Professional Documents
Culture Documents
03 1741 COC-已解锁
03 1741 COC-已解锁
CONDITIONS OF CONTRACT
FOR
All rights including, without limitation, intellectual property rights in and to this document and any
information contained in this document are proprietary and are solely and absolutely owned by MTR
Corporation Limited. The document and any information contained in the document are strictly
confidential and must not be used, disclosed, transmitted, copied, printed or otherwise
disseminated without the prior written consent of MTR Corporation Limited. Violators will be
subject to legal sanctions such as an injunction order and will be held liable for any damages,
losses, costs and expenses incurred by MTR Corporation Limited.
September 2020
D/MTRCL/NW/E&M/COC/001/A6
CONTENTS
Table of Contents i - xv
Appendix B - Bond B1 - B6
September 2020
CONDITIONS OF CONTRACT
FOR
ENGINEERING WORKS
TABLE OF CONTENTS
Page
Clause Number
1.1 Definitions 1
1.7 Language 11
1.8 Subsidiaries 12
i September 2020
D/MTRCL/NW/E&M/COC/001/A6
Page
Clause Number
AUTHORISED PERSON
4.1 Assignment 16
5.1 Sub-Contracts 16
CONTRACT DOCUMENTS
DOCUMENTS
ii September 2020
D/MTRCL/NW/E&M/COC/001/A6
Page
Clause Number
CONTRACT FORMALITIES
13.1 Bond 26
13.2 Guarantee 26
Page
Clause Number
INSPECTION OF SITE
PROGRAMMES
16.6 Responsibility 32
iv September 2020
D/MTRCL/NW/E&M/COC/001/A6
Page
Clause Number
19.1 Setting-Out 35
INDEMNITIES
v September 2020
D/MTRCL/NW/E&M/COC/001/A6
Page
Clause Number
INSURANCES
NOTICES TO BE SUBMITTED
vi September 2020
D/MTRCL/NW/E&M/COC/001/A6
Page
Clause Number
MISCELLANEOUS
42.2 Explosives 53
43.1 Fossils 53
44.1 Publicity 54
Page
Clause Number
46.3 Co-ordination 55
LABOUR
55.1 Epidemics 59
56.1 Passes 59
Page
Clause Number
57.8 Access 61
57.18 Delivery 63
62.6 Retesting 66
ix September 2020
D/MTRCL/NW/E&M/COC/001/A6
Page
Clause Number
70.1 Damages 77
70.6 Set-Off 79
x September 2020
D/MTRCL/NW/E&M/COC/001/A6
Page
Clause Number
CERTIFICATION ON COMPLETION
DEFECTS LIABILITY
79.1 Variations 92
xi September 2020
D/MTRCL/NW/E&M/COC/001/A6
Page
Clause Number
79.4 Changes 94
81.1 Daywork 97
MEASUREMENT
Page
Clause Number
Page
Clause Number
SUB-CONTRACTORS
Page
Clause Number
RESOLUTION OF DISPUTES
NOTICES
DEFAULT OF EMPLOYER
xv September 2020
D/MTRCL/NW/E&M/COC/001/A6
CONDITIONS OF CONTRACT
FOR
ENGINEERING WORKS
INDEX TO CONDITIONS
CLAUSE PAGE
Abandonment of Contract
by Contractor 101.1 119
by Employer following suspension 73.1 83
Accelerated completion, see Delay Recovery measures
Access Certificate 74.8 87
definition 1.1.1 1
Access, Assistance and Facilities 21.6 37
" 57.8 61
for Others 46.2 55
for Engineer 59.1 63
for subsequent contractors 71.1 81
Accident or injury to workmen 24.5 40
Accommodation for the Works 66.1 71
Accounts, Contractor to submit audited accounts 31.3 44
Additional payment, Contractor's notice of
intention to claim 82.1 98
Adverse physical conditions and artificial obstructions 38.1 51
delay and extra cost (including reasonable profit) 38.3 51
measures to be taken on discovery of 38.2 50
reasonably foreseeable 38.4 51
Advertising on Site 44.1 54
Agent
Contractor's 17.2 33
responsible for safety 17.2 33
Aggregate of Damages 70.11 81
Agreement for Hire 91.1 107
Agreement, Formal 12.1 26
Alcoholic Liquor and Drugs 53.1 58
Alteration of Time for Completion 68.1 73
Ambiguities, Engineer to explain 6.2 17
Approval
definition 1.1.2 1
of programmes 15.8 30
Approved, definition 1.1.3 1
Approved Design Data, definition 1.1.4 1
Arbitration
Engineer as witness in 103.16 128
evidence at 103.15 128
interlocutory relief prior to 103.10 127
limitation period for purposes of 103.12 128
mediation prior to 103.6 126
reference to 103.5 125
Arbitrator
appointment of 103.5 125
powers of 103.14 128
Archaeological finds 43.1 53
Arms and ammunition 42.1 53
As-built drawings, Building Services Equipment
and ABWF Works 9.10 22
As-built record drawings 58.1 63
Assignment 4.1 16
Assignment of sub-contracts and supply agreements
to Employer on forfeiture 101.2 120
Assignment of warranties and guarantees to Employer 78.1 92
Assistants to Engineer's Representative 2.4 13
Audited Accounts 31.3 44
Authorised Person 3.1 15
definition 1.1.5 1
Avoidance of damage to highways and bridges 35.1 46
Certified amounts
failure to pay by Employer 90.2 107
payment of 90.1 106
Changes 79.4 94
definition 1.1.7 1
in Control of Contractor 31.4 45
in Control of Contractor, termination due to 101.6 121
to be in writing 79.2 99
Claims, notice of (additional payment) 82.1 98
Claims, particulars of (additional time) 68.3 74
Clause numbers, references to 1.5 11
Clearance of Site on completion 41.1 52
Commencement of Works 64.1 69
Compensation payments 36.3 48
Completion Obligations 67.1 72
cost of breach of 70.2 78
definition 1.1.8 1
delay in achieving 68.1 73
revision due to instruction for delay recovery 69.7 76
revision to 68.1 73
Completion of Works
alteration of time for 68.1 73
certificate of substantial (whole of the Works) 74.1 84
" " " (part or Section) 74.2 85
" " " (other parts) 74.3 85
vacation and clearance of Site upon 41.1 52
Completing part of the Works in lieu of determination
of Contractor's employment 101.8 123
Conditions of Contract
definition 1.1.9 2
to prevail 6.1 17
Conditions on Site and Clearance on Completion 41.1 52
Construction, methods of
Contractor to submit details of 16.1 30
Contractor's responsibility for 16.6 32
delay/cost resulting from changes in 16.5 32
mode and manner of, to be acceptable to Engineer 16.2 31
Contemporary Records 82.2 99
Contract
abandonment of by Contractor 101.1 119
abandonment of by Employer 73.1 83
definition 1.1.11 2
Formal Agreement 12.1 26
right of Employer to determine, due to war 102.1 123
Contract Price
definition 1.1.12 2
not subject to variation 85.2 104
Contract Sum, definition 1.1.13 2
Contractor
abandonment of Contract by 101.1 119
bankruptcy 101.6 121
change in control of 31.4 45
definition 1.1.14 2
Employer's remedy on failure to insure 29.1 44
Engineer's order, default in compliance with 61.2 65
general responsibilities of 10.1 23
indemnity to Employer
for accident or injury to workmen 24.5 40
for unreasonable noise disturbance and pollution 34.2 46
liable for liquidated damages for delay in completion 70.3 78
responsibility for design 10.2 24
responsibility unaffected by Engineer's
approval of Design Data 9.12 23
approval of documents 8.4 20
responsible for acts of sub-contractors 5.2 16
responsible for safety of all persons 21.1 36
responsible for safety of Site 10.4 24
to conform with any enactment 32.1 45
to conform with Buildings Ordinance 10.5 24
" " " " " 74.4 85
to co-operate with the Authorised Person and the
Registered Structural Engineer 10.5 24
to co-ordinate his own work with others 46.3 55
to execute the Works with due diligence 10.1 23
to give notices required by enactment 31.1 44
to keep records of levels and dimensions 58.1 63
to pay all royalties 36.3 48
to preserve peace 52.1 58
to provide audited accounts 31.3 44
to provide competent agent 17.2 33
to provide documents and drawings 8.1 19
to provide preliminary ABWF Programme 15.3 29
to provide superintendence of sub-contractors 5.4 16
to provide superintendence of the Works 17.1 33
to search for cause of defects 77.1 91
to take precautions against damage to highways 35.1 46
Contractor's agent 17.2 33
change in 17.4 34
Contractor's all risks Insurance 25.1 40
Contractor's Employees 18.1 34
accident or injury to, Contractor to indemnify
Employer against 24.1 39
English speaking 17.3 33
removal of 18.2 34
replacement of 18.3 35
Contractor’s Equipment
clearance through Customs of 39.4 52
conditions of hire of 91.3 107
costs of 91.4 108
definition 1.1.15 2
disposal of 91.8 108
incorporation of Clause 91 in sub-contracts 91.10 108
irremovability of 91.6 108
liability for loss or damage to 91.9 109
no approval by vesting 91.11 109
ownership of 91.5 108
revesting and removal of 91.7 108
supply of 39.1 52
to conform with laws of Hong Kong 39.1 52
use of 37.1 49
vesting of 91.2 107
Contractor's notice 7.3 18
Contractor's superintendence 17.1 33
Contractor's warranties 11.1 25
Co-ordinated Installation Programme 15.4 29
definition 1.1.16 2
Co-ordination of work by Contractor 46.3 55
Copyright in drawings 36.1 47
" " " 36.4 48
Correction and withholding of certificates 89.1 106
Correction of errors in Works 19.2 35
Cost, definition 1.1.17 3
Cost Centre
definition 1.1.18 3
value of 84.1 100
Cross liability clause in third party insurance 25.2 41
Covering up, examination of work beforehand 60.1 64
making good of 22.4 38
to highways or bridges 35.1 46
to persons or property, exceptions 24.1 39
xx September 2020
D/MTRCL/NW/E&M/COC/001/A6
Defects
Contractor to search for 77.1 91
Correction Certificate 75.8 90
Correction Certificate, definition 1.1.21 3
execution of work of repair 75.2 89
failure to finish work of repair 75.5 89
Liability Period 74.1 84
Liability Period, definition 1.1.22 3
Definitions [see word defined for individual references] 1.1 1
Delay
claims for 68.3 74
due to activities of Designated Contractor 46.6 55
due to adverse physical conditions 38.1 50
" " " " " 38.3 51
due to Engineer's delay in
issue of drawings 7.4 19
providing approval of Design Data 9.7 21
due to Engineer's failure to give consent to
proposed methods of construction 16.5 32
due to Excepted Risks 22.6 38
due to failure of utility company to comply with
the utility programme 46.7 56
due to failure to give timely possession of Site 65.5 70
due to obtaining Buildings Ordinance consent 74.4 85
due to providing facilities for other contractors 37.2 50
due to tests not provided for 57.12 62
due to use of Works by Employer before completion 74.6 86
due to Variation ordered 68.1(b) 72
in carrying out Tests on Completion 62.3 64
in completion, liquidated damages for 70.3 78
Delay recovery measures
definition 69.3 75
instruction of 69.7 76
price of 69.9 76
proposals for 69.3 74
Delegation of duties and authorities by Engineer 2.5 13
Design Approval Process 9.2 20
definition 1.1.23 4
Design Data 9.1 20
amendments to 79.9 96
definition 1.1.24 4
delaying Approval of 9.7 21
errors in 9.4 21
submission of 9.2 20
Designated Contracts 46.1 54
definition 1.1.25 4
Engineer
as witness in arbitration 103.16 128
assistants to 2.4 13
definition 1.1.30 4
delegation of powers of 2.5 14
duration of powers of 2.8 15
duties and powers of 2.1 12
reference to on dissatisfaction 2.7 14
to act impartially 2.2 13
to explain ambiguities in Contract 6.2 17
to fix rates for Variations not covered by Contract 80.2 97
to provide drawings and documents 7.1 18
to provide Preliminary Co-ordinated Installation 15.4 29
Programme
Engineer's
action on determination of Nominated Sub-contract 98.3 118
approval/refusal of Contractor's programmes 15.8 30
consent to Contractor's methods of construction 16.2 31
decision on dispute 2.8 15
effect of on Contractor and Employer 103.5 125
determination where tests not provided for 57.12 62
failure to disapprove Plant and Materials not final 61.3 65
power to correct or withhold certificates 89.1 106
Engineer's Representative
assistants to 2.4 13
definition 1.1.31 4
delegation to of Engineer's duties 2.5 14
duration of Powers of 2.8 15
functions of 2.3 13
reference to Engineer on dissatisfaction 2.7 14
reference to, on dissatisfaction with assistant 2.7 14
Epidemics 55.1 59
Errors
in setting out, correction of 19.2 35
Examination of Works before covering up 60.1 64
Excepted Risks 23.1 38
cost 22.5 38
delay 22.6 38
Execution of the Works
definition 1.1.32 5
investigation of progress 15.11 30
reporting of progress 15.10 30
Explosives 42.2 53
Extension of time for completion
assessment at due date of 68.1 73
Extraordinary traffic 35.1 46
settlement of claims 35.3 47
special loads 35.2 46
Labour
accommodation for 48.1 57
engagement of 47.1 56
expatriate 47.3 57
hours of work 51.1 57
religious customs of 54.1 59
returns for 50.1 57
wages and conditions for 49.1 57
Language
English speaking staff 17.3 33
of Contract 1.7 11
of instructions 1.7 11
of notices required by Government regulations 33.1 45
Letter of Acceptance, definition 1.1.45 7
Letter of Clarification, definition 1.1.46 7
Liability for loss of or damage to Contractor’s
Equipment 91.9 109
Liquidated damages
for delay in completion 70.3 78
limitation of 70.11 81
not a penalty 70.3(d) 78
" " " 70.8 80
rate of 70.4 79
set-off against sums due 70.6 79
Manpower 51.3 58
Marine Works
provision of buoys and moorings 63.2 68
provision of shipkeepers 63.1 68
sunken 63.3 68
Master Programme
definition 1.1.47 7
Measurement
application 83.1 99
Measures to be taken when adverse physical
conditions etc. met 38.2 50
Mediation 103.6 126
Methods of Manufacture, Construction or Installation 16.1 30
changes in 16.5 32
Engineer's consent not to relieve the Contractor
of responsibility 16.6 32
Engineer's consent to be obtained 16.2 31
failure to comply with Engineer's objections 16.3 31
late consent of the Engineer 16.4 31
to be submitted to Engineer 16.1 30
Milestone
achievement of 84.5 102
definition 1.1.48 7
failure to achieve 84.4 101
late achievement of 84.6 102
Milestone Percentage
definition 1.1.49 7
revision to 84.6 102
Milestone Schedules
definition 1.1.50 7
revision to 84.7 103
" " 84.6 102
Month, definition 1.1.51 8
Monthly Statements and Payments 85.1 104
Safety
Contractor responsible for 21.1 36
Contractor's agent responsible for 17.2 33
Officer and Health and Safety Plan 21.5 37
Samples, provision and cost of 57.9 61
Secretary General of the Hong Kong
International Arbitration Centre 103.5 125
Section
certificate of substantial completion for 74.2 85
definition 1.1.68 9
Security of Site 21.1 36
Service of Notices 104 129
Setting-out of Works 19.1 35
Settlement of disputes 103 125
Singular & Plural 1.2 11
Site
access for Engineer to be provided by Contractor 59.1 63
articles etc. discovered on 43.1 53
definition 1.1.69 10
possession of 65.1 69
failure to give possession of 65.5 70
Valuation
at date of forfeiture 101.3 120
of Variations and other items of work 80.1 96
of work under Provisional Sums and Prime Cost Items 97.8 116
Valuation Period, definition 1.1.75 10
Variations
by Engineer 79.1 92
definition 1.1.76 10
ordered, to be in writing 79.2 93
valuation of 80.1 96
Vesting of Contractor’s Equipment 91.2 107
War
payment in event of frustration due to 102.5 124
provisions to apply as from outbreak of 102.1 123
Works to continue for 14 days after outbreak of 102.1 123
Warranties
assignment of 78.1 92
Withholding and correcting certificates 89.1 106
Work
examination of 60.1 64
execution of 75.2 89
of repair, cost of execution of 75.3 89
outstanding 22.3 38
execution of outstanding 75.1 88
remedy on Contractor's failure to carry out 75.5 89
to be subject to tests 57.1 60
to satisfy Engineer 57 60
unsatisfactory, removal and proper re-execution 57.3 60
Workmen
accident or injury to 24.5 40
removal of 18.2 34
Works
accommodation for 66.1 71
care of 22.1 37
commencement of 64.1 69
definition 1.1.77 11
insurance of 25.1 40
Permanent, definition 1.1.56 8
setting-out of 19.1 35
Works (cont’d)
subject to Buildings Ordinance 74.4 85
" " " " 10.5 24
suspension of 72 82
Temporary, definition 1.1.72 10
to continue for 14 days after outbreak of war 102.1 123
1 September 2020
D/MTRCL/NW/E&M/COC/001/A6
3 September 2020
D/MTRCL/NW/E&M/COC/001/A6
4 September 2020
D/MTRCL/NW/E&M/COC/001/A6
6 September 2020
D/MTRCL/NW/E&M/COC/001/A6
7 September 2020
D/MTRCL/NW/E&M/COC/001/A6
8 September 2020
D/MTRCL/NW/E&M/COC/001/A6
9 September 2020
D/MTRCL/NW/E&M/COC/001/A6
10 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Singular and Plural 1.2 Words used in the Contract which import the singular
only also include the plural and vice-versa where the
context so admits.
Masculine, 1.3 Words used in the Contract which import one gender
Feminine and (whether masculine, feminine or neuter) shall be
Neuter taken to include any other gender where the context
so admits.
Headings and 1.4 The index, headings and marginal notes in the
Marginal Notes Conditions of Contract, the Form of Tender, the
Pricing Document and the Specification shall not be
part thereof or be taken into consideration in the
interpretation of the Contract.
Clause Numbers 1.5 Throughout the Contract, clause numbers quoted for
reference purposes use a number without a "point"
(e.g. Clause 69) when reference is being made to all
the clauses having that number before the "point"
(e.g. Clauses 69.1 to 69.11 inclusive). A reference
made using a "point" (e.g. Clause 69.4) refers to that
numbered clause (i.e. Clause 69.4) and any
sub-clauses of that numbered clause. A reference
made using two "points" (e.g. Clause 1.1.1) refers to
that sub-clause and any sub-sub-clauses of that
sub-clause.
Duties and Powers 2.1 (a) The Engineer shall perform the functions and
of Engineer exercise the powers specified in or necessarily
to be implied from the Contract.
Engineer to Act 2.2 The Engineer shall, except in connection with matters
Impartially requiring the specific approval of the Employer under
Clause 2.1(c), act impartially within the terms of the
Contract having regard to all the circumstances.
Delegation by 2.5 (a) The Engineer may from time to time in writing
Engineer authorise the Engineer's Representative or any
other person responsible to the Engineer to act
on behalf of the Engineer either generally in
respect of the Works or specifically in respect of
a Section or other part of the Works or
specifically in respect of particular clauses of
these Conditions of Contract. Any act of any
such person within the scope of his authority
shall for the purposes of the Contract constitute
an act of the Engineer and all references to the
"Engineer" in the Contract (apart from this
clause) shall be taken as references to such
person so far as they concern matters within
the scope of his authority. Notice in writing of
any such authorisation shall be given by the
Engineer to the Contractor. Such
authorisation shall continue in force until such
time as the Engineer shall notify the Contractor
in writing that the same is determined.
AUTHORISED PERSON
Authorised Person 3.1 Where the Works or any Section or part thereof are
subject to the Buildings Ordinance the Engineer shall
notify the Contractor of the name of the Authorised
15 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Assignment 4.1 The Contractor shall not assign the Contract or any
part thereof or any benefit or interest therein or
thereunder (otherwise than by a charge in favour of
the Contractor's bankers on any monies due or to
become due under this Contract) without the prior
written consent of the Employer.
Sub-Contracts 5.1 The Contractor shall not sub-contract the whole of the
Works. Except where otherwise provided by the
Contract the Contractor shall not sub-contract part of
the Works without prior Approval (which shall not be
unreasonably withheld) and such Approval if given
shall not relieve the Contractor from any liability or
obligation under the Contract. The acquisition by the
Contractor of labour on a piecework basis shall be
deemed to be sub-contracting under the Contract.
CONTRACT DOCUMENTS
Engineer to Explain 6.2 Subject to Clause 6.1 the documents forming the
Ambiguities Contract are to be taken as mutually explanatory of
one another, but in case of ambiguities or
discrepancies the Engineer shall explain and adjust
them and may thereupon issue to the Contractor
instructions so as to resolve the said ambiguities or
discrepancies or require the Contractor to put forward
proposals for Approval whereby they may be
resolved. Provided always that if in the opinion of
the Engineer compliance with any such instruction
shall cause the Contractor to suffer delay or incur
Cost, then:
DOCUMENTS
Further Drawings 7.2 The Engineer shall have full power and authority to
and Instructions supply to the Contractor from time to time during the
progress of the Works such further specifications,
drawings, design criteria and instructions as shall be
necessary for the purpose of the proper and
adequate Execution of the Works and the Contractor
shall carry out and be bound by the same. If such
further specifications, drawings, design criteria and
instructions require any change or modification to
any part of the Works which would, if ordered by the
Engineer pursuant to Clause 79.1, constitute a
Variation, such change or modification shall be
deemed to have been ordered pursuant to Clause
79.1.
Notice by 7.3 The Contractor shall give such notice in writing to the
Contractor Engineer as the Engineer considers reasonable of
any further design criteria, drawing, specification or
18 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Design Data 9.1 The Design Data shall be prepared by the Contractor
in compliance with the Specification and the
Drawings.
20 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Errors in Design 9.4 The Contractor shall be responsible for, and shall
Data bear, any Costs arising out of any errors or omissions
in any of the Design Data whether the same have
been Approved or not, with the exception of any Costs
arising out of errors and/or omissions due to
inaccurate information issued to the Contractor in
writing by the Engineer. All such errors and/or
omissions shall be corrected by the Contractor without
delay and the revised Design Data re-submitted to the
Engineer for Approval.
22 September 2020
D/MTRCL/NW/E&M/COC/001/A6
23 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Contractor's 10.2 The Contractor shall with due diligence carry out and
Responsibility for complete as part of the Execution of the Works, the
Design design of those parts of the Works identified in the
Specification as parts which are to be designed by the
Contractor including, without limitation;
Contractor 10.4 The Contractor shall take full responsibility for the
Responsible for adequacy, stability and safety of all Site operations
Safety of Site and methods of manufacture, construction and
installation.
Works subject to 10.5 Where the Works or any Section or part thereof are
Buildings subject to the Buildings Ordinance the Contractor
Ordinance shall cooperate with the Authorised Person and do all
things which it is within his power to do in order to
ensure that the Execution of the Works is undertaken
in accordance with the Buildings Ordinance. Without
24 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Joint Ventures 10.6 In the event that the Contractor comprises two or
more Persons acting in partnership, joint-venture or
otherwise, the liability of each such Person under this
Contract shall be joint and several.
CONTRACT FORMALITIES
Bond 13.1 The Contractor shall within 30 Days of the date of the
Letter of Acceptance (and at the expense in all
respects of the Contractor) submit to the Employer a
bond in the sum stated in the Appendix to the Form of
Tender, in the form appearing in Appendix B hereto
and duly executed under seal by an insurance
company or bank approved in writing by the Employer
(the Employer shall not be required to give reasons for
not approving).
26 September 2020
D/MTRCL/NW/E&M/COC/001/A6
INSPECTION OF SITE
27 September 2020
D/MTRCL/NW/E&M/COC/001/A6
PROGRAMMES
28 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Three Month 15.2 The Contractor shall by the date stated in the
Rolling Programme Specification prepare and submit to the Engineer a
three month rolling programme in accordance with the
Specification. The Contractor shall at the end of each
two month period submit a new three month rolling
programme for the next three months prepared in
accordance with this Clause 15.2.
Revision of 15.7 Should it appear to the Engineer at any time that the
Programmes progress of the Execution of the Works does not
conform with any programme Approved pursuant to
this Clause 15 in circumstances where the
Contractor is not entitled to an alteration of any
relevant Completion Obligation in accordance with
29 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Progress Reporting 15.10 The Contractor shall report progress of the Execution
of the Works in the manner described in the
Specification, or in such other manner as may be
Approved. The Contractor shall attend progress
meetings at times and places to be determined by the
Engineer.
Engineer's Consent 16.2 The Engineer shall inform the Contractor in writing
within a reasonable period after receipt of information
submitted in accordance with Clause 16.1 either:
Engineer's 16.3 Should the Contractor fail to comply with any of the
Objections: Failure Engineer's objections or requirements under Clauses
to Comply 8.2, 9, 16.1 or 16.2 within a reasonable time, the
Engineer may suspend any relevant part of the Works
until such compliance without any compensation or
extension of time being permitted to the Contractor.
31 September 2020
D/MTRCL/NW/E&M/COC/001/A6
withdrawn
Setting-Out 19.1 The Contractor shall be responsible for the true and
proper setting-out of the Works in relation to original
points, lines and levels of reference given by the
Engineer in writing or shown on any Drawings or in
the Approved Design Data and for the correctness of
the positions, levels, dimensions and alignment of all
parts of the Works and for the provision of all
necessary instruments, appliances and labour in
connection therewith. No check of any setting-out
or any line or level performed by the Engineer shall
in any way relieve the Contractor of his responsibility
for the correctness thereof.
Correction of 19.2 If at any time during the progress of the Works any
Errors error shall appear or arise in the position, levels,
dimensions or alignment of any part of the Works the
Contractor shall draw the attention of the Engineer to
the same and on being required so to do the
Contractor shall rectify such error to the satisfaction
of the Engineer. Any Cost involved in rectifying the
error shall be borne by the Contractor. Provided
always that if such error arises from incorrect data
supplied by the Engineer and if the rectification of
such error pursuant to this clause, in the opinion of
the Engineer, causes the Contractor to suffer delay
or to incur Cost, then:
Protection and 19.3 The Contractor shall carefully protect, preserve and
Recording replace when necessary all control stations, bench
marks, sight rails, pegs and other things used in
setting out the Works and shall compile and maintain
records of all control stations, bench marks and
35 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Safety and Security 21.1 The Contractor shall throughout the progress of the
Works have full regard for the safety of all persons
entitled to be upon the Site and shall keep the Site
and the Works in an orderly state conducive to the
avoidance of danger to such persons and he shall, in
connection with the Works, without limiting the
generality of the foregoing, provide and maintain at
his own Cost all lights, guards, fencing, warning signs,
watching and any other appropriate safety and
security measures when and where necessary or
required by the Engineer or by any competent
statutory or other authority for the protection of the
Works or for the safety and convenience of the public
or others.
Health and Safety 21.2 The Contractor shall by the date stated in the
Plan Specification submit to the Engineer for his consent
a health and safety plan, which shall set out details
of the health and safety measures to be
implemented by the Contractor in order to comply
with his obligations under Clause 21.1 and with all
relevant Enactments applicable from time to time.
The submission of such health and safety plan, and
all submissions to the Engineer of supplemental
parts of such health and safety plan shall be made in
accordance with the Specification, but shall not
otherwise be subject to the procedure set out in
Clause 8. All submissions of supplemental parts of
such health and safety plan shall be made not less
than 30 Days before commencement of any work
which is the subject of any such submission.
Form and Content 21.3 The form and content of the initial submission of the
of Health and said health and safety plan, and of all supplemental
Safety Plan parts thereof, shall be in accordance with the
requirements prescribed in the Specification.
Safety Officer and 21.5 The Contractor shall, in accordance with the
Health and Safety requirements set out in the Specification, appoint a
Plan suitably qualified and experienced person to act as
safety officer. The safety officer shall monitor,
report to and advise the Contractor's management
on the application of the Health and Safety Plan.
The safety officer shall manage and coordinate the
activities of his supporting safety staff who shall be
appointed in accordance with the Specification.
Access, Assistance 21.6 The Contractor shall provide all necessary access,
and Facilities assistance and facilities both on and off the Site to
enable the Engineer to verify that the Health and
Safety Plan is being properly and fully implemented
and/or to conduct safety audits.
Care of Works 22.1 Subject to Clause 22.2 and Clause 74.7, from the
Date for Commencement until the date of issue of the
Certificate of Completion for the whole of the Works,
the Contractor shall take full responsibility for the care
of the Works which shall include the responsibility for
all Plant and Materials, Contractor's Equipment,
temporary buildings, goods and materials and things
whatsoever on the Site or delivered to or placed on
the Site in connection with or for the purposes of the
Works.
Where Part Handed 22.2 In the event that the Engineer issues a Certificate of
Over Completion or a Handing Over Certificate in respect of
any Section or part of the Works before a Certificate
of Completion is issued in respect of the whole of the
Works, the Contractor's responsibility defined in
Clause 22.1 shall cease in respect of that Section or
part of the Works upon the issue by the Engineer of
such Certificate of Completion or Handing Over
Certificate. In the event that the Engineer issues an
Access Certificate in respect of any part of the Works
in accordance with Clause 74.8 the Contractor's
responsibility for preventing the causing by any party
37 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Making Good of 22.4 Subject to Clause 22.2, in the event that any damage,
Damage loss or injury shall happen to the Works or any part
thereof or to such Plant and Materials, Contractor's
Equipment, temporary buildings, goods or materials
or things whatsoever as are referred to in Clause 22.1
from any cause whatsoever (save and except the
Excepted Risks set out in Clause 23), the Contractor
shall at his own Cost and with all possible speed
make good any such damage, loss or injury to the
satisfaction of the Engineer and shall notwithstanding
such damage, loss or injury proceed with the
Execution of the Works in all respects in accordance
with the Contract and the Engineer's instructions.
Excepted Risks: 22.5 In the event of any such damage, loss or injury
Cost happening by reason of any of the Excepted Risks, or
in circumstances where the risk of such damage, loss
or injury happening no longer lies with the Contractor
by virtue of Clause 22.2, the Contractor shall, if and to
the extent required by the Engineer, repair and make
good the same as aforesaid at the Cost of the
Employer.
Excepted Risks 23.1 The "Excepted Risks" are war, hostilities (whether
war be declared or not), invasion, act of foreign
enemies, terrorism, rebellion, revolution, insurrection
38 September 2020
D/MTRCL/NW/E&M/COC/001/A6
INDEMNITIES
Damage to Persons 24.1 The Contractor shall, save insofar as the Contract
and Property provides otherwise, indemnify the Employer against
any loss or expense sustained by the Employer and
against all losses and claims in respect of death or
injuries or damage to any person or property
whatsoever which may arise out of or in consequence
of the Execution of the Works and against all claims,
proceedings, damages, Costs, charges and expenses
whatsoever in respect of or in relation thereto, except
any compensation or damages for or with respect to:
Accidents or Injury 24.5 The Employer shall not be liable for or in respect of
to Workmen any damages or compensation payable at law in
respect or in consequence of any accident, illness or
injury to any workman or other person in the
employment of the Contractor or of his
sub-contractors or suppliers arising out of and in the
course of his employment and the Contractor shall
throughout the period of the Contract indemnify and
keep indemnified the Employer against all such
damages and compensation and against all claims
demands proceedings Costs charges and expenses
whatsoever in respect thereof or in relation thereto.
INSURANCES
40 September 2020
D/MTRCL/NW/E&M/COC/001/A6
41 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Professional 26.3 The Contractor shall effect and maintain or cause his
Indemnity sub-contractors of any level and his design
Insurance consultants to effect and maintain professional
indemnity insurance in respect of any design of the
Works (including Temporary Works), such insurance
to provide cover in a sum and for a period not less
than that stated in the Appendix to the Form of Tender.
In the event that the limit of indemnity under any of the
professional indemnity insurance policies is
exhausted by reason of indemnity payments paid or
payable under such insurance policy, the limit of
indemnity under the policy shall be reinstated in
accordance with the Letter of Undertaking for
Professional Indemnity Insurance in the Appendix to
the Form of Tender.
Motor & Marine 26.4 The Contractor shall at all material times keep in force
Insurance the following additional insurances in so far as they
may be applicable:
Marine Cargo 26.5 The Contractor shall effect and maintain for the
Insurance benefit of and in the joint names of the Employer, the
Contractor and sub-contractors of any level a Marine
Cargo Insurance on all risks conditions including
war, strike, riots, and civil commotion in respect of
each shipment of Plant and Materials from the time
of departure from the Contractor's premises or place
of manufacture or store outside Hong Kong until
delivery to the Site. The sum insured under such
cargo insurance shall be for not less than the full
value for each shipment of the Plant and Materials
shipped as set out in the Pricing Document including
freight or such other figure as may be agreed by the
Engineer.
Other Insurance 26.6 The Contractor shall effect and maintain ‘all risks’
cover to the Engineer's satisfaction on any Plant and
Materials in course of manufacture off Site until such
Plant and Materials become insured under the
policies referred to in Clause 25.1 and/or Clause 26.5.
Remedy on Failure 29.1 If the Contractor or the Employer fails to effect and
to Insure keep in force the insurances referred to in Clauses 26
and 25 respectively then in such case, the Employer
or the Contractor, as the case may be, may effect and
keep in force any such insurances and pay such
premium or premiums as may be necessary for that
purpose and from time to time deduct, or as the case
may be, add, the amount so paid from or to any
monies due or which may become due to the
Contractor or recover the same as a debt due from or,
as the case may be, to the Contractor.
NOTICES TO BE SUBMITTED
Giving of Notices 31.1 The Contractor shall give all notices and pay all fees
and Payment of required to be given or paid by any Enactment or any
Fees other requirement of any duly constituted authority in
relation to the Execution of the Works.
Audited Accounts 31.3 The Contractor shall submit to the Employer annual
audited accounts (both accounts of the Contractor's
expenses and income as a whole and of his expenses
and income relating to the Works) within 120 Days
after the end of the period to which they relate and
44 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Change in Control 31.4 The Contractor shall notify the Employer if the
Contractor becomes a subsidiary of a Person of
whom the Contractor was not a subsidiary at the
date of the Letter of Acceptance or comes under the
control of two or more Persons acting in concert so
that if they were one company the Contractor would
be its subsidiary, and in such event Clause 101.6
shall apply.
Compliance with 32.1 The Contractor shall comply and shall require any
Enactments sub-contractors and/or agents to undertake in any
relevant contracts to comply in all respects with the
provisions of any Enactment and with any other
requirements of any duly constituted authority which
may be applicable to the Works and/or to the
Execution of the Works and shall keep the Employer
indemnified against all penalties and liabilities of every
kind for breach of any such Enactment or
requirement.
Interference with 34.1 All operations necessary for the Execution of the
Traffic and Works shall, so far as compliance with the
Adjoining requirements of the Contract permit, be carried on so
Properties as not to interfere unnecessarily or improperly with
the public convenience or the access to or use or
occupation of public roads and footpaths and
waterways, anchorages and navigation channels or
access to or use or occupation of properties whether
in the possession of the Employer or of any other
Person and the Contractor shall indemnify and keep
indemnified the Employer (throughout the period of
the Execution of the Works) against any expense or
loss sustained by the Employer and against all
losses and claims for injuries or damage to any
person or any property whatsoever and against all
claims, demands, proceedings, damages, Costs,
45 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Nuisance and 34.2 All work shall be carried out without unreasonable
Disturbance nuisance and disturbance. The Contractor shall
take all steps to comply with the requirements of the
Specification in these matters. The Contractor shall
indemnify and keep indemnified the Employer
(throughout the period of the Execution of the
Works) against any expense or loss sustained by the
Employer and against all losses and claims for
injuries or damage to any person or any property
whatsoever and against all claims, demands,
proceedings, damages, Costs, charges and
expenses arising out of or in relation to the
Execution of the Works.
MISCELLANEOUS
Patent Rights 36.1 The Contractor shall save harmless and indemnify
the Employer from and against all claims and
proceedings for or on account of infringement or
alleged infringement of any Intellectual Property
Rights in respect of the Works or of any Plant and
Materials, Contractor's Equipment, other plant or
equipment, machine, documents, drawings, or
material used for or in connection with the Works
and from and against all claims, demands,
proceedings, damages, Costs, charges and
expenses whatsoever in respect thereof or in
relation thereto in Hong Kong or any country,
howsoever caused and whensoever arising.
47 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Royalties and 36.3 The Contractor shall be responsible for the payment
Other of all tonnage and other royalties, licence fees, rent
Compensation and other payments or compensation of whatsoever
Payments nature arising out of the Execution of the Works, or
any work method, process, system, document,
drawing, Contractor's Equipment or Plant and
Materials required for the Works. Any royalties or
licence fees received by or for the Contractor arising
out of other Intellectual Property Rights jointly
developed by the Contractor and the Employer shall
be shared between them in proportions which
properly reflect the financial and design contribution
made by each of them to the development of the
Intellectual Property Rights. In the event of a failure
to agree the said proportions, the proportions shall
be fixed by mediation or by an arbitrator, in
accordance with the procedure set out in Clause
103.
49 September 2020
D/MTRCL/NW/E&M/COC/001/A6
thinks fit:
Delay and Extra 38.3 To the extent that the Engineer shall decide that the
Cost whole or some part of the said physical conditions or
artificial obstructions could not reasonably have been
foreseen by an experienced contractor at the date of
the Letter of Clarification the Engineer shall take any
delay or disruption of working suffered by the
Contractor as a result of such conditions or
obstructions into account in determining any
extension of time to which the Contractor is entitled
under Clause 68.1. If the Contractor shall comply with
Clause 82 (notwithstanding that the Engineer may not
have given any instructions or orders pursuant to
Clause 38.2) the Engineer shall assess such sum as
represents the reasonable Cost of carrying out any
additional work done and additional Contractor's
Equipment used which would not have been done or
used had such conditions or obstructions or such part
thereof as the case may be not been encountered,
together with a reasonable percentage addition
thereto in respect of profit; and the reasonable Costs
incurred by the Contractor by reason of any delay or
disruption of working suffered as a consequence of
encountering the said conditions or obstructions or
such part thereof. The Engineer shall certify the
amount by which such sum exceeds the amount
specified in the Appendix to the Form of Tender by
reference to this clause and the amount so certified
shall be paid by the Employer to the Contractor. This
clause shall not apply to any Variation ordered
pursuant to Clause 38.2(d) or Clause 79 which shall
be valued in accordance with Clause 80.
Conditions on Site 41.1 During the Execution of the Works the Contractor
and Clearance of shall keep the Site in a clean and tidy condition to
Site on Completion the satisfaction of the Engineer and so order the
Works and his Contractor's Equipment and Plant
and Materials as to allow the Execution of the Works
52 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Arms and 42.1 The Contractor shall not hold on the Site arms or
Ammunition ammunition of any description nor shall he permit
others to do so. The Contractor shall notify the
Commissioner of Police of any explosives, arms or
ammunition found or suspected to be on the Site.
53 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Conflicts of Interest 45.4 The Contractor shall require its directors, employees,
agents and sub-contractors who are involved in this
Contract to declare in writing to the Contractor any
conflict or potential conflict between their
personal/financial interests and their duties in
connection with this Contract. In the event that such
conflict or potential conflict is disclosed in a
declaration, the Contractor shall forthwith take
measures reasonably required by the Employer to
mitigate as far as possible or remove the conflict or
potential conflict so disclosed.
Access for Others 46.2 The Contractor shall in accordance with the
requirements of the Engineer afford all reasonable
opportunities for carrying out their work to the utility
companies, Government Departments, any other
contractors employed by the Employer and their
workmen, any workmen of any Interfacing
Contractors and the workmen of the Employer or
Government Departments who may be engaged in
the execution on or near the Site of any work
ancillary to the Works but not included in the
Contract and shall not cause them unnecessary
inconvenience.
Designated and 46.6 If the Contractor shall suffer delay or incur Cost
Other Contractors: because the activities of any Designated Contractor
Delay or Interfacing Contractor are such that the
Contractor is unable to proceed with the Execution
of the Works with due despatch in accordance with
the Master Programme, the Installation Programme
and/or the Co-ordinated Installation Programme, or if
compliance with Clause 46.2 or Clause 46.3 shall
involve the Contractor in delay or Cost, then:
LABOUR
Engagement of 47.1 The Contractor shall make his own arrangements for
Labour the engagement of all labour local or otherwise skilled
and unskilled as may be required for the Execution of
the Works in Hong Kong and for their payment,
housing, feeding and transport. All such
arrangements shall be in accordance with the general
local usage and subject to such Enactments as
Government may from time to time require to be
observed.
Expatriate 47.3 If the Contractor is unable to obtain all the skilled and
Personnel unskilled labour required pursuant to Clause 47.2 by
employing residents of Hong Kong he shall make his
own arrangements to obtain suitable persons outside
Hong Kong and shall obtain the approval of the
Immigration Department for the employment of every
such person.
Wages and 49.1 The Contractor shall pay rates of wages and observe
Conditions for hours and conditions for labour which are not less
Labour favourable than the general level of wages, hours and
conditions observed by other employers in Hong Kong
whose general circumstances in the trade or industry
in which the Contractor is engaged are similar.
authorised by him.
Contractor to 52.1 The Contractor shall at all times during the progress
Preserve Peace of the Contract take all requisite precautions and use
his best endeavours to prevent any riotous or
unlawful behaviour by or amongst the workmen and
others employed on or in connection with the Works
and for the preservation of the peace and protection
of the inhabitants and the security of all property in
the neighbourhood of the Works in Hong Kong, and
58 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Restrictions on 53.1 The Contractor shall not at any time give, sell or
Alcoholic Liquor barter any alcoholic liquors or drugs or permit or
and Drugs suffer any such sale, gift or barter to be made by any
sub-contractor, employee or agent of the Contractor,
nor import or permit or suffer the importation of any
alcoholic liquors or drugs into Hong Kong or any part
thereof otherwise than in conformity with such
Enactments as may be applicable.
Festivals and 54.1 The Contractor, all sub-contractors and all their
Religious Customs agents and employees shall in all their dealings with
their workmen and labourers for the time being
employed on or in connection with the Execution of
the Works in Hong Kong have due regard to all
recognised festivals and religious and other customs.
Quality and Manner 57.1 All Plant and Materials and workmanship shall be
of Execution subjected from time to time to such inspections and
tests as the Engineer may direct or approve at the
place of manufacture or fabrication or on the Site or
at such other place or places as may be specified in
the Contract or Approved. If part of the Plant and
Materials is being manufactured on premises other
than the Contractor’s premises, the Contractor shall
obtain for the Engineer permission to inspect,
examine and test as if the Plant and Materials were
being manufactured on the Contractor's premises.
Quality Plan 57.4 The Contractor shall by the date stated in the
Specification submit to the Engineer for Approval a
quality plan, which shall set out details of the quality
management system to be implemented by the
Contractor in order to control all design,
procurement, manufacture, construction and
installation activities required by the Contract in such
a way as to ensure completion of the Works in
accordance with the Contract, with the Approved
Design Data and with any drawings or documents
submitted by the Contractor pursuant to Clause 8
and Approved. The submission of such quality plan,
and all submissions to the Engineer of supplemental
parts of such quality plan, shall be made in
accordance with the Specification and shall not
otherwise be subject to the procedure set out in
Clause 8. All submissions of supplemental parts of
such quality plan pursuant to this Clause 57.4 shall
in any event be made not less than 30 Days before
the commencement of any work or the placing of any
order which is the subject of any such submission.
Form and Content 57.5 The form and content of the initial submission of the
of Quality Plan said quality plan, and of all supplemental parts
thereof, shall be in accordance with the requirements
prescribed in the Specification.
Quality Manager 57.7 The Contractor shall appoint a Site based suitably
qualified and experienced person to act as manager
of the quality management system set out in the
Quality Plan and shall from time to time provide such
other personnel and resources as may be required
to ensure effective implementation of the Quality
Plan.
Cost of Samples 57.9 All samples shall be supplied by the Contractor at his
own Cost if the supply thereof is clearly intended by or
61 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Cost of Tests 57.10 The Cost of making any test shall be borne by the
Contractor if such test is:
Cost of Tests not 57.11 If any test required by the Engineer which is:
Provided for
(a) not so intended by or provided for; or
62 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Inspection and 57.14 The Engineer shall be entitled at all reasonable times
Testing during during manufacture to inspect, examine and test on
Manufacture the Contractor's premises or elsewhere the materials
to be incorporated within the Plant and Materials,
labour who will undertake the manufacture of the
Plant and Materials and completed components of the
Plant and Materials and if part of the Plant and
Materials is being manufactured on other premises
the Contractor shall obtain for the Engineer
permission to inspect, examine and test as if the Plant
and Materials were being manufactured on the
Contractor's premises. Such inspection,
examination or testing, if made, shall not release the
Contractor from any obligation under the Contract.
Testing before 57.15 Parts of the Plant and Materials shall be tested
Delivery before delivery to Site as provided for in the
Specification or as may be agreed with the Engineer.
The Contractor shall give reasonable notice in
writing to the Engineer of the date on which, and the
place at which, any parts of the Plant and Materials
will be tested, as provided in the Contract, and
unless the Engineer attends at the place so named
within 21 Days of the date which the Contractor has
stated in his notice, the Contractor may proceed with
the tests which shall be deemed to have been made
in the Engineer's presence and shall forthwith
forward to the Engineer duly certified copies of the
test results and readings. The Engineer shall give
the Contractor not less than twenty four hours notice
in writing of his intention to attend the tests.
57.17 The Engineer shall also have the right to inspect the
packing of parts of the Plant and Materials before
despatch from the manufacturer's premises. The
Contractor shall notify the Engineer when he
anticipates packed parts of the Plant and Materials
will be ready for inspection. The Engineer shall
notify the Contractor either that he waives inspection
or that he will inspect the said part of the Plant and
Materials.
Records of Levels 58.1 The Contractor shall keep records of levels and
and Dimensions dimensions during the course of the Execution of the
Works in an Approved form and shall submit records
as and when required by the Engineer.
Access to Site and 59.1 The Engineer and any person authorised by him in
Places of writing shall at all times have access to the Works and
Manufacture to the Site and to all places where work is being
executed or whence Plant and Materials and
Contractor’s Equipment are being supplied for the
Works and the Contractor shall afford every facility for
and every assistance in obtaining such access. The
Contractor shall provide all necessary assistance and
facilities both on and off the Site to enable the
Engineer to verify that the Quality Plan is being
properly and fully implemented and/or to conduct
quality audits.
Removal of 61.1 The Engineer shall during the progress of the Works
Improper Plant and have power to order in writing from time to time:
Materials
(a) the removal from the Site, within such time or
times as may be specified in the order, of any
Plant and Materials which in the opinion of the
Engineer are not in accordance with the
Contract;
Retesting 62.6 If the Works or any Section or any part of the Works
fail or fails to pass the Tests on Completion applicable
thereto the Contractor shall at his own expense:
Consequences of 62.7 If the Works or any Section or any part of the Works
Failure to Pass fail or fails to pass any repetition of the Tests on
Tests on Completion applicable thereto carried out pursuant
Completion to Clause 62.6, the Engineer shall, after due
consultation with the Employer and the Contractor,
be entitled:
Marine Works 63.1 The Contractor shall provide and maintain to the
satisfaction of the Engineer efficient ship-keepers for
all floating plant and marine platforms and other
marine craft and shall display such lights, flags,
signals and markings as may be required by the
Marine Department for the safety of vessels, craft
and the public.
Possession of Site 65.2 Save in so far as the Contract prescribes the extent
to which the Contractor shall be allowed to enter
portions of the Site from time to time and the order in
which entry to such portions shall be permitted and
subject to any requirement in the Contract as to the
order in which the Works shall be carried out, the
Contractor shall be permitted to enter and to work on
so much of the Site as may be required to enable the
Contractor to commence and proceed with the
Execution of the Works in accordance with the
Master Programme and/or the Co-ordinated
Installation Programme and the Contractor shall be
permitted to enter and to work on such further
portions of the Site as may be required to enable the
Contractor to proceed with the Execution of the
Works with due despatch in accordance with the
said programmes.
65.4 The Contractor shall ensure that all of the work force
engaged in the Execution of the Works on the Site
comply with all reasonable requirements and
directions of the Designated Contractor who has
possession of the Site including, without prejudice to
the generality of this requirement, all such
requirements and directions relating to security,
safety and all related matters in respect of the Site.
Access to Site 65.9 The Employer shall provide reasonable access in the
form of a road or railway suitable for the transport of
all parts of the Plant and Materials and Contractor's
Equipment necessary for the Execution of the Works
from an adequate public thoroughfare or railway
available to the Contractor to the point on the Site
where it is to be delivered or used. If a building,
structure, foundation or approach is to be provided by
the Employer under the contract such building,
structure, foundation or approach shall be in a
condition suitable for the efficient transport, reception,
71 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Accommodation 66.1 The Contractor shall provide at his own expense any
for the Works additional land or buildings outside the Site which are
required by him for the purposes of the Works.
Completion 67.1 In the Contract there are set out dates by which:
Obligations
(a) substantial completion of the Works; and
Achievement of 67.2 In the Contract there are set out dates by which
Milestones Milestones are to be achieved. If and so often as
any Milestone shall not be achieved on or before the
date for the achievement thereof then the provisions
of Clauses 84.4 to 84.8 shall take effect.
Notwithstanding any provisions of these Conditions
of Contract, the obligation of the Contractor to make
payments and the right of the Employer to make
deductions under Clause 70 in respect of any failure
by the Contractor to achieve a Completion
Obligation shall not be prejudiced or in any way
affected by virtue of such failure also constituting the
non-achievement of a Milestone. The Engineer
72 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Rate of Progress 69.1 The Contractor shall satisfy the Engineer that the
whole of the Plant and Materials and Contractor's
Equipment and labour to be provided by the
Contractor and the method, manner and speed of the
Execution of the Works are adequate to enable the
Completion Obligations to be achieved.
76 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Cost of Breach 70.2 Breach of any Completion Obligation will result in the
Employer suffering losses which may include (but
shall not be limited to) any or all of:
73.2 Clause 73.1 shall not apply in a case where the Works
have been suspended by reason of some default on
the part of the Contractor.
CERTIFICATION ON COMPLETION
Certificate of 74.1 When the Contractor shall consider that the whole of
84 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Completion of 74.3 If the Engineer shall be of the opinion that any part of
85 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Works subject to 74.4 Where the Works or any Section or part thereof are
Buildings subject to the Buildings Ordinance then the Works or
Ordinance any such Section or part shall not be considered to be
substantially completed at any time before the
granting of an occupation permit or temporary
occupation permit or any other equivalent permit or
approval under the Buildings Ordinance in respect
thereof. The time for completion of the Works or any
such Section or part shall be deemed to include time
for:
Handing-Over 74.7 In the event of the Employer using the Works or any
Certificate substantial part of the Works before the issue of a
Certificate of Completion (provided that occupation
and/or use by a Designated Contractor or an
Interfacing Contractor or other Person shall not
amount to occupation or use by the Employer) and
whether or not any relevant Tests on Completion or
other tests prescribed or Approved under the
Contract have been carried out and accepted, the
Engineer shall issue a Handing-Over Certificate to
the Contractor and the Employer at the time of the
Employer commencing such use. The
Handing-Over Certificate shall state details of the
part of the Works used by the Employer and the
work which in the Engineer's opinion is required to
be done by the Contractor within that part of the
Works before the issue of a Certificate of Completion
in respect of the whole of the Works or in respect of
any part of the Works which includes the part the
subject of the Handing-Over Certificate. The
Employer or the Contractor shall notify the Engineer
within 7 Days of receipt of a Handing-Over
Certificate of any disagreement and of the details in
the Handing-Over Certificate with which he
disagrees. The Employer shall assume
87 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Access Certificate 74.8 In the event of the Employer taking over the control
of access to any part of the Works prior to its use by
the Employer then the Engineer shall issue an
Access Certificate to the Contractor and the
Employer at the time of the Employer taking over
such control of access. The Access Certificate
shall identify the part of the Works in relation to
which the Employer has taken over control of
access. Such right on the part of the Employer to
take over control of access shall be limited to those
parts of the Works in relation to which the
Specification indicates that an Access Certificate
may be issued. Upon the issue of an Access
Certificate, the parties' respective obligations in
relation to care of the part of the Works which is the
subject of the Access Certificate shall, from the time
of the issue of the certificate, be as set out in Clause
22.2.
DEFECTS LIABILITY
Execution of 75.1 The Contractor shall finish the work (if any)
Outstanding Work outstanding at the date of completion (as certified by
the Engineer pursuant to Clause 74) of the Works or,
as the case may be, of any part of the Works or of any
Section within such reasonable time or times as may
be specified by the Engineer. If no such times are
specified such work shall be finished as soon as may
be practicable after such date of completion and in
any event within the relevant Defects Liability Period.
Execution of Work 75.2 The Contractor shall at his own expense execute all
of Repair work of repair, replacement, modification,
amendment, reconstruction, rectification and making
good of defects, imperfections, shrinkages or other
faults (of whatever nature and from whatever cause
the same may arise) which the Engineer shall during
the Defects Liability Period, or within 14 Days after
its expiration, require the Contractor in writing to
execute, following an inspection made by or on
behalf of the Engineer prior to the expiration of the
Defects Liability Period. Provided that in the case
of defects, imperfections, shrinkages, or other faults
which in the opinion of the Engineer result from
improper use of the Works or are otherwise caused
by the Employer the Contractor shall be entitled to
be paid by the Employer the Cost of such work of
repair, replacement, modification, amendment,
reconstruction, rectification and making good, the
amount of such Cost to be certified by the Engineer.
Failure to Finish 75.5 If the Contractor shall fail to do or finish any work
Work of Repair required under Clause 75 the Employer may do or
89 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Defects Correction 75.8 Upon the expiration of the Defects Liability Period or
Certificate where there is more than one such period upon the
expiration of the latest such period and when all
outstanding work referred to in Clause 74 and all
work of repair, modification, replacement,
amendment, reconstruction, rectification and making
good of defects, imperfections, shrinkages or other
faults referred to in Clause 75 shall have been
completed the Engineer shall issue to the Employer
(with a copy to the Contractor) a Defects Correction
Certificate stating the date on which the Contractor
shall have completed his obligations to execute and
complete the Works and correct defects therein to
the Engineer's satisfaction.
herein contained:
Contractor to 79.3 The Engineer may pursuant to this Clause 79.3 give
Propose Estimates to the Contractor written details of any proposed
Variation before ordering the same. In that event,
the Contractor shall within 14 Days (or such other
period as the Engineer may in writing allow) of the
Engineer providing such written details of the
proposed Variation notify the Engineer in writing
whether in his opinion the Variation would, if ordered,
94 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Engineer to Fix 80.2 Where work in the opinion of the Engineer is not of a
Rates similar character or is not executed under similar
conditions the rates and prices in the Pricing
Document shall be used as the basis for valuation so
far as may be reasonable failing which a fair valuation
shall be made. Failing agreement between the
Engineer and the Contractor as to any rate or price to
be applied in any valuation under this Clause 80 the
Engineer shall determine the rate or price in
accordance with the foregoing principles and he shall
notify the Contractor accordingly.
Interim Account 82.3 After the giving of a notice to the Engineer under
Clause 80.3 or 82.1 as the case may be the
Contractor shall as soon as is reasonable in all the
circumstances send to the Engineer a first interim
account giving full and detailed particulars of the
amount claimed to that date and of the grounds upon
which the claim is based together with full particulars
of any benefits or advantages whether direct or
indirect which shall have accrued or may be expected
to accrue to the Contractor in consequence of the
circumstances giving rise to the Contractor's claim for
additional payment. Thereafter at such intervals as
the Engineer may reasonably require the Contractor
shall send to the Engineer further up to date accounts
giving the accumulated total of the claim and any
further grounds upon which it is based together with
up to date particulars of the said benefits or
advantages.
MEASUREMENT
Application 83.1 To the extent that the Works or any part of the Works
are stated in the Pricing Document as being subject to
admeasurement the Special Conditions of Contract
appended to these Conditions will apply to the Works
or any part of the Works so identified.
Interim Payment 84.1 The Pricing Document is divided into Cost Centres
as set out therein. The value of the Cost Centre in
each case shall be the total amount shown for that
Cost Centre in the Pricing Document adjusted to
reflect:
Failure to Achieve 84.4 If any Milestone shall not be achieved by the end of
Milestone the Valuation Period in which it is due to be achieved,
101 September 2020
D/MTRCL/NW/E&M/COC/001/A6
then:
Interim Statements 85.1 At the end of each Valuation Period the Contractor
may apply to the Engineer for an Interim Payment
Certificate. Each such application shall state the
amount claimed broken down into:
Contract Price not 85.2 The rates and prices in the Pricing Document shall not
Subject to Variation be adjusted in respect of any increase or decrease of
104 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Certification for 86.1 The Engineer shall certify within 30 Days from
Interim Payment receipt of the Contractor's particulars under Clause
85.1 the amount payable by the Employer to the
Contractor by way of interim payment. Such
amount shall be the payment due determined in
accordance with Clause 84 plus the value of
dayworks ordered pursuant to Clause 81 plus any
sums considered due by the Engineer pursuant to
Clause 82 less retention calculated at the
percentage named in the Appendix to the Form of
Tender until the limit of the Retention Money named
in the Appendix to the Form of Tender has been
reached and less any amounts certified for payment
in any Interim Payment Certificate previously issued.
87.2 One half of the Retention Money less any sums paid
pursuant to Clause 87.1 shall be certified for payment
by the Engineer within 7 Days of the date of issue of a
Certificate of Completion for the whole of the Works
pursuant to Clause 74.1 or within 7 Days of the date of
receipt by the Engineer of the last of the as-built
drawing and operation and maintenance manuals (if
any) in relation to the Works whichever shall be later.
Application for 88.1 Not later than 90 Days after the date of issue of the
Final Payment Defects Correction Certificate to the Employer, the
Contractor shall submit to the Engineer a statement
of final account and supporting documentation
showing in detail the value in accordance with the
Contract of the work done in accordance with the
Contract together with all further sums which the
Contractor considers to be due to him under the
Contract up to the date of the Defects Correction
Certificate.
Correction and 89.1 The Engineer shall have power to omit from any
106 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Agreement for Hire 91.1 For the purpose of Clause 91, the expression
"agreement for hire" shall be deemed to include an
agreement for hire purchase.
Revesting and 91.7 Upon the removal from the Site of any such
Removal of Contractor's Equipment as have been deemed to
Contractor’s have become the property of the Employer under
Equipment Clause 91.2 with the consent as aforesaid or under
the provisions of Clause 105.2 the property therein
shall be deemed to revest in the Contractor and
108 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Liability for Loss of 91.9 The Employer shall not at any time be liable for the
or Damage to loss of or damage to any of the Contractor's
Contractor’s Equipment which have been deemed to become the
Equipment property of the Employer under Clause 91.2 save
where such loss or damage is caused by an Excepted
Risk set out in Clauses 22.5 and 23.
No Approval by 91.11 The operation of this clause shall not imply any
Vesting approval by the Engineer of the materials or other
matters referred to herein nor shall it prevent the
rejection of any such materials at any time by the
Engineer.
times, namely:
Lien on Plant and 92.4 Neither the Contractor nor a sub-contractor nor any
Materials other Person shall have a lien on any Plant and
Materials which have vested in the Employer under
Clause 92.1 for any sum due to the Contractor,
sub-contractor or other Person and the Contractor
shall take all such steps as may reasonably be
necessary to ensure that the title of the Employer and
the exclusion of any such lien is reflected in any
sub-contract or other contractual arrangement
between the Contractor and any other Persons
dealing with any such Plant and Materials.
Amount of 93.1 For the purposes of Clause 84.1 the amount of each
Provisional Sum Provisional Sum together with any amounts stated in
the Pricing Document in respect of items for all other
charges and profit and for general attendance
related to Nominated Sub-Contracts shall, as at the
date of the Letter of Acceptance, be deemed to be
deducted from the total amount of the Cost Centre to
which such Provisional Sum relates. Thereafter no
part of such Provisional Sum (or of any such amount
so stated in the Pricing Document) shall be included
in or considered to form part of the Contract Price or
the total amount of the Cost Centre to which it
relates unless and until the Engineer shall issue an
order under Clause 93.2, in which event an amount
equal to the value determined in accordance with
Clause 80 or Clause 97.8, as the case may be, shall
be added to and form part of the Contract Price and
the total amount of the Cost Centre to which the
relevant Provisional Sum relates.
Prime Cost Item 93.3 In respect of every Prime Cost Item the Contractor
shall, unless otherwise instructed in writing by the
Engineer, enter into a sub-contract for the execution
of any work or the supply of any Plant and Materials
or services included in the Prime Cost Item with a
sub-contractor nominated by the Engineer in
accordance with the procedure set out in Clause
96.1. The Engineer shall also have power to order
the Contractor to execute any such work or to supply
any such Plant and Materials or services, in which
event the Contractor shall be paid in accordance
with the terms of a quotation submitted by him in
accordance with Clause 80.
SUB-CONTRACTORS
Nominated 96.1 Upon receipt of an order from the Engineer for work
Sub-Contractors: to be executed or Plant and Materials or services to
Details be supplied by a Nominated Sub-Contractor
pursuant to Clause 93.2 or Clause 93.3, the
Contractor shall forthwith enter into a sub-contract.
objection in writing.
Valuation of Work 97.8 For all work executed or Plant and Materials or
under Provisional services supplied by any Nominated Sub-Contractor,
Sums and Prime there shall be included in the Contract Price:
Cost Items
(a) the actual price paid or due to be paid by the
Contractor, on the direction of the Engineer, and
in accordance with the Sub-Contract;
Payment after 101.4 If the Employer shall enter and expel the Contractor
Forfeiture under Clause 101.1 he shall not be liable to pay to
the Contractor any money on account of the
Contract until the expiration of the Defects Liability
Period (or, where there is more than one such
period, the expiration of the latest such period) and
thereafter until the Costs of completion and
correction of defects, damages for any delay in
completion and all other expenses incurred by the
Employer have been ascertained and the amount
thereof certified by the Engineer. The Contractor
shall then be entitled to receive only such sum or
sums (if any) as the Engineer may certify would have
been due to him upon due completion by him after
deducting the said amount. But if such amount
shall exceed the sum which would have been
payable to the Contractor on due completion by him
then the Contractor shall upon demand pay to the
Employer the amount of such excess and it shall be
deemed a debt due by the Contractor to the
Employer and shall be recoverable accordingly.
Insolvency or 101.6 If :
Change in Control
(a) the Contractor shall become bankrupt or
insolvent or have a receiving order made
against him or shall present his petition in
bankruptcy or shall make an arrangement with
or assignment in favour of his creditors or shall
agree to carry out the Contract under a
committee of inspection of his creditors, or
being a corporation commence to be wound up
(such winding-up not being a members'
voluntary winding up for the purpose of
amalgamation or reconstruction), or shall have
a receiver appointed over all or any part of its
undertaking or assets or go into liquidation; or
Termination of Part 101.8 The Employer may in lieu of exercising his right of
forfeiture under Clause 101.1 take part only of the
Works out of the hands of the Contractor and may by
himself, his servants or agents execute, complete and
maintain such part and in such event the Employer
may recover his reasonable Costs of so doing from
the Contractor or deduct such Costs from money
otherwise becoming due to the Contractor from time
to time.
Outbreak of War 102.1 If during the currency of the Contract there shall be
an outbreak of war (whether war is declared or not)
in any part of the world which whether financially or
otherwise substantially affects the Execution of the
Works the Contractor shall unless and until the
Contract is terminated under the provisions
contained in this clause use his best endeavours to
complete the Execution of the Works provided
always that the Employer shall be entitled at any
time after such outbreak of war to terminate this
Contract by giving 14 Days notice in writing to the
Contractor and upon such notice being given this
Contract shall (save as to the rights of the parties
under this Clause 102 and to the operation of Clause
103) determine at the expiry of the 14 Days but
without prejudice to the rights of either party in
respect of any antecedent breach thereof.
Payment in Event 102.5 In the event of the Contract being frustrated whether
of Frustration by war or by any other supervening event which may
occur independently of the will of the parties the sum
payable by the Employer to the Contractor in respect
of the work executed shall be the same as that which
would have been payable under Clause 102.3 if the
Contract had been determined by the Employer under
Clause 102.1.
RESOLUTION OF DISPUTES
Settlement of 103.1 This Clause 103 shall apply to any and all disputes
Disputes: over any decision, opinion, instruction, direction,
Arbitration certificate, estimate or valuation of the Engineer, and
to all disputes between the Employer and the
Contractor which may arise out of or in connection
with the Contract or the carrying out of the Works.
Either party desiring redress, remedy or relief of any
kind against the other party in relation to any such
dispute shall pursue the same in accordance with the
procedure set out in this Clause 103, which shall be
the sole means of resolving disputes under the
Contract.
Notice of Dispute 103.2 For the purposes of Clauses 103.3 to 103.16 below, a
dispute shall be deemed to arise when one party
serves on the Engineer and on the other party a
Notice of Dispute.
Limitation Period 103.12 The parties agree that, in determining whether any
proceedings have been commenced within the
period after the relevant cause of action arose
allowed by the Limitation Ordinance (or any statutory
re-enactment or modification thereof) for the
commencement of litigation or arbitration
proceedings, such proceedings shall be deemed to
have commenced when the cause of action was
made the subject matter of a Notice of Dispute
served under Clause 103.2.
NOTICES
DEFAULT OF EMPLOYER
payment certificate,
CONDITIONS OF CONTRACT
FOR
APPENDIX A
FORMAL AGREEMENT
September 2020
D/MTRCL/NW/E&M/COC/001/A6
APPENDIX A
FORMAL AGREEMENT
BETWEEN
WHEREAS the Employer is desirous that certain Works should be constructed, namely the
Permanent Works and Temporary Works in connection with
1. In this Agreement words and expressions shall have the same meanings as
are respectively assigned to them in the Conditions of Contract hereinafter
referred to.
A1 September 2020
D/MTRCL/NW/E&M/COC/001/A6
2. The documents deemed to form and be read and construed as part of this
Agreement are those listed in the Letter of Clarification, Supplement to the
Letter of Clarification [delete if not applicable] and the Letter of Acceptance.
IN WITNESS whereof the parties hereto have caused this Agreement to be executed as a
deed the day and year first above written.
Director: ...............
Secretary: ..............
A2 September 2020
D/MTRCL/NW/E&M/COC/001/A6
OR
Notes:
(For preparation of but not inclusion in any engrossment of the Formal Agreement)
(a) Where the Contractor comprises more than one company, add:
(b) If the Contractor comprises more than one company each member of the joint
venture or consortium must execute this Formal Agreement.
(c) These notes and the reference within the text above to "Note a)" should be deleted
before the Formal Agreement is engrossed.
A3 September 2020
D/MTRCL/NW/E&M/COC/001/A6
CONDITIONS OF CONTRACT
FOR
APPENDIX B
BOND
September 2020
D/MTRCL/NW/E&M/COC/001/A6
APPENDIX B
BOND
WHEREAS:
B. At the request and for the account of the Contractor, the Bondsman has
agreed to provide this Bond,
1. Upon demand in writing made by the Employer upon the Bondsman from time
to time or at any time hereunder, the Bondsman shall forthwith pay to the
Employer the sum mentioned in the said demand, provided that any such
demand in writing shall be substantially in the form of either Annexure 1A or
Annexure 1B to this Bond, and as between the Employer and the Bondsman
the facts set out in that demand shall be deemed to be true.
B1 September 2020
D/MTRCL/NW/E&M/COC/001/A6
3. The liability of the Bondsman under this Bond shall remain in full force and
effect and shall not be affected or discharged in any way by any alteration to
the terms of the Contract or in the extent or nature of the Works to be carried
out thereunder with or without the Bondsman's knowledge and the
Bondsman's liability hereunder shall not be affected or discharged by any time
being given to the Contractor or by any other indulgence or concession to the
Contractor or by any forbearance forgiveness or any other thing done omitted
or neglected to be done under the Contract or by the termination of the
Contract or the employment of the Contractor or by any other bond security or
guarantee now or hereafter held by the Employer for all or any part of the
obligations of the Contractor under the Contract or by the release or waiver of
any such bond security or guarantee or by any other matter or thing which but
for this provision would or might affect or discharge the liability of the
Bondsman.
4. The liability of the Bondsman under this Bond shall be continuing and shall
remain in operation until the Contract shall have been duly and properly
performed and completed according to the true purport intent and meaning
thereof or until this Bond shall have been paid in full, whichever shall first
occur.
5. In the event of a formal agreement being entered into between the Employer
and Contractor pursuant to Clause 12.1 of the Conditions of Contract, whether
the same is executed under seal or under hand only, all references herein to
"the Contract" shall with effect from the execution of such agreement be
construed as references to the said formal agreement and to any conditions of
contract incorporated into the said formal agreement but this instrument shall
otherwise continue in full force and effect.
B2 September 2020
D/MTRCL/NW/E&M/COC/001/A6
8. The Employer shall be entitled to assign the benefit of this Bond at any time
without the consent of the Bondsman being required.
9. This Bond shall be governed by and construed according to the laws of Hong
Kong and the Bondsman hereby submits to the non-exclusive jurisdiction of
the courts of Hong Kong.
OR
B3 September 2020
D/MTRCL/NW/E&M/COC/001/A6
ANNEXURE 1A
Dear Sirs,
[Name of Project]
Contract No. [ ]
The Contractor has not taken steps, which we consider adequate to remedy the breaches
referred to in the enclosed copy letter.
We hereby demand payment from you forthwith of the sum of $[ ] under your
bond.
Yours faithfully,
B4 September 2020
D/MTRCL/NW/E&M/COC/001/A6
ANNEXURE 1B
Dear Sirs,
[Name of Project]
Contract No. [ ]
An event has occurred of the type described in Clause 101.6(a) of the Conditions of
Contract which entitles us (inter alia) to terminate the employment of the Contractor under
the Contract in accordance with Clause 101.6.
Yours faithfully,
B5 September 2020
D/MTRCL/NW/E&M/COC/001/A6
ANNEXURE 2
Dear Sirs,
[Name of Project]
Contract No. [ ]
As explained in previous letters to you, you are in breach of your obligations under Contract
No. [ ], and you have not proposed or implemented sufficient steps to
remedy those breaches.
This letter notifies you that unless within the next 14 days you take steps which we consider
adequate to remedy the breaches we shall be entitled without further notice to you to call
for payment under the bond given on your behalf by [the Bondsman].
Yours faithfully,
B6 September 2020
D/MTRCL/NW/E&M/COC/001/A6
CONDITIONS OF CONTRACT
FOR
APPENDIX C
September 2020
D/MTRCL/NW/E&M/COC/001/A6
APPENDIX C
BETWEEN:-
WHEREAS:-
B. Pursuant to the terms of the Contract, [the Contractor] [See Note (d)] has
agreed to procure the provision of a guarantee in the terms hereof.
C. At the request of [ ] | [the Contractor] [See Note (c)], the Guarantor has
agreed to provide this Guarantee.
C1 September 2020
D/MTRCL/NW/E&M/COC/001/A6
1. In consideration of the Employer entering into the Contract and any Formal
Agreement with [ ], in its capacity as a joint venture party to the Contractor]
|[and]| [the Contractor,] [See Notes (e) and (f)] the Guarantor irrevocably and
unconditionally guarantees to the Employer, as primary obligor and not merely
as surety, that [ ] |[and/or] | [the Contractor] [See Notes (e) and (f)] shall
properly and punctually perform every Obligation under or in connection with
the Contract and any Formal Agreement and shall comply with all the terms
and conditions thereof according to their true purport, intent and meaning and
with all the terms and conditions of any agreement entered into between the
Employer and [ ] | [and/or] | [the Contractor] [See Notes (e) and (f)]
pursuant to Clause 12.1 of the Conditions of Contract including without
limitation any Obligation on the part of [ ] | [and/or] | [the Contractor][see
Notes (e) and (f)] to indemnify the Employer against any losses, claims,
damages, costs and expenses. If there is default in respect thereof by [ ]
|[and/or] | [the Contractor] [See Notes (e) and (f)] or if [ ] | [and/or] | [the
Contractor] [See Notes (e) and (f)] shall become liable in contract, tort or
otherwise to the Employer in connection with the Works to be performed, or
that have been performed, by [ ] | [and/or] | [the Contractor] [See Notes (e)
and (f)] under or in connection with the Contract and any Formal Agreement,
then the Guarantor will indemnify the Employer on demand against and in
respect of all losses, claims, damages, costs and expenses thereby suffered or
incurred by the Employer to the extent that [ ] | [and/or] | [the Contractor]
[See Notes (e) and (f)] is or would be liable for the same.
2. The Guarantor shall not be discharged or released from this Guarantee by:
C2 September 2020
D/MTRCL/NW/E&M/COC/001/A6
3. This Guarantee shall not in any way be prejudiced or affected by any other
bond, security or guarantee now or hereafter held by the Employer for all or
any part of the Obligations whose performance is hereby guaranteed or the
release or waiver thereof. This Guarantee may be enforced without first
having recourse to any such bond, security or guarantee or taking any steps or
proceeding against [ ] | [and/or] | [the Contractor] [See Notes (e) and (f)].
4. This Guarantee is a continuing guarantee and accordingly shall cover all of the
Obligations and liabilities of [ ] | [and/or] | [the Contractor] [See Notes (e)
and (f)] under the Contract and any Formal Agreement and shall remain in full
force and effect until the latter of:
(a) all the Obligations of the Contractor have been carried out completed and
discharged to the satisfaction of the Employer in accordance with the
Contract and any Formal Agreement; or
(b) the expiry of the applicable Hong Kong statutory limitation period.
5. The Employer shall be entitled to assign the benefit of this Guarantee at any
time without the consent of the Guarantor or [ ] | [and/or] | [the Contractor]
[See Notes (e) and (f)] being required.
C3 September 2020
D/MTRCL/NW/E&M/COC/001/A6
IN WITNESS whereof this Guarantee has been executed as a Deed on the day first before
written.
OR
NOTES:
(a) For preparation of, but not inclusion in, the engrossment of the Guarantee.
(c) If the Contractor does not comprise of more than one company, reference should be
made to the “Contractor” only and delete Recital [D].
(d) If the Contractor comprises more than one company, Recital [A] must note the
existence of the unincorporated joint venture arrangement (or other relevant
agreement) and the relationship of the Guarantor to the relevant company forming
part of the Contractor.
(e) If each parent company is required to guarantee the Contractor and its relevant
subsidiary, then refer to the subsidiary and “the Contractor”, and include the words
“and” or “and/or” (as the case may be).
(f) If it is agreed to accept separate guarantees from each parent company which will
only guarantee the relevant subsidiary, delete references to “the Contractor” and
the words “and” or “and/or” (as the case may be).
C4 September 2020
D/MTRCL/NW/E&M/COC/001/A6
CONDITIONS OF CONTRACT
FOR
APPENDIX D
September 2020
D/MTRCL/NW/E&M/COC/001/A6
APPENDIX D
BETWEEN:-
WHEREAS:-
B. Pursuant to the terms of the Contract, the Contractor has agreed to procure
the provision of a guarantee in the terms hereof.
C. At the request of the Contractor, the Guarantors have agreed to provide this
Guarantee.
D1 September 2020
D/MTRCL/NW/E&M/COC/001/A6
1. In consideration of the Employer entering into the Contract and any Formal
Agreement with the Contractor, the Guarantors, jointly and severally,
irrevocably and unconditionally guarantee to the Employer, as primary obligors
and not merely as sureties, that the Contractor shall properly and punctually
perform every Obligation under or in connection with the Contract and any
Formal Agreement and shall comply with all the terms and conditions thereof
according to their true purport, intent and meaning and with all the terms and
conditions of any agreement entered into between the Employer and the
Contractor pursuant to Clause 12.1 of the Conditions of Contract including
without limitation any Obligation on the part of the Contractor to indemnify the
Employer against any losses, claims, damages, costs and expenses. If there
is default in respect thereof by the Contractor or if the Contractor shall become
liable in contract, tort or otherwise to the Employer in connection with the
Works to be performed, or that have been performed, by the Contractor under
or in connection with the Contract and any Formal Agreement, then the
Guarantors will, jointly and severally indemnify the Employer on demand
against and in respect of all losses, claims, damages, costs and expenses
thereby suffered or incurred by the Employer to the extent that the Contractor is
or would be liable for the same.
2. The Guarantors shall not be discharged or released from this Guarantee by:
(a) any arrangement made between the Contractor and the Employer
without the assent of the Guarantors;
(b) any termination of the Contract or the Formal Agreement or of the
employment of the Contractor for any reason;
(c) any alteration in the Obligations undertaken by the Contractor or
variation of the Contract or the Formal Agreement;
(d) any forbearance or forgiveness extended by the Employer to the
Contractor whether as to payment time performance or otherwise and
whether such alteration variation or forbearance or forgiveness shall be
made or extended with or without the knowledge or consent of the
Guarantors; or
(e) any other matter or thing which but for this provision would or might
discharge or release the Guarantors.
D2 September 2020
D/MTRCL/NW/E&M/COC/001/A6
3. This Guarantee shall not in any way be prejudiced or affected by any other
bond, security or guarantee now or hereafter held by the Employer for all or any
part of the Obligations whose performance is hereby guaranteed or the release
or waiver thereof. This Guarantee may be enforced without first having
recourse to any such bond, security, or guarantee or taking any steps or
proceeding against the Contractor.
4. This Guarantee is a continuing guarantee and accordingly shall cover all of the
Obligations and liabilities of the Contractor under the Contract and any Formal
Agreement and shall remain in full force and effect until the latter of:
(a) all the Obligations of the Contractor have been carried out completed
and discharged to the satisfaction of the Employer in accordance with the
Contract and any Formal Agreement; or
(b) the expiry of the applicable Hong Kong statutory limitation period.
5. The Employer shall be entitled to assign the benefit of this Guarantee at any
time without the consent of the Guarantors or the Contractor being required.
IN WITNESS whereof this Guarantee has been executed as a Deed on the day first before
written.
D3 September 2020
D/MTRCL/NW/E&M/COC/001/A6
OR
OR
NOTES:
(a) For preparation of, but not inclusion in, the engrossment of the Guarantee.
(c) If the Contractor is an incorporated joint venture, reference should be made to the
“Contractor” only.
(d) If the Contractor comprises more than one company (unincorporated joint venture)
Recital A must note the existence of the unincorporated joint venture arrangement
(or other relevant agreement) and the relationship of the relevant Guarantor to the
relevant company forming part of the Contractor.
D4 September 2020
D/MTRCL/NW/E&M/COC/001/A6
CONDITIONS OF CONTRACT
FOR
APPENDIX E
September 2020
D/MTRCL/NW/E&M/COC/001/A6
APPENDIX E
TABLE OF CONTENTS
CONDITIONS
SCC1 Measurement E1
E1 September 2020
D/MTRCL/NW/E&M/COC/001/A6
APPENDIX E
A. Where these Special Conditions of Contract amend, vary or modify in any way
whatsoever the application or interpretation of the Conditions of Contract, the
Conditions of Contract shall be so amended, varied or modified.
SCC1 MEASUREMENT
1.1 In respect of the Works or any part of the Works to which pursuant to Clause 83.1
of the Conditions of Contract these Special Conditions of Contract apply:
(a) Quantities
The quantities set out in the Pricing Document are estimated quantities of
the work and are not to be taken as the actual and correct quantities of
the work to be executed by the Contractor.
E2 September 2020
D/MTRCL/NW/E&M/COC/001/A6
The Engineer shall when he requires any part or parts of the work to be
measured give reasonable notice to the Contractor who shall attend or
send a qualified agent to assist the Engineer or the Engineer's
Representative in making such measurement and shall furnish all
particulars required by either of them. Should the Contractor not attend
or neglect or omit to send such agent then the measurement made by the
Engineer or Approved by him shall be taken to be the correct
measurement of the work.
2.1 Add the following new Clauses 85.3(S) to 85.6(S) after Clause 85.2 of the
Conditions of Contract:
85.4(S) For the purpose of Clause 85.3(S), the adjustment in respect of each
payment certificate shall be calculated by multiplying the “Combined
Price Fluctuation Factor” by the “Effective Value”, where:
E3 September 2020
D/MTRCL/NW/E&M/COC/001/A6
(i) the amount which in the opinion of the Engineer is due to the
Contractor under 84.2 of the Conditions of Contract; and
(ii) the amount calculated in accordance with (i) above in the last
preceding interim certificate.
85.6(S) For clarity, the “Effective Value” shall exclude the following:
(ix) the increase or decrease to the value of Cost Centre arising from
admeasurement;
E4 September 2020
D/MTRCL/NW/E&M/COC/001/A6
4.1 Add the following new Clause 106(S) – Incentive Payment for Safety and
Environmental Performance:
E5 September 2020
D/MTRCL/NW/E&M/COC/001/A6
CONDITIONS OF CONTRACT
FOR
APPENDIX F
September 2020
D/MTRCL/NW/E&M/COC/001/A6
APPENDIX F
BETWEEN :
WHEREAS
B The Contractor wishes to enter into an agreement with the Sub-Contractor ("the
Sub-Contract") for the Sub-Contractor to carry out and complete a part of the Works
as more particularly described in the Sub-Contract ("the Sub-Contract Works").
F1 September 2020
D/MTRCL/NW/E&M/COC/001/A6
C The Main Contract provides that the Contractor shall procure that the Sub-Contractor
enters into a warranty under seal in favour of the Employer.
1. The Sub-Contractor warrants to the Employer that he will execute and complete the
Sub-Contract Works and carry out each and all of his duties and obligations under
the Sub-Contract in a good and workmanlike manner and in accordance with the
terms of the Sub-Contract (as the same may from time to time be varied or amended
with the prior consent of the Employer).
2. The Sub-Contractor undertakes to indemnify the Employer from and against the
consequences of any breach by the Sub-Contractor of any of the warranties and
undertakings in this Warranty provided that the Sub-Contractor shall be liable to the
Employer by virtue of this Warranty only insofar as and to the extent that the
Contractor is liable to the Employer under the Main Contract by reason of any breach
by the Sub-Contractor of his obligations under the Sub-Contract or this Warranty.
(a) the Sub-Contractor, his servants, agents and sub-contractors of any level and
each of them will exercise all the skill, care and diligence of a properly qualified
and competent professional or contractor experienced in carrying out work of a
similar size, scope and complexity to the Sub-Contract Works in:
(i) the design of the Sub-Contract Works insofar as the Sub-Contract Works
are required to be designed by or on behalf of the Sub-Contractor; and
(ii) the selection of materials and goods for the Sub-Contract Works insofar as
such materials and goods are required to be selected by or on behalf of
the Sub-Contractor;
F2 September 2020
D/MTRCL/NW/E&M/COC/001/A6
(b) the Sub-Contract Works and all materials and goods comprised therein will
correspond as to description, quality and condition with the requirements of the
Sub-Contract and be of sound manufacture and workmanship;
(c) the Sub-Contract Works will on completion comply in all respects with any
performance specification or requirement insofar as such performance
specification or requirement is included or referred to in the Sub-Contract, and
any part of the Sub-Contract Works designed or to be designed by the
Sub-Contractor will on completion comply with the relevant Approved Design
Data;
(d) the Sub-Contract Works will comply with any enactment or statutory
requirement (or any procedures in respect thereof) applicable to the
Sub-Contract Works.
(a) save insofar as he is delayed by a reason for which the Contractor could obtain
an extension of time under the Contract (except for delay or default on the part
of the Sub-Contractor) supply the Employer or the Contractor with all drawings,
documents and information (including, without limitation, notices, programmes
and Design Data (if any) ) which the Sub-Contractor is required by the
Sub-Contract to provide at such times as the Employer or the Contractor
respectively may reasonably require and in any event so that the Engineer
appointed under the Main Contract will not be delayed in issuing instructions or
drawings to the Contractor for which delay the Contractor might have a valid
claim to an extension of time for completion of the Works or any part thereof or
a valid claim for loss and/or expense; and
F3 September 2020
D/MTRCL/NW/E&M/COC/001/A6
6. (a) The Sub-Contractor shall not exercise or seek to exercise any right which may
be or may become available to the Sub-Contractor to terminate the
Sub-Contract or treat the same as having been terminated or discontinue or
suspend the performance of any of his duties and obligations under the
Sub-Contract or treat his employment under the Sub-Contract as determined
without first giving to the Employer not less than 21 days prior notice in writing
of his intention to do so ("the Sub-Contractor's Notice") and specifying in such
notice his grounds for doing so.
(b) Within 21 days of the date of the Sub-Contractor's Notice or, if the
Sub-Contract or the employment of the Sub-Contractor thereunder shall be
automatically terminated pursuant to any of its provisions, within 21 days of
such automatic termination, the Employer may give written notice to the
Sub-Contractor ("the Novation Notice") that the Employer shall be substituted
for the Contractor as the first-named party to the Sub-Contract in accordance
with sub-clause (c) below.
(c) With effect from the date of the service of any Novation Notice:
(i) the Employer shall be substituted for the Contractor in the Sub-Contract
and all references in the Sub-Contract to the Contractor shall be construed
as references to the Employer;
(ii) the Sub-Contractor shall be bound to continue with the performance of his
duties and obligations under the Sub-Contract and any exercise or
purported exercise by the Sub-Contractor prior to the date of the Novation
Notice of any right to terminate the Sub-Contract or treat the same as
having been terminated or to discontinue or suspend the performance of
F4 September 2020
D/MTRCL/NW/E&M/COC/001/A6
(iii) the Employer shall become and be bound to perform all obligations and
duties of the Contractor under the Sub-Contract which fall to be performed
after the date of the Novation Notice and shall as soon as practicable
thereafter make payment of any amounts properly due to the
Sub-Contractor as at the date of the Novation Notice and still outstanding;
(iv) the Contractor shall be released from further performance of the duties
and obligations of the Contractor under the Sub-Contract, but without
prejudice to any rights and remedies of the Sub-Contractor against the
Contractor in respect of any matter or thing done or omitted to be done on
or before the date of service of the Novation Notice.
7. Entirely without prejudice to the rights and obligations as between the Employer and
the Sub-Contractor set out in this Warranty, the Sub-Contractor shall in addition
indemnify the Contractor for any losses, damages, costs and charges incurred by the
Contractor as a result of any breach by the Sub-Contractor of the terms of the
Warranty.
F5 September 2020
D/MTRCL/NW/E&M/COC/001/A6
10. For the purposes of this Warranty, the terms "Design Data", "Approved Design Data",
"ABWF Works", "Intellectual Property Rights", "Railway" and "Railway under
Construction" shall have the same meanings as are ascribed to those terms in the
Main Contract.
11. In the event of any ambiguity or conflict between the terms of the Sub-Contract and
this Warranty, the terms of this Warranty shall prevail.
12. The provisions of this Warranty shall be without prejudice to and shall not be deemed
or construed so as to limit or exclude any rights or remedies which the Employer may
have against the Sub-Contractor whether in tort or otherwise.
13. Subject to Clause 6 of this Warranty, nothing contained in this Warranty shall vary or
affect the Sub-Contractor's rights and obligations under the Sub-Contract.
14. The Employer shall be entitled to assign the benefit of this Warranty at any time
without the consent of the Sub-Contractor being required.
15. The Contractor has executed this Warranty as confirmation of his concurrence with
and acceptance of the above arrangements and that he will observe and comply with
the same.
16. This Warranty shall be governed by and construed according to the laws of Hong
Kong and the parties submit to the non-exclusive jurisdiction of the Hong Kong
Courts.
F6 September 2020
D/MTRCL/NW/E&M/COC/001/A6
IN WITNESS whereof this Warranty has been executed as a Deed on the date first before
written.
Director _______________________
Secretary______________________
OR
F7 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Director _____________________
Secretary____________________
OR
______________________________
Notes :
(for preparation of but not inclusion in the engrossment of this Warranty).
(a) Where the Contractor comprises more than one company, it will be necessary to
add at this point:
(b) If the Contractor comprises more than one company each member of the joint
venture or consortium must execute this Sub-Contract Warranty.
(c) These notes and the reference within the text to "Note a)" should be deleted
before the Sub-Contract Warranty is engrossed..
F8 September 2020
D/MTRCL/NW/E&M/COC/001/A6
CONDITIONS OF CONTRACT
FOR
APPENDIX G
September 2020
D/MTRCL/NW/E&M/COC/001/A6
APPENDIX G
MEDIATION
1.1 These Rules are the MTRCL Mediation Rules (November 1992 Edition).
1.2 Mediation under these Rules is a private dispute resolution process in which a
neutral person ("the mediator") helps the parties to reach a negotiated
settlement. It should be entered into by both parties with an open mind in an
attempt to settle the dispute amicably. The mediation process will be
administered by the Hong Kong International Arbitration Centre ("HKIAC").
1.3 Either party may require the other party to participate in a mediation process in
accordance with these Rules, as provided for in the Conditions of Contract to
which these Rules are appended ("the Conditions of Contract"), but neither
party shall be bound by an opinion, report, direction or order of the mediator
except for an order in relation to costs made under Rule 20. The Conditions
of Contract require that all issues arising in a dispute shall have been the
subject of a reference to mediation in accordance with these Rules as a
condition precedent to the taking of any steps in an arbitration apart from the
formal appointment of an arbitrator.
1.4 Words and expressions used in these Rules shall have the meaning assigned
to them in the Conditions of Contract.
2.1 In relation to any dispute which has been referred to arbitration in accordance
with Clause 103.5 of the Conditions of Contract either party may initiate a
mediation by delivering a written request for mediation ("the Request for
G1 September 2020
D/MTRCL/NW/E&M/COC/001/A6
Mediation") to the other party with copies to the Engineer and to HKIAC, but no
mediation shall without the written consent of both parties be so initiated until
thirty (30) days have elapsed after the issue of the Certificate of Completion for
the whole of the Works or the determination or abandonment of the Contract,
or the determination of the Contractor's employment under the Contract
(whichever shall happen first).
2.2 The Request for Mediation shall contain a brief self-explanatory statement of
the nature of the dispute, the quantum in dispute (if any), and the relief or
remedy sought.
THE MEDIATOR
4.1 Within seven (7) days after the delivery of the Request for Mediation the
parties shall exchange lists of those persons each of them proposes should be
invited to act as mediator. Each party's list shall propose a minimum of two (2)
persons, each of whom shall have confirmed that he is willing and able to act
as the mediator.
4.2 Within fourteen (14) days of the parties' exchange of lists pursuant to Rule 4.1
above the parties shall attempt to agree a person willing and able to act as the
mediator and, failing agreement, either party may request HKIAC to nominate
a mediator. Likewise, in the event that one party fails to provide a list of
proposed mediators in accordance with Rule 4.1 above, the other party may
request HKIAC to nominate a mediator.
4.3 Within fourteen (14) days of receipt of a request for nomination, HKIAC shall
nominate a mediator who is prepared to serve and is not disqualified under
Rule 6.
G2 September 2020
D/MTRCL/NW/E&M/COC/001/A6
5.1 Subject to Rule 6, the mediation shall be deemed for the purposes of these
Rules to commence on the date ("the Mediation Commencement Date") of
appointment of a person willing and able to act as mediator being the date
upon which:
5.1.1 The parties agree the identity of the mediator under Rule 4.2 or
otherwise; or
5.1.2 HKIAC makes a nomination under Rule 4.3; or
5.2 The party who served the Request for Mediation shall notify the Engineer and
HKIAC in writing of the identity of the mediator upon receipt of confirmation
from that person of his acceptance of the appointment.
6. No person shall serve as mediator in any dispute in which that person has any
financial or personal interest in the result of the mediation except by written
consent of the parties. Prior to accepting an appointment, the proposed
mediator shall disclose to HKIAC any circumstances likely to create a
presumption of bias or prevent a prompt resolution of the dispute. Upon
receipt of the information HKIAC shall immediately communicate the
information in writing to the parties for their comments. If any party serves a
written objection to the proposed mediator within seven (7) days of receipt of
such communication, he shall not be appointed. In such a case, within
fourteen (14) days of such written objection the HKIAC shall nominate a further
mediator in accordance with the terms of Rule 4.3.
7. The mediator shall enter upon the mediation as soon as possible after his
appointment and shall use his best endeavours to conclude the mediation
(which for the avoidance of doubt will include provision of any report which
may be required by Rule 15) as expeditiously as possible, but in any event the
G3 September 2020
D/MTRCL/NW/E&M/COC/001/A6
mediation process shall not continue for more than forty-two (42) days after the
Mediation Commencement Date unless the parties agree otherwise.
8. The parties shall at all times give assistance to the mediator to enable the
mediation to proceed.
10. The mediator shall inform himself in any way he thinks fit of the nature and
facts of the dispute including requiring the Engineer to see him.
11. The mediator shall conduct the mediation in such a manner as will permit full
and expeditious presentation to him by the parties of their views. The
mediator may see the parties together or separately for the purpose of
informing himself of the nature and facts of the dispute.
13. During the course of the mediation, the mediator may attempt various
compromise solutions with the parties in an informal manner. Should a
solution be agreed it will be accepted by both parties in accordance with Rule
17.
14. In the event that the mediator is unable to facilitate a satisfactory resolution, he
shall first notify the parties orally of his views.
G4 September 2020
D/MTRCL/NW/E&M/COC/001/A6
those facts as found by him), and proposing terms of settlement which seem to
him to be appropriate. Within fourteen (14) days of receipt of the report the
parties will indicate, each to the other, whether the mediator's proposed terms
of settlement are acceptable in whole or in part. If, however, the mediator is
unable to produce a full report as envisaged by this Rule, he may at his
discretion produce a report on his views however incomplete or tentative if he
considers that it might assist the parties to resolve the dispute.
16. Notwithstanding Rule 7 but subject to producing any report requested under
Rule 15, the mediator may abandon the mediation whenever in his judgment
further efforts at mediation would not lead to a settlement of the dispute. The
mediator shall notify the parties in writing of any such abandonment by him,
whereupon the mediation shall automatically be terminated and the arbitration
previously commenced between the parties may proceed in accordance with
Clause 103.11 following such abandonment.
17. The mediation is regarded as being a private and confidential matter between
the parties to the Contract and the procedures of the mediation should be so
conducted. In the event that the mediation is successful, neither party shall
be bound until the terms of the settlement have been recorded in writing and
signed by both parties. Copies of the signed agreement shall be provided to
the Engineer by the party issuing the Request for Mediation, who shall also
inform HKIAC that the dispute has been settled.
18. Nothing that transpires during the course of the mediation (other than a signed
settlement agreement) is intended to or shall in any way affect the rights or
prejudice the position of the parties to the dispute under the Contract or in any
subsequent arbitration or litigation, and without derogating from the generality
of the foregoing and merely by way of example:
(b) the fact that information of whatsoever nature was made available to
the mediator does not mean that privilege or confidentiality is waived
for any subsequent arbitration or litigation; and
G5 September 2020
D/MTRCL/NW/E&M/COC/001/A6
(c) the fact that the accuracy of information or the validity or meaning of
documents was not challenged during the mediation does not
preclude challenge in subsequent arbitration or litigation.
COSTS
19.1 Each party shall within seven (7) days of the Mediation Commencement Date
deposit the sum of HK$50,000 with HKIAC as a payment on account of the
cost and proper expenses of the mediation. The sum of HK$50,000 is subject
to review and adjustment by HKIAC.
19.2 The mediator may at any time during the course of the mediation require the
parties to make a further deposit or deposits with HKIAC to cover anticipated
additional fees and expenses.
19.3 In the event of default by a party in making a deposit required under Rule 19.1
or 19.2, the other party may either:
19.3.1 make such payment itself, in which case the provisions of Rule 20.1
will apply; or
19.3.2 serve notice on the party in default requiring payment within seven (7)
days failing which the mediation shall be deemed to be abandoned.
19.4 Subject to any order the mediator may make under Rule 20:
19.4.1 all fees and expenses of the mediator (including any costs incurred
pursuant to Rule 12) and all administrative costs and expenses of the
mediation and of the HKIAC shall be borne equally by the parties and
each party shall bear its own costs regardless of the outcome of the
mediation or of any subsequent arbitration or litigation;
19.4.2 at the conclusion of the mediation, HKIAC shall deduct the costs and
expenses of the mediation from the monies deposited under Rule
19.1 or 19.2 and shall return any surplus as follows:
G6 September 2020
D/MTRCL/NW/E&M/COC/001/A6
19.4.2.1 in the event and to the extent of any payment made under
Rule 19.3.1, to the party making such payment;
19.4.3 in the event that at the conclusion of the mediation the costs and
expenses of the mediation exceed the monies deposited under Rules
19.1 or 19.2, the mediator may order the shortfall to be paid equally
by the parties. The Employer will pay the full amount of the shortfall
to HKIAC within twenty-one (21) days of such order and the
Contractor will reimburse the Employer half the amount of such
shortfall within twenty-eight (28) days of such order.
20.1.1 to order one party to reimburse the other party such sum or sums as
may have been deposited by the other party under Rule 19.3.1 to the
extent that such sum or sums will not be refunded by HKIAC in
accordance with Rule 19.4.2.1;
20.1.2 in the event that the mediator finds that the mediation has been
initiated or conducted frivolously or vexatiously, to order the party
who in his opinion initiated or conducted the mediation in a frivolous
or vexatious manner to reimburse the other party, in full or in such
part as the mediator considers appropriate, in respect of:
20.1.2.1 the other party's liability for the fees and expenses of the
mediator and the administrative costs of the mediation;
and/or
G7 September 2020
D/MTRCL/NW/E&M/COC/001/A6
20.2 Both parties agree to be bound by an order of the mediator made under Rule
20.1 and any liability on one party to make payment to the other party pursuant
to such an order shall be deemed a debt due.
21. The mediator shall not be appointed as arbitrator in any subsequent arbitration
between the parties, whether arising out of the dispute or otherwise arising out
of or in connection with the Contract, unless the parties agree otherwise in
writing. Neither party shall be entitled to call the mediator as a witness in any
subsequent arbitration or litigation arising out of or in connection with the
Contract. Any communications whether oral or written which either party
shall have with the mediator or with other parties in connection with the
mediation shall be absolutely privileged.
WRITTEN RECORD
22. No formal written record shall be kept of the mediation process. Any written
view expressed under Rule 12, the written report provided for in Rule 15 and
any notes or record made by the mediator, and/or the parties, shall remain
private and confidential and not subject to disclosure in any subsequent
proceedings.
EXCLUSION OF LIABILITY
23. It is agreed that the mediator and the HKIAC shall not be liable to any party for
any act or omission in connection with any mediation conducted under these
Rules, save for the consequences of fraud or dishonesty.
LANGUAGE
24. The language of the mediation shall be English and all written communications
and all hearings shall be conducted in the English language unless the parties
and the mediator otherwise agree.
G8 September 2020