PROYECTO : "CREACIÓN DEL SERVICIO ACADÉMICO DE LA FACULTAD DE MEDICINA HUMANA DE LA UNIVERSIDAD NACIONAL SANTIAGO ANTÚNEZ DE MAYOLO - DISTRITO DE HUARAZ -
PROVINCIA DE HUARAZ - DEPARTAMENTO DE ANCASH"
fecha de
CONCRETO m3 Estruct # Factor Largo Ancho Alto Parcial f´c
vaciado
C1, C2, C3, C4, C5, C6 y C7 7.00 1.00 0.50 0.50 2.40 4.20 280.00
C8 1.00 1.00 0.50 0.50 2.40 0.60 280.00
C9 (Circular) 1.00 1.00 0.64 2.40 1.54 280.00
C10 1.00 1.00 0.55 0.55 2.40 0.73 280.00
C11-C12 2.00 1.00 0.50 0.50 2.40 1.20 280.00
C13-C14 2.00 1.00 0.60 0.60 2.40 1.73 280.00
C15 (Circular) 1.00 1.00 0.64 2.40 1.54 280.00
C16 (Circular) 1.00 1.00 0.64 2.40 1.54 280.00
C17 (Circular) 1.00 1.00 0.64 2.40 1.54 280.00
C18 1.00 1.00 0.60 0.60 2.40 0.86 280.00
C19-C20 2.00 1.00 0.50 0.50 2.40 1.20 280.00
C21, C22, C23, C24, C25, C26, C27 y C28 8.00 1.00 0.60 0.60 2.40 6.91 280.00
C29 1.00 1.00 0.60 0.60 2.40 0.86
C30 1.00 1.00 0.60 0.60 2.40 0.86
C31 1.00 1.00 0.50 0.50 2.40 0.60
C32 1.00 1.00 0.50 0.50 2.40 0.60
C33, C34, C35, C36, C37, 38, C39, C40 y C41 9.00 1.00 0.50 0.50 2.40 5.40
C42-C43 2.00 1.00 0.50 0.50 2.40 1.20
C44 (Circular) 1.00 1.00 0.16 2.40 0.38 280.00
C45, C46, C47 y C48 4.00 1.00 0.25 0.25 2.40 0.60 280.00
C49-C50 2.00 1.00 0.25 0.25 2.40 0.30 280.00
C51 1.00 1.00 0.25 0.25 2.40 0.15 280.00
C52, C53, C54 y C55 4.00 1.00 0.16 2.40 1.54 280.00
C56 1.00 1.00 0.45 0.90 2.40 0.97 280.00 6/1/2021
C57 1.00 1.00 0.45 0.90 2.40 0.97
C58 1.00 1.00 0.45 0.90 2.40 0.97 280.00 6/1/2021
C59, C61, C62, C63, C64, C65 y C67 7.00 1.00 0.45 0.90 2.40 6.80
C60 1.00 1.00 0.45 0.90 2.23 0.90 280.00 6/5/2021
C66 1.00 1.00 0.45 0.90 2.40 0.97 280.00
C68-C69 2.00 1.00 0.30 0.60 2.23 0.80 280.00 6/1/2021
C70-C71 2.00 1.00 0.30 0.60 2.40 0.86 280.00
PL1 1.00 1.00 3.34 2.40 8.02 280.00 6/1/2021
PL2 1.00 1.00 7.32 2.40 17.57 280.00 6/1/2021
PL3 1.00 1.00 4.92 0.30 2.40 3.54 280.00 6/5/2021
PL4 1.00 1.00 4.92 0.30 2.40 3.54 280.00 6/1/2021
PL4 1.00 1.00 4.92 0.30 3.20 4.72 280.00 6/5/2021
M1 1.00 1.00 31.00 0.30 2.40 22.32
M2 1.00 1.00 3.90 0.30 2.40 2.81
M3 1.00 1.00 4.50 0.30 2.40 3.24
M4 1.00 1.00 8.50 0.30 2.40 6.12
M5 1.00 1.00 3.25 0.30 2.40 2.34
M6 1.00 1.00 4.26 0.30 2.40 3.07
M7 1.00 1.00 4.40 0.30 2.40 3.17
M8 1.00 1.00 8.50 0.30 2.40 6.12
MC1 1.00 1.00 4.22 0.30 2.40 3.04
MC2 1.00 1.00 3.55 0.30 2.40 2.56
MC3 1.00 1.00 3.55 0.30 2.40 2.56
MDR1 1.00 1.00 2.00 0.30 2.40 1.44
MDR2 1.00 1.00 3.65 0.30 2.40 2.63
MP1 1.00 1.00 3.46 0.30 2.40 2.49 280.00 6/1/2021
MP2 1.00 1.00 3.46 0.30 2.40 2.49
MiZ1 1.00 1.00 2.00 0.30 2.40 1.44 280.00 6/1/2021
MiZ2 1.00 1.00 3.05 0.30 2.40 2.20
Cisterna CI
Lado 1 1.00 2.00 5.70 0.25 2.10 5.99 210.00
fecha de
CONCRETO m3 Estruct # Factor Largo Ancho Alto Parcial f´c
vaciado
C1, C2, C3, C4, C5, C6 y C7 7.00 1.00 0.50 0.50 2.40 4.20 280.00
C8 1.00 1.00 0.50 0.50 2.40 0.60 280.00
C9 (Circular) 1.00 1.00 0.64 2.40 1.54 280.00
C10 1.00 1.00 0.55 0.55 2.40 0.73 280.00
C11-C12 2.00 1.00 0.50 0.50 2.40 1.20 280.00
C13-C14 2.00 1.00 0.60 0.60 2.40 1.73 280.00
C15 (Circular) 1.00 1.00 0.64 2.40 1.54 280.00
C16 (Circular) 1.00 1.00 0.64 2.40 1.54 280.00
C17 (Circular) 1.00 1.00 0.64 2.40 1.54 280.00
C18 1.00 1.00 0.60 0.60 2.40 0.86 280.00
C19-C20 2.00 1.00 0.50 0.50 2.40 1.20 280.00
C21, C22, C23, C24 4.00 1.00 0.60 0.60 2.40 3.46 280.00
C25, C26 2.00 1.00 0.60 0.60 2.40 1.73 280.00 6/12/2021
C27 y C28 2.00 1.00 0.60 0.60 2.40 1.73 280.00 6/9/2021
C29 1.00 1.00 0.60 0.60 2.40 0.86
C30 1.00 1.00 0.60 0.60 2.40 0.86
C31 1.00 1.00 0.50 0.50 2.40 0.60
C32 1.00 1.00 0.50 0.50 2.40 0.60
C33, C34, C35, C36, C37, 38, C39, C40 y C41 9.00 1.00 0.50 0.50 2.40 5.40
C42-C43 2.00 1.00 0.50 0.50 2.40 1.20
C44 (Circular) 1.00 1.00 0.16 2.40 0.38 280.00
C45, C46, C47 y C48 4.00 1.00 0.25 0.25 2.40 0.60 280.00
C49-C50 2.00 1.00 0.25 0.25 2.40 0.30 280.00
C51 1.00 1.00 0.25 0.25 2.40 0.15 280.00
C52, C53, C54 y C55 4.00 1.00 0.16 2.40 1.54 280.00
C56 1.00 1.00 0.45 0.90 2.40 0.97 280.00
C57 1.00 1.00 0.45 0.90 2.40 0.97
C58 1.00 1.00 0.45 0.90 2.40 0.97 280.00
C59, C61, C62, C63, C64, C65 y C67 7.00 1.00 0.45 0.90 2.40 6.80
C60 1.00 1.00 0.45 0.90 2.23 0.90 280.00
C66 1.00 1.00 0.45 0.90 2.40 0.97 280.00
C68-C69 2.00 1.00 0.30 0.60 2.23 0.80 280.00
C70-C71 2.00 1.00 0.30 0.60 2.40 0.86 280.00
PL1 1.00 1.00 3.34 3.20 10.69 280.00 6/9/2021
PL2 1.00 1.00 7.32 3.20 23.42 280.00 6/12/2021
PL3 1.00 1.00 4.92 0.30 1.50 2.21 280.00 6/9/2021
PL4 1.00 1.00 4.92 0.30 2.40 3.54 280.00
PL4 1.00 1.00 4.92 0.30 3.20 4.72 280.00
M1 1.00 1.00 31.00 0.30 2.40 22.32
M2 1.00 1.00 3.90 0.30 2.40 2.81
M3 1.00 1.00 4.50 0.30 2.40 3.24
M4 1.00 1.00 8.50 0.30 2.40 6.12
M5 1.00 1.00 3.25 0.30 2.40 2.34
M6 1.00 1.00 4.26 0.30 2.40 3.07
M7 1.00 1.00 4.40 0.30 2.40 3.17
M8 1.00 1.00 8.50 0.30 2.40 6.12
MC1 1.00 1.00 4.22 0.30 2.40 3.04
MC2 1.00 1.00 3.55 0.30 2.40 2.56
MC3 1.00 1.00 3.55 0.30 2.40 2.56
MDR1 1.00 1.00 2.00 0.30 2.40 1.44
MDR2 1.00 1.00 3.65 0.30 2.40 2.63
MP1 1.00 1.00 3.46 0.30 2.40 2.49 280.00
MP2 1.00 1.00 3.46 0.30 2.40 2.49
MiZ1 1.00 1.00 2.00 0.30 2.40 1.44 280.00
MiZ2 1.00 1.00 3.05 0.30 2.40 2.20
Cisterna CI
Lado 1 1.00 2.00 5.70 0.25 2.10 5.99 210.00
Solado 4" 1.00 1.00 2.30 2.3 0.10 0.53 1:12 6/9/2021
Solado 4" 1.00 1.00 8.70 2.1 0.10 1.83 1:12 6/9/2021
Solado 4" 1.00 1.00 2.75 0.4 0.10 0.11 1:12 6/9/2021
C.4.1 1.00 1.00 2.75 0.4 0.40 0.44 280.00 6/12/2021
PROGRAMACIÓN DE CONCRETO SEMANA 10 07/06/2021 AL 13/06/2021
FECHA
DESCRIPCIÓN 6/7/2021 6/8/2021 6/9/2021 6/10/2021 6/11/2021 6/12/2021 6/13/2021 TOTAL
CONCRETO SIMPLE (MANUAL) 1:12 - - 2.47 - - - - 2.47
CONCRETO F'C= 280 KG/CM2 - - 14.63 - - 49.15 - 63.78
CONCRETO F'C= 245 KG/CM2 - - - - - - - 0.00
CONCRETO F'C= 210 KG/CM2 - - - - - - - 0.00
CONCRETO F'C= 175 KG/CM2 - - - - - - - 0.00
TOTAL 0.00 0.00 17.10 0.00 0.00 49.15 0.00 66.25