Description

The following table represents a plan for a project. Work in teams of 2 on the questions in the next slide.
Expected Crash

a
Crash Cost Per

vi
Task Description Predecessor Time Variance Time unit time ($)
(days) (days)

ed
A Pictures ---- 5 0.5 2 100

ar
B Videos ---- 7 1 3 150
C Main page's design ---- 3 0.5 1 120

sh
D Catalog's design ---- 3 0.5 1 210

as
E Ordering system's design ---- 3 0.5 1 220
F Main page's completion A, B, C 3 1 90

w
0.5
G Main page's review F 2 0 1 140

m e
H Catalog and systems' completion A, B, D, E 3 0.5 1 150
I Catalog and systems' review co rc H 2 0 1 230
o. sou
J Registration videos B 19 3 5 50
K Registeration section's design J 5 1 2 80
re

L Social media J 4 1 1 40
200
dy

M Integration G, I, K, L 3 0 2
This study source was downloaded by 100000826241731 from CourseHero.com on 05-28-2021 04:58:52 GMT -05:00
Questions (TOTAL 10 pts)
1 – Construct the appropriate network diagram, and calculate the early start/early finish late
start/late finish for each activity. (3 pts)

2 – Indicate the critical path. (1 pt)

a
vi
ed
3 – How much slack do we have on each of these activities?
What does it mean to have a slack on activity? (1 pt)

ar
sh
4 – What is the expected completion time for the project? (1pt)

as
w
5 – if you would like to shorten the project by 1 day, indicate your plan and cost. Explain. (2 pts)

m e
co rc
6 – What is the possibility that the project will take more than 28 days to complete? (2 pts)
o. sou
re

Type you answers in a word document and submit through Blackboard. NO PDF PLEASE. (PDF will cause you
to loose points). You can hand-draw your network diagram in question 1 only, and include it in your
dy

document as a snapshot.