Item Description SC’s DHK’s Details

No. Scope Scope

1. General

1.1 Power supply including Main DB, DHK to supply 110V to


reticulations (max distance: 25m work area

from working area) and
consumption.

1.2 Extension leads and electrical All extensions and


tools. √ electrical tools to be color
code tagged

1.3 Water supply General water supply by



DHK if necessary

1.4 Hoses To be supplied by SC if



necessary

1.5 Horizontal transportation The Contractor provide


(transportation between areas at tower crane for the
ground level) Subcontract Works.

If the tower crane does


√ not cover Subcontract
Works, the Subcontractor
will provide crane lorry for
internal transportation for
the Subcontract Works
within the Site.

1.6 Vertical transportation The Contractor provide


(transportation between different √ tower crane for the
levels) Subcontract Works.

1.7 Loading and offloading √

1.8 Lifting gears (chains) By the Subcontractor for



crane lorry.

1.9 Other Lifting gears (straps, slings



and the like)
Item Description SC’s DHK’s Details
No. Scope Scope

1.10 Concrete pump, concrete pump Concrete pump truck


truck, skip supplied by Contractor,
√ others including horizontal
pipe lines connection by
Subcontractor

1.11 Vibrators & associated equipment



for concreting works

1.12 All necessary small equipment and



tools for concreting works

1.13 General lighting √

1.14 Specific lighting (work area) √

1.15 Supply of scaffolding √

1.16 Installation of scaffolding for the



subcontractor and the steel fixers

1.17 Supply of lockers for



subcontractor’s workers

1.18 Supply of site office & changing The Contractor will


rooms provide the containers for
√ rental and the rental
charges will be deducted
from the Subcontractor.

1.19 Main Security √ Access control, guards

1.20 Specific Security The Contractor is not



responsible for thefts

1.21 Safety In accordance with this



Subcontract

1.22 Collective safety protection of the handrails, access and the



work area like
Item Description SC’s DHK’s Details
No. Scope Scope

1.23 PPEs for Subcontractor’s workers The Contractor will


provide PPE and the
√ related charges will be
deducted from the
Subcontractor.

1.25 Waste management: collect and Waste to be segregated


dumping of waste to refuse point √ as requested by the
Contractor

1.26 Survey & setting out √

1.27 Housekeeping √

1.28 Dewatering √

1.29 Maintenance of the dewatering



system once installed

1.30 Testing cubes casting and slump Contractor will arrange


testing authorized person to lead
Subcontractor workers to
marking cube and
√ conduct slump test. The
concrete testing after
cube making will be
conducted in Government
laboratory

1.31 Testing and certificates as required


by the Employer’s requirements,

and/or as required by relevant
Government Authorities.

1.32 CIC and PCFB levy √ 0.68%


Item Description SC’s DHK’s Details
No. Scope Scope

2. Material

2.1 Supply of plywood formworks To be compliant with GS


(including boxing out), propping, and ER.
safety, working platform

Boxing out not exceeding
300x300mm are including
in formworks unit rate

2.2 Supply of false works √

2.3 Supply of release agent, retarder & To be compliant with GS


curing products √ and ER. To use the
approved products.

2.4 Supply of hi-rib for construction To be compliant with GS



joint and ER

2.5 Supply of tie rods & watertight tie To be compliant with GS


rods for underground plantrooms √ and ER
and pits

2.6 Supply of concrete √ 3% of wastage allowed.

2.7 Supply of patching system To be compliant with GS


(including sealant or glue) to fill in √ and ER and to be the
voids created by tie rods. approved products

2.8 Supply of concrete repair materials To be compliant with GS


if necessary. √ and ER and to be the
approved products.

3. Installation

3.1 Installation, maintenance, Boxing out not exceeding


certification, modification, removal / 300x300mm are including
disposal of formworks (including √ in formworks unit rate
boxing out), falseworks, propping,
working platform, scaffolding
Item Description SC’s DHK’s Details
No. Scope Scope

3.2 Apply and/or removal as required


by the Contractor of all necessary

hi-rib, release agent, retarder,
curing products

3.3 Casting of concrete √

3.4 Removal of any “plastic cups” of


the tie-rod system and installation
of patching system to fill in and √
make good the voids created by tie
rods

3.5 Apply of concrete repair material



where necessary

4. Design

4.1 Design of the formworks (including The subcontractor shall


calculations and shop drawings) be responsible for
√ formwork design and the
Contractor will help
material submission

Notes

1. SC : The Subcontractor
2. DHK : The Contractor
3. √ : be responsible