Action Required
Question: According to facade lighting drawings for PKG#154 , found :-
Regarding facade lighting package please clarify:
1- the source of power for each lighting fixture in terraces and building
entrances.
2- whether to remove the old lighting fixtures in terraces and replace it with
the new fixtures or remain both.
Recommended Solution:
Page 1 of 3
Response
Final Response:
Supervision Consultant’s 1. Proceed for all building /floors only with new design DWGs for façade
Response: lightings.
2. As per the façade lighting (SWI) we recommend to cancel the wall
mounted lighting fixtures at the previous lighting design on terrace areas.
3. All fittings installed in the tenants balconies to be operated by residents.
4. Light fittings installed at ground/retail podium level to be controlled
separately from the upper level façade lighting.
PMC Response: Proceed According to SC Reply and Emaar confirmation in Emaar
Response .
Design Consultant
Response:
Cost Consultant
Response:
Emaar Response: Proceed only with Façades lighting and outlets according revised design
DWGs at S1 buildings have been issued through SWI while other facades
outlets at original design to be cancelled.
Lighting fixtures within terraces premises to be controlled by apartments'
clients with the same concept gas been previously applied at R1 and R2.
Task Details
From: Mahmoud El Sayed Task Due Task Notes (0)
Date:
Cc:
Sent For: Contractor Final Review
Workflow Progress
Page 2 of 3
Step Name Assignee Company Status Action Completion Date
Contractor karim hassan FORW_MSA Completed Send to 12/26/2020 12:48 PM
Supervision
Consultant
Page 3 of 3
Request for Information (RFI)
Main Form
General
Record Number: RFI-00015 Creator: karim hassan
Title
Title: Exit sign difference QTY
RFI Information
Location: General Priority:
Others (Specify):
RFI Description
RFI Description: Exit sign difference QTY
Action Required
Question: According to IFC drawings for PKG#154 , found :-
Concerning the exit signs, a difference was found in it`s quantities between
the electrical IFC drawings and the strategic plans in the architectural IFC
drawings. Please clarify which drawings (electrical or architectural) to
proceed accordingly.
Recommended Solution:
Page 1 of 3
Response
Final Response: - The contractor is requested to submit RFP for Exit lighting fixtures
according to strategic plan foe final approval.
Supervision Consultant’s - The contractor is requested to submit RFP for Exit lighting fixtures
Response: according to strategic plan foe final approval.
- Final action for EMAAR design.
PMC Response: - The contractor is requested to submit RFP for Exit lighting fixtures
according to strategic plan foe final approval.
Design Consultant
Response:
Cost Consultant
Response:
Emaar Response:
Task Details
From: Mahmoud El Sayed Task Due Task Notes (0)
Date:
Cc:
Sent For: Contractor Final Review
Workflow Progress
Step Name Assignee Company Status Action Completion Date
Contractor karim hassan FORW_MSA Completed Send to 02/02/2021 02:21 PM
Supervision
Consultant
Page 2 of 3
Page 3 of 3
Request for Information (RFI)
Main Form
General
Record Number: RFI-00017 Creator: karim hassan
Title
Title: EXTERNAL OPENING CONFILICTION
RFI Information
Location: General Priority:
Others (Specify):
RFI Description
RFI Description: EXTERNAL OPENING CONFILICTION
Page 1 of 4
Action Required
Question: According to received IFC drawing no: -
S1S2-( T1.A , T2.A , T1.B & T2.C ) 100 ,101 ,102 ,103 ,104
WE found five main cases of conflict opening with some other cases
the Main cases are:
*Case 1-the opening no on plan not match with opening schedule
*Case 2-the opening no on plan not match with elevation
*Case 3-the opening on plan and elevation not found on opening schedule
we need to add a new type
*Case 4-the opening no not found on plan
*Case 5-the opening on plan is window but on elevation is door (terrace &
ground floor)
- Building 17:-
-Case 1 (point 2,3,8,9,14,16,19,21,24,25,28,30,33,36,37,39,40,42,43)
-Case 2 (point 5,6,11,12,15,16,19,22,24,25,28,31,33,34,39,44,46)
-Case 3 (point 7,10,13,17,18,20,23,26,27,29,32,35,38,41,45)
-Case 4 (point 20)
-Case 5 (1,4,5)
-Point 2-we need a door to access mechanical room
-Building 18:-
-Case 1 (point 13)
-Case 2 (point 11)
-Case 5 (1,2,3,4,5,6,7,8,9,10)
-Building 19:-
-Case 1 (point 5,6,7)
-Point (1,2,3,4) better to be a door opening as all the other building to have
access to garden
-Building 20:-
-Case 1 (point 2,6,7,9,11,14,17,18,23,24,25,26,27)
-Case 3(point 3,5,8,10,12,15,16,19,20,21,22,28)
-Case 5 (point 1,3,4,13)
-Building 21:-
-Case 1 (point 7)
-Case 2 (point 1)
-Case 4 (point 6,10)
-Case 5 (point 2,4,5,8,9,11,12,13,14)
-Point 3: drawn wrong in elevation
-Building 23:-
-point 1 – main mechanical room is a single leaf we need it to be a double
leaf according to mechanical department recommendation.
-Point 2-we need a door to access mechanical room
-Point 3-we need to make this window a door to make access to meters
room and give it a number with is comment is typical in all floors
-Point (4,5) - case 3
-Point (6,7) -dimension in schedule differ from drawn we need to update
schedule
-Point (8,11) -this window information was missing in window schedule
-Point (9,10) - case 4
-Building 24:-
-Case 1 (point 1,7,5,4,8)
-Case 3 (point 6,9)
-point 2 (we need to make this window a door to make access to meters
Page 2 of 4
room and give it a number and this comment is typical in all floors)
-Point 3 (we need a door to access mechanical room as the mechanical
department recommendation)
Please advice
Recommended Solution:
Response
Final Response:
Supervision Consultant’s Building No.23
Response: 1&2 / The contractor must send R.F.I Separated between mechanical &
Arch department
3 / what is the reference to say this window follow doors schedule for
service area ( all doors metal doors )
Point 4&5 case 3 / Time & Emaar for action.
Point 6 & 7 the same case point 4 & 5 not found in opening schedule
window type (D15) / Time & Emaar for action.
Point 8 & 11 window type (W07) not found in the opening schedule / Time
& Emaar for action.
Point 9 & 10 / window type (D14) not found in the opening schedule / Time
& Emaar for action.
Building No.24
Case 1 / Point 1&7&5&4&8 / D11 / contractor follow plan size .
Case 3 point 6&9 / door type (D17) not found in opening schedule / Time &
Emaar for action.
Point 2 / what is the reference to say this window follow doors schedule for
service area ( all doors metal doors )
Point 3 / The contractor must send R.F.I Separated between mechanical &
Arch department
For the other buildings mentioned, each building is provided separately
PMC Response: As discussed ,contractor to resubmit after completing the missing data
mentioned at the RFI (doors & windows schedules ,Elevation drawings ) ,in
addition to submit separate RFIS for the following ;-
1- Mechanical room conflicts
2- Electric meters doors conflicts
3- Windows that need to be changed to doors for garden accessibility
Design Consultant
Response:
Cost Consultant
Response:
Emaar Response:
Task Details
From: Wael Badr Eldin Task Due Task Notes (0)
Date:
Page 3 of 4
To: karim hassan Task Status: Not Started
Cc:
Sent For: Contractor Revision / Clarification
Workflow Progress
Step Name Assignee Company Status Action Completion Date
Contractor karim hassan FORW_MSA Completed Send to 02/08/2021 08:17 AM
Supervision
Consultant
Page 4 of 4
Request for Information (RFI)
Main Form
General
Record Number: RFI-00025 Creator: karim hassan
Title
Title: Facades Retail Building (23)
RFI Information
Location: PKG-154 Priority:
Others (Specify):
RFI Description
RFI Description: Facades Retail Building (23)
Action Required
Question: Regarding to the SWI (6) please reply.
* The screen for retail what is the type of matrial & details upper retail area
elevation (2).
Please advice
Recommended Solution:
Page 1 of 3
Response
Final Response: Please follow the new revised drawings and resubmit
Supervision Consultant’s - Contractor should submit sketches to clarify the question.
Response:
PMC Response: Please follow the new revised drawings and resubmit
Design Consultant
Response:
Cost Consultant
Response:
Emaar Response:
Task Details
From: Wael Badr Eldin Task Due Task Notes (0)
Date:
Cc:
Sent For: Contractor Final Review
Workflow Progress
Step Name Assignee Company Status Action Completion Date
Contractor karim hassan FORW_MSA Completed Send to 03/14/2021 04:12 PM
Supervision
Consultant
Page 2 of 3
Page 3 of 3
Request for Information (RFI)
Main Form
Page 1 of 0