AGENDA

FOLLOW-UP CP ALIGNMENT MEETING


SASOL SATELITE OPERATION
27 SEP 2021
NO ITEM RESPONSIBLE PERSON
1. Opening and Welcome Chairperson

2.
Complete earthing of the station:

 Studs welds to be done and install lighting arrestor.



Stud weld on both sides of the gas inlet section IJ:

 Studs welds to be done and install lighting arrestor.

Connect a lightning arrestor across the IJ:

 Studs welds to be done and install lighting arrestor.

Stud weld for an additional stud onto which to attach an earth cable:

 No TPs.
Detailed SOW for SP:

 Sasol Sat Ops.


Execution Date:

 Studs welds to be done and install lighting arrestor.