LOOKAHEAD 10/4/2021 Printed on 10/4/2021 10:47 AM

0 Advance or retard days POB 111 MAX POB 114 without Hot Bed

0 RIG: RAISIS- Apexindo Swamp Barge WELL: HCB-247/258


Page 1
Mon 04 Oct Tue 05 Oct Wed 06 Oct Thu 07 Oct Fri 08 Oct
0:00 Pump hidens & circulate for Cleaning sequenc 0:00 0:00 0:00 Move out from platform 0:00
1:00 1:00 1:00 M/up and land pre stab tubing hanger assy w/ 1:00 Ballasting 1:00 M/U & RIH 12-1/4" drilling BHA to ± 92 mMD.
2:00 2:00 2:00 2:00 2:00
3:00 3:00 3:00 Set debris catcher. L/D landing joint. 3:00 3:00 Wash down to CP shoe at 105 mMD while take
4:00 4:00 4:00 LIFT BOP & Put on Stump 4:00 4:00
5:00 Pump OOH Motor BHA to top of BHA. Flow ch 5:00 5:00 5:00 5:00 Drill f/ 105 to 200 m
6:00 6:00 6:00 6:00 6:00
7:00 Pump OOH to surface. L/D BHA. 7:00 POOH PT/FA 7:00 Transfer X-Tree to moon pool area. 7:00 7:00
8:00 8:00 8:00 8:00 8:00 Drill f/ 200 to 300 m
9:00 9:00 9:00 L/D 44 stands 5" DP + 8 stands 5" HWDP from 9:00 9:00
10:00 PJSM. R/U Halco surface equipment. 10:00 Retrieve wear bushing & wash tubing hanger la10:00 10:00 10:00 Drill f/ 300 to 400 m
11:00 11:00 R/U tubing handling equipment. PJSM 11:00 11:00 11:00
12:00 M/U wireline logging tool & surface test 12:00 RIH 3-1/2" tubing to 9-5/8" casing 12:00 12:00 12:00
13:00 RIH - PT/FA 13:00 13:00 13:00 13:00 Drill f/ 400 to 500 m
14:00 14:00 14:00 14:00 14:00
15:00 15:00 Break circulate. 15:00 15:00 15:00 Drill f/ 500 to 600 m
16:00 16:00 RIH 3-1/2" tubing in open hole to TRSV. 16:00 16:00 16:00
17:00 17:00 17:00 Sea fastening & prepare for rig move 17:00 17:00
18:00 18:00 18:00 Deballast 18:00 18:00 Drill f/ 600 to 666 m
19:00 19:00 19:00 19:00 19:00
20:00 20:00 20:00 20:00 20:00 Circulate for Cleaning sequence
21:00 21:00 Continue RIH to last joint before tubing hanger 21:00 21:00 21:00 Last Survey & Flow check.
22:00 22:00 22:00 22:00 22:00 Spot Hivis
23:00 23:00 23:00 23:00 23:00
EQUIPMENT FROM RIG EQUIPMENT FROM RIG EQUIPMENT FROM RIG EQUIPMENT FROM RIG EQUIPMENT FROM RIG

EQUIPMENT TO RIG EQUIPMENT TO RIG EQUIPMENT TO RIG EQUIPMENT TO RIG EQUIPMENT TO RIG

Slickline Riser
Anadrill BHA for HYA

(To Rig) CREWCHANGE (From Rig) (To Rig) CREWCHANGE (From Rig) (To Rig) CREWCHANGE (From Rig) (To Rig) CREWCHANGE (From Rig) (To Rig) CREWCHANGE (From Rig)

3 Expro Slickline Expro Slickline 3 Rig Mover 2 1 PHM DCSV 1


Hallco Logging 5 Baker MTGL Eng 1 PHM Topo Supv 1
PHM DRL Eng. 1 Hallco Comp. 1 Pageo 5
CWO Tech 2 Primacom 1
2 Rig Mover
1 PHM Topo Supv
5 Pageo
2 Primacom
2 SDI

0 0 3 6 12 7 0 9 1 1
POB 111 POB 108 POB 113 POB 104 POB 104
VESSELS VESSELS VESSELS VESSELS VESSELS
ST Dorado ST Dorado ST Dorado ST Dorado ST Dorado
DP Barge Winsen-03 DP Barge Winsen-03 DP Barge Winsen-03 DP Barge Winsen-03 DP Barge Winsen-03