Marassi-BP#154-Village S1 Apartment Building-Updated Time Schedule Update

Activity ID Activity Name Original Performance % Start Finish Schedule % BL Project BL Project Total Budgeted Total
Duration Complete Complete Start Finish Float Cost

Marassi-BP#154-Village S1 Apartment Building-U


Marassi 831 43.13% 23-Apr-20 A 18-Mar-23 56.19% 23-Apr-20 24-Oct-22 -124 510,462,820.59
L.E
General
Gener 830 56.55% 23-Apr-20 A 18-Mar-23 56.55% 23-Apr-20 24-Oct-22 -124 48,052,400.00
LE
Milestones
Milest 830 56.55% 23-Apr-20 A 18-Mar-23 56.55% 23-Apr-20 24-Oct-22 -124 48,052,400.00
LE
G00 Signing Contract 0 100% 23-Apr-20 A 100% 23-Apr-20 0.00 L.E
G00 Commencement Date 0 100% 23-Apr-20 A 100% 23-Apr-20 0.00 L.E
G00 Signing Letter of Acceptance 0 100% 23-Apr-20 A 100% 23-Apr-20 0.00 L.E
G00 Handover of "Group 3,(with related landscape and roads) C 0 0% 18-Mar-23* 0% 24-Oct-22 -124 0.00 L.E
G00 Handover of "Groups1,2(with related landscape and roads 0 0% 11-Feb-23* 0% 20-Aug-22 -148 0.00 L.E
G00 Preliminaries 706 56.55% 23-Apr-20 A 18-Mar-23 56.55% 23-Apr-20 24-Oct-22 -124 48,052,400.00
LE
MLS Project Completion Date 0 0% 18-Mar-23* 0% 24-Oct-22 -124 0.00 L.E
MLS Completion of Skeleton, Infrastructure and Facades work fo 0 0% 27-Mar-22* 0% 08-Nov-21 -115 0.00 L.E
Key Dates
D 819 0% 23-Apr-20 A 05-Mar-23 0% 23-Apr-20 24-Oct-22 -113 0.00 L.E

Engine
Engineering 606 0% 23-Apr-20 A 14-Jun-22 0% 23-Apr-20 04-Jun-22 97 0.00 L.E

Procurement
Procur 600 0% 11-May-20 A 19-Jun-22 0% 11-May-20 28-May-22 93 5,406,037.00
LE
Mockup Apartment Construction
Mocku 259 0% 25-Jan-21 A 22-Dec-21 0% 30-Nov-20 27-Feb-21 236 0.00 L.E

Construction
Constr 801 42.23% 23-Apr-20 A 11-Feb-23 56.81% 23-Apr-20 29-Sep-22 -113 457,004,383.59
LE
Group 1 ( Buildings 23 & 24) 786 49.92% 23-Apr-20 A 23-Jan-23 60.69% 23-Apr-20 19-Jul-22 -132 116,494,376.02
LE
Bui
Building 23 (Type T1B) 786 48.98% 23-Apr-20 A 23-Jan-23 61.05% 23-Apr-20 06-Jul-22 -132 56,028,279.76
General 784 0% 23-Apr-20 A 23-Jan-23 0% 23-Apr-20 06-Jul-22 -132 0.00 L.E L E
Receive Building Construction Permit 1 100% 23-Apr-20 A 15-Aug-20 A 100% 23-Apr-20 23-Apr-20 0.00 L.E
Finish Complete Building 23 0 0% 23-Jan-23 0% 06-Jul-22 -132 0.00 L.E
Sub-Structure 230 100% 09-Aug-20 A 22-Apr-21 A 100% 03-Jun-20 26-Oct-20 7,254,599.00
Earth Works 181 100% 09-Aug-20 A 11-Feb-21 A 100% 03-Jun-20 10-Sep-20 LE
1,517,629.00
Foundations 200 100% 01-Sep-20 A 22-Apr-21 A 100% 09-Jul-20 26-Oct-20 LE
5,736,970.00
Super-Structure 669 41.39% 05-Oct-20 A 23-Jan-23 55.25% 11-Aug-20 06-Jul-22 -132 LE
48,773,680.76
Ground Floor (23) 588 47.18% 05-Oct-20 A 27-Oct-22 57.49% 11-Aug-20 04-Jul-22 -57 LE
8,497,132.14
First Floor (23) 559 43.6% 23-Nov-20 A 08-Nov-22 53.27% 08-Sep-20 29-Jun-22 -67 LE
7,248,423.14
Second Floor (23) 554 42.48% 29-Dec-20 A 07-Dec-22 51.87% 07-Oct-20 29-Jun-22 -92 LE
7,248,423.14
Third Floor (23) 558 41.86% 19-Jan-21 A 31-Dec-22 53.27% 07-Nov-20 29-Jun-22 -112 LE
7,248,423.14
Fourth Floor (23) 553 40.55% 15-Feb-21 A 23-Jan-23 50.51% 05-Dec-20 06-Jul-22 -132 LE
7,482,924.14
Roof Floor (23) 371 67.01% 13-Mar-21 A 04-Jul-22 76.75% 02-Jan-21 04-Jul-22 32 LE
2,677,169.06
LE
Page 1 of 5 [filter_list
Marassi-BP#154-Village S1 Apartment Building-Updated Time Schedule Update

Activity ID Activity Name Original Performance % Start Finish Schedule % BL Project BL Project Total Budgeted Total
Duration Complete Complete Start Finish Float Cost

Elevator Shafts 15 0% 24-May-22 09-Jun-22 0% 24-May-22 09-Jun-22 52 774,400.00 L.E


Chute Room 27 0% 24-May-22 23-Jun-22 0% 24-May-22 23-Jun-22 40 470,645.00 L.E
MEP Shafts 100 0% 27-Jan-22 06-Jun-22 39.72% 05-Sep-21 25-May-22 55 819,716.00 L.E
HVAC Ducts Shaft 20 0% 24-May-22 15-Jun-22 0% 24-May-22 15-Jun-22 37 1,239,416.00
Facade Finishes 256 50.69% 30-Mar-21 A 22-Feb-22 100% 07-Mar-21 01-Sep-21 -86 LE
4,007,939.00
Stairs and Service Area 137 4.4% 25-Sep-21 A 29-Jun-22 39.12% 28-Jun-21 29-Jun-22 35 LE
1,059,070.00
Building 24 (Type T2C)
Bui 750 50.8% 23-Apr-20 A 12-Dec-22 60.36% 23-Apr-20 19-Jul-22 -96 LE
60,466,096.26
General 748 0% 23-Apr-20 A 12-Dec-22 0% 23-Apr-20 19-Jul-22 -96 0.00 L.E L E
Receive Building Construction Permit 1 100% 23-Apr-20 A 23-Apr-20 A 100% 23-Apr-20 23-Apr-20 0.00 L.E
Finish Complete Building 24 0 0% 12-Dec-22 0% 19-Jul-22 -96 0.00 L.E
Sub-Structure 256 100% 03-Jun-20 A 27-May-21 A 100% 03-Jun-20 31-Oct-20 9,277,122.00
Earth Works 171 100% 03-Jun-20 A 14-Mar-21 A 100% 03-Jun-20 16-Sep-20 LE
2,156,217.00
Foundations 230 100% 05-Jul-20 A 27-May-21 A 100% 05-Jul-20 31-Oct-20 LE
7,120,905.00
Super-Structure 672 41.88% 12-Aug-20 A 12-Dec-22 53.17% 22-Aug-20 19-Jul-22 -96 LE
51,188,974.26
Ground Floor (24) 591 48.7% 12-Aug-20 A 13-Sep-22 51.91% 22-Aug-20 04-Jul-22 -21 LE
9,532,830.42
First Floor (24) 539 44.44% 22-Oct-20 A 13-Sep-22 55.58% 20-Sep-20 29-Jun-22 -21 LE
8,039,131.50
Second Floor (24) 508 43.12% 29-Dec-20 A 15-Oct-22 55.58% 19-Oct-20 29-Jun-22 -46 LE
8,039,132.09
Third Floor (24) 507 41.75% 23-Jan-21 A 13-Nov-22 55.58% 18-Nov-20 29-Jun-22 -71 LE
8,039,132.09
Fourth Floor (24) 519 38.78% 17-Feb-21 A 12-Dec-22 55.58% 15-Dec-20 19-Jul-22 -96 LE
8,039,132.09
Roof Floor (24) 364 62.38% 21-Mar-21 A 04-Jul-22 71.78% 12-Jan-21 04-Jul-22 32 LE
3,395,823.06
Elevator Shafts 33 0% 07-Aug-22 13-Sep-22 0% 24-May-22 02-Jul-22 -21 LE
774,400.00 L.E
Chute Room 27 0% 24-May-22 23-Jun-22 0% 24-May-22 23-Jun-22 40 451,810.00 L.E
MEP Shafts 153 0% 27-Jan-22 17-Aug-22 38.4% 05-Sep-21 25-May-22 2 820,377.00 L.E
HVAC Ducts Shaft 20 0% 24-May-22 15-Jun-22 0% 24-May-22 15-Jun-22 37 943,778.00 L.E
Facade Finishes 254 66.62% 07-Apr-21 A 28-Feb-22 100% 28-Feb-21 17-Aug-21 -92 1,644,873.00
Stairs and Service Area 85 4.62% 28-Sep-21 A 20-Jul-22 0% 26-Oct-21 29-Jun-22 24 LE
1,468,555.00
Group 2 ( Buildings 17 & 18) 749 40.25% 01-Jul-20 A 11-Feb-23 62.51% 13-Jul-20 20-Aug-22 -148 LE
136,585,280.60
LE
Bui
Building 17 ( Type T1A) 709 39.51% 01-Jul-20 A 26-Dec-22 49.97% 13-Jul-20 20-Aug-22 -108 67,339,446.28
General 703 0% 01-Jul-20 A 26-Dec-22 0% 13-Jul-20 20-Aug-22 -108 0.00 L.E L E
Receive Building Construction Permit 1 100% 01-Jul-20 A 01-Jul-20 A 100% 13-Jul-20 14-Jul-20 0.00 L.E
Finish Complete Building 17 0 0% 26-Dec-22 0% 20-Aug-22 -108 0.00 L.E
Sub-Structure 317 100% 02-Jul-20 A 13-Sep-21 A 100% 14-Jul-20 03-Dec-20 8,046,814.00
Earth Works 151 100% 02-Jul-20 A 14-Mar-21 A 100% 14-Jul-20 28-Oct-20 LE
1,812,462.00
Foundations 291 100% 18-Jul-20 A 13-Sep-21 A 100% 24-Aug-20 03-Dec-20 LE
6,234,352.00
LE

Page 2 of 5 [filter_list
Marassi-BP#154-Village S1 Apartment Building-Updated Time Schedule Update

Activity ID Activity Name Original Performance % Start Finish Schedule % BL Project BL Project Total Budgeted Total
Duration Complete Complete Start Finish Float Cost

Super-Structure 658 31.3% 29-Aug-20 A 26-Dec-22 43.19% 22-Sep-20 20-Aug-22 -108 59,292,632.28
Ground Floor 598 39.02% 29-Aug-20 A 24-Oct-22 49.16% 22-Sep-20 04-Jul-22 -54 LE
10,505,638.18
First Floor 526 33.69% 15-Nov-20 A 22-Sep-22 37.78% 19-Oct-20 29-Jun-22 -29 LE
9,448,285.21
Second Floor 518 32.76% 26-Dec-20 A 23-Oct-22 36.67% 14-Nov-20 29-Jun-22 -53 LE
9,448,285.21
Third Floor 518 31.24% 25-Jan-21 A 20-Nov-22 35.81% 14-Dec-20 02-Aug-22 -77 LE
9,671,080.21
Fourth Floor 510 28.84% 06-Mar-21 A 18-Dec-22 36.09% 13-Jan-21 20-Aug-22 -101 LE
9,448,285.21
Roof Floor 492 56.51% 04-Apr-21 A 26-Dec-22 73.76% 14-Feb-21 04-Jul-22 -108 LE
3,303,568.25
Elevator Shafts 34 0% 22-Sep-22 03-Nov-22 0% 30-May-22 16-Jul-22 -63 LE
1,557,372.00
Chute Room 27 0% 24-May-22 23-Jun-22 0% 24-May-22 23-Jun-22 40 LE
421,674.00 L.E
MEP Shafts 194 0% 27-Jan-22 04-Oct-22 2.73% 05-Sep-21 21-Jul-22 -39 679,245.00 L.E
HVAC Ducts Shaft 20 0% 24-May-22 15-Jun-22 0% 24-May-22 15-Jun-22 37 148,494.00 L.E
Facade Finishes 198 13.32% 21-Jun-21 A 20-Mar-22 100% 18-Mar-21 16-Sep-21 -109 4,079,230.00
Stairs and Service Area 85 4.09% 22-Sep-21 A 30-Aug-22 0% 14-Oct-21 27-Jul-22 -9 LE
581,475.00 L.E
Building 18 ( Type T2A)
Bui 738 40.98% 22-Aug-20 A 11-Feb-23 74.69% 26-Jul-20 20-Aug-22 -148 69,245,834.32
General 732 0% 22-Aug-20 A 11-Feb-23 0% 26-Jul-20 20-Aug-22 -148 0.00 L.E L E
Receive Building Construction Permit 1 100% 22-Aug-20 A 22-Aug-20 A 100% 26-Jul-20 27-Jul-20 0.00 L.E
Finish Complete Building 18 0 0% 11-Feb-23 0% 20-Aug-22 -148 0.00 L.E
Sub-Structure 287 100% 24-Aug-20 A 28-Sep-21 100% 27-Jul-20 17-Dec-20 22 8,549,460.00
Earth Works 182 100% 24-Aug-20 A 28-Sep-21 100% 27-Jul-20 31-Oct-20 22 LE
1,818,326.00
Foundations 246 100% 22-Sep-20 A 13-Jul-21 A 100% 05-Sep-20 17-Dec-20 LE
6,731,134.00
Super-Structure 660 32.66% 07-Nov-20 A 11-Feb-23 71.13% 04-Oct-20 20-Aug-22 -148 LE
60,696,374.32
Ground Floor 646 34.82% 07-Nov-20 A 01-Feb-23 85.45% 04-Oct-20 10-Aug-22 -140 LE
11,399,607.46
First Floor 577 34.08% 02-Jan-21 A 07-Jan-23 84.46% 01-Nov-20 06-Jul-22 -118 LE
10,077,480.15
Second Floor 521 33.45% 04-Feb-21 A 01-Dec-22 78.66% 19-Nov-20 18-Jun-22 -87 LE
10,077,215.15
Third Floor 464 33.03% 08-Mar-21 A 27-Oct-22 57.05% 22-Dec-20 18-Jun-22 -57 LE
10,077,215.15
Fourth Floor 407 29.15% 08-Apr-21 A 20-Sep-22 46.33% 16-Jan-21 18-Jun-22 -27 LE
10,351,685.15
Roof Floor 159 64.12% 05-May-21 A 23-Nov-21 100% 14-Feb-21 19-Jun-21 206 LE
3,474,064.92
Elevator Shafts 33 0% 03-Jan-23 11-Feb-23 0% 03-Jul-22 20-Aug-22 -148 LE
1,548,800.00
Chute Room 27 0% 28-Sep-21 31-Oct-21 100% 03-Apr-21 18-May-21 226 LE
414,140.00 L.E
MEP Shafts 322 0% 08-Dec-21 15-Jan-23 100% 21-Apr-21 21-Jul-22 -125 585,367.35 L.E
HVAC Ducts Shaft 20 0% 10-Nov-21 02-Dec-21 100% 03-Apr-21 04-May-21 188 148,494.00 L.E
Facade Finishes 122 24.7% 03-Aug-21 A 06-Feb-22 100% 11-Apr-21 07-Sep-21 -74 1,827,280.00
Stairs and Service Area 85 3.46% 11-Sep-22 A 21-Dec-22 0% 26-Feb-22 19-Jun-22 -104 LE
715,025.00 L.E
Group 3 ( Buildings 19,20 and 21) 697 39.15% 01-Jul-20 A 15-Jan-23 50.79% 25-Aug-20 29-Sep-22 -90 203,924,726.97
LE
Building 19 ( Type T1A)
Bui 630 37.63% 01-Jul-20 A 27-Oct-22 49.9% 25-Aug-20 29-Sep-22 -23 67,339,446.28
LE
Page 3 of 5 [filter_list
Marassi-BP#154-Village S1 Apartment Building-Updated Time Schedule Update

Activity ID Activity Name Original Performance % Start Finish Schedule % BL Project BL Project Total Budgeted Total
Duration Complete Complete Start Finish Float Cost

General 624 0% 01-Jul-20 A 27-Oct-22 0% 25-Aug-20 29-Sep-22 -23 0.00 L.E


Receive Building Construction Permit 1 100% 01-Jul-20 A 01-Jul-20 A 100% 25-Aug-20 26-Aug-20 0.00 L.E
Finish Complete Building 19 0 0% 27-Oct-22 0% 29-Sep-22 -23 0.00 L.E
Sub-Structure 314 100% 29-Jul-20 A 29-Sep-21 A 100% 26-Aug-20 09-Jan-21 8,046,814.00
Earth Works 195 100% 29-Jul-20 A 24-Jul-21 A 100% 26-Aug-20 02-Dec-20 LE
1,812,462.00
Foundations 290 100% 15-Sep-20 A 29-Sep-21 A 100% 26-Sep-20 09-Jan-21 LE
6,234,352.00
Super-Structure 582 29.17% 21-Oct-20 A 27-Oct-22 43.1% 07-Nov-20 29-Sep-22 -23 LE
59,292,632.28
Ground Floor 526 35.99% 21-Oct-20 A 28-Aug-22 48.13% 07-Nov-20 23-Aug-22 28 LE
10,728,433.18
First Floor 413 31.57% 20-Feb-21 A 10-Aug-22 36.67% 05-Dec-20 29-Jun-22 43 LE
9,448,285.21
Second Floor 406 29.09% 17-Mar-21 A 28-Aug-22 36.67% 04-Jan-21 05-Jul-22 28 LE
9,448,285.21
Third Floor 411 28.84% 07-Apr-21 A 26-Sep-22 36.67% 07-Feb-21 18-Aug-22 3 LE
9,448,285.21
Fourth Floor 423 28.84% 02-May-21 A 27-Oct-22 36.67% 08-Mar-21 29-Sep-22 -23 LE
9,448,285.21
Roof Floor 294 58.67% 23-Jun-21 A 04-Jul-22 73.76% 05-Apr-21 04-Jul-22 67 LE
3,303,568.25
Elevator Shafts 32 0% 21-Jul-22 29-Aug-22 0% 24-Jul-22 31-Aug-22 27 LE
1,557,372.00
Chute Room 27 0% 24-May-22 23-Jun-22 0% 24-May-22 23-Jun-22 75 LE
421,674.00 L.E
MEP Shafts 174 0% 27-Jan-22 11-Sep-22 2.73% 05-Sep-21 13-Sep-22 16 679,245.00 L.E
HVAC Ducts Shaft 20 0% 24-May-22 15-Jun-22 0% 24-May-22 15-Jun-22 72 148,494.00 L.E
Facade Finishes 134 7.15% 07-Aug-21 A 01-Mar-22 100% 20-May-21 11-Sep-21 -93 4,079,230.00
Stairs and Service Area 85 4.09% 22-Sep-21 A 24-Aug-22 0% 09-May-22 27-Aug-22 31 LE
581,475.00 L.E
Building 20 ( Type T1A)
Bui 685 39.85% 08-Sep-20 A 15-Jan-23 51.65% 08-Sep-20 29-Sep-22 -90 67,339,446.28
General 679 0% 08-Sep-20 A 15-Jan-23 0% 08-Sep-20 29-Sep-22 -90 0.00 L.E L E
Receive Building Construction Permit 1 100% 08-Sep-20 A 09-Sep-20 A 100% 08-Sep-20 09-Sep-20 0.00 L.E
Finish Complete Building 20 0 0% 15-Jan-23 0% 29-Sep-22 -90 0.00 L.E
Sub-Structure 239 100% 20-Sep-20 A 28-Jun-21 A 100% 09-Sep-20 12-Jan-21 8,046,814.00
Earth Works 153 100% 20-Sep-20 A 29-Mar-21 A 100% 09-Sep-20 05-Dec-20 LE
1,812,462.00
Foundations 211 100% 13-Oct-20 A 28-Jun-21 A 100% 11-Oct-20 12-Jan-21 LE
6,234,352.00
Super-Structure 628 31.68% 19-Nov-20 A 15-Jan-23 45.09% 09-Nov-20 29-Sep-22 -90 LE
59,292,632.28
Ground Floor 613 37.99% 19-Nov-20 A 04-Jan-23 51.91% 09-Nov-20 20-Sep-22 -82 LE
10,728,433.18
First Floor 529 33.82% 05-Jan-21 A 15-Nov-22 43.02% 05-Dec-20 08-Aug-22 -39 LE
9,448,285.21
Second Floor 516 33.02% 09-Feb-21 A 30-Nov-22 41.58% 31-Dec-20 29-Jun-22 -52 LE
9,448,285.21
Third Floor 452 30.93% 13-Mar-21 A 18-Oct-22 41.58% 02-Feb-21 17-Jul-22 -15 LE
9,448,285.21
Fourth Floor 400 29.09% 07-Apr-21 A 11-Sep-22 41.39% 07-Mar-21 29-Jun-22 16 LE
9,448,285.21
Roof Floor 307 59.39% 25-May-21 A 04-Jul-22 73.76% 01-Apr-21 04-Jul-22 67 LE
3,303,568.25
Elevator Shafts 33 0% 07-Dec-22 15-Jan-23 0% 22-Aug-22 29-Sep-22 -90 LE
1,557,372.00
LE

Page 4 of 5 [filter_list
Marassi-BP#154-Village S1 Apartment Building-Updated Time Schedule Update

Activity ID Activity Name Original Performance % Start Finish Schedule % BL Project BL Project Total Budgeted Total
Duration Complete Complete Start Finish Float Cost

Chute Room 27 0% 24-May-22 23-Jun-22 0% 24-May-22 23-Jun-22 75 421,674.00 L.E


MEP Shafts 256 0% 27-Jan-22 18-Dec-22 2.73% 05-Sep-21 03-Sep-22 -67 679,245.00 L.E
HVAC Ducts Shaft 20 0% 24-May-22 15-Jun-22 0% 24-May-22 15-Jun-22 72 148,494.00 L.E
Facade Finishes 176 18.06% 01-Aug-21 A 27-Mar-22 70.52% 19-May-21 08-Nov-21 -115 4,079,230.00
Stairs and Service Area 100 4.09% 22-Sep-21 A 05-Nov-22 0% 20-Mar-22 27-Jul-22 -30 LE
581,475.00 L.E
Building 21 ( Type T2A)
Bui 594 39.96% 28-Jul-20 A 10-Oct-22 50.81% 19-Sep-20 29-Sep-22 -7 69,245,834.42
General 588 0% 28-Jul-20 A 10-Oct-22 0% 19-Sep-20 29-Sep-22 -7 0.00 L.E L E
Receive Building Construction Permit 1 100% 28-Jul-20 A 28-Aug-20 A 100% 19-Sep-20 19-Sep-20 0.00 L.E
Finish Complete Building 21 0 0% 10-Oct-22 0% 29-Sep-22 -7 0.00 L.E
Sub-Structure 315 100% 29-Jul-20 A 29-Sep-21 A 100% 20-Sep-20 21-Jan-21 8,549,460.00
Earth Works 158 100% 29-Jul-20 A 31-May-21 A 100% 20-Sep-20 15-Dec-20 LE
1,818,326.00
Foundations 297 100% 12-Sep-20 A 29-Sep-21 A 100% 21-Oct-20 21-Jan-21 LE
6,731,134.00
Super-Structure 563 31.51% 26-Oct-20 A 10-Oct-22 43.88% 18-Nov-20 29-Sep-22 -7 LE
60,696,374.42
Ground Floor 550 34.04% 26-Oct-20 A 29-Sep-22 44.34% 18-Nov-20 18-Jun-22 0 LE
11,399,607.47
First Floor 410 33.08% 14-Jan-21 A 23-Jun-22 37.53% 15-Dec-20 18-Jun-22 75 LE
10,077,480.17
Second Floor 409 31.82% 23-Feb-21 A 09-Aug-22 36.54% 13-Jan-21 06-Sep-22 44 LE
10,351,685.17
Third Floor 406 33.14% 16-Feb-21 A 04-Sep-22 37.53% 14-Feb-21 29-Sep-22 22 LE
10,077,215.17
Fourth Floor 400 29.95% 04-May-21 A 29-Sep-22 37.53% 13-Mar-21 07-Sep-22 0 LE
10,077,215.17
Roof Floor 126 57.27% 16-Jun-21 A 01-Dec-21 100% 10-Apr-21 29-Jul-21 234 LE
3,474,064.92
Elevator Shafts 32 0% 31-Aug-22 10-Oct-22 0% 09-Apr-22 28-May-22 -7 LE
1,548,800.00
Chute Room 27 0% 28-Sep-21 31-Oct-21 100% 19-May-21 20-Jun-21 261 LE
414,140.00 L.E
MEP Shafts 216 0% 08-Dec-21 12-Sep-22 100% 05-Jun-21 12-Sep-22 15 585,367.35 L.E
HVAC Ducts Shaft 20 0% 10-Nov-21 02-Dec-21 100% 19-May-21 12-Jun-21 223 148,494.00 L.E
Facade Finishes 113 13.3% 21-Aug-21 A 01-Feb-22 100% 27-May-21 27-Sep-21 -70 1,827,280.00
Stairs and Service Area 85 3.46% 22-Sep-21 A 08-Aug-22 0% 01-Dec-21 14-Mar-22 45 LE
715,025.00 L.E
Handing Over Process
Handi 136 0% 10-Oct-22 18-Mar-23 0% 07-Jul-22 24-Oct-22 -124 0.00 L.E