SECTION-VI COMMISSIONING TESTS
6.1 GENERAL
DRPC Trf options , MV Swgr & cabling, Grounding
& Stn. Service Trf., RTDS, Sec VI modified
The term DRPC mentioned in this PTS refers to both Conventional DRPC and Hybrid
DESCRIPTION
A. A list, giving the details of the commissioning and site tests shall be prepared by the
CONTRACTOR and submitted to COMPANY for review and approval not less than Six
(6) months before the schedule date of tests.
B. The CONTRACTOR shall be responsible for providing all appropriate tools, test
NO.
REVISIONS commissioning and site tests. All tests shall be performed in accordance with the
applicable IEC and ANSI Standards and established practices and procedures and
PREPARED BY: AAA /AMT latest revision of Company standard TCS-P-105.
H. In addition to the tests required in this standard, all tests required by the cable
CERTIFIED
manufacturer shall be performed. In the event of a conflict between the testing
requirements of this standard and those of the cable manufacturer, COMPANY shall
be the sole judge as to which tests shall take precedence.
I. All site testing and commissioning will be done under COMPANY witness. Witnessing
of testing/commissioning by COMPANY does not mean acceptance of test results.
BY: Ahmad M Al-Zahrani Test results will be reviewed and approved by COMPANY separately after
DATE: 06 May 2020
CONTRACTOR submits the same for review and approval.
J. Field tests and commissioning results shall be submitted to COMPANY as per latest
revision of Company standard TCS-P-105.
THIS DOCUMENT IS NOT TO
BE USED FOR K. This section is common for DRPC and Capacitor Bank installations. Testing and
CONSTRUCTION OR FOR
ORDERING MATERIALS commissioning shall be performed for both DRPC & Capacitor Bank installations as
UNTIL CERTIFIED AND
DATED applicable even if not specifically mentioned below.
A
CERT.
الشركة السعودية للكهرباء
AMZ
SAUDI ELECTRICITY COMPANY
CHK’ D APP’ D
new equipment installed under this PROJECT in accordance with applicable sections
of COMPANY Construction Standard TCS-P-105, Commissioning Test and Checks of
& Stn. Service Trf., RTDS, Sec VI modified
The CONTRACTOR shall perform the entire applicable site commissioning test for
High & Low Voltage Cables installed under this PROJECT in accordance with
applicable sections of COMPANY Construction Standards TCS-P-105, “Pre-
Commissioning Tests/procedures for COMPANY Transmission electrical Installations”.
NO.
REVISIONS
All the SF6 Gas Works and High Voltage Testing for the existing GIS related to cable
connection/disconnection for new DRPC projects, circuit modifications etc., shall be
PREPARED BY: AAA /AMT
carried out under the GIS Manufacturer's supervision or by the Manufacturer itself.
A. General
Type test assessment reports for all main equipment shall be provided.
The scope and details of items above shall be submitted to the COMPANY six
weeks after contract award, where after the final scope and details of all testing
shall be agreed with the COMPANY within ten weeks after contract award. In
PTS- 20WM319 Final_R1
SCOPE OF WORK & TECHNICAL SPECIFICATION FOR PLANT NO. INDEX DOCUMENT NO. PAGE NO. REV.
INSTALLATION OF DYNAMIC REACTIVE POWER
COMPENSATION (DRPC) AT TABUK 380kV BSP PTS- 127
JOB ORDER NO.
Of 01
TABUK SAUDI ARABIA SE0437 A 20WM319
133
A
CERT.
الشركة السعودية للكهرباء
AMZ
SAUDI ELECTRICITY COMPANY
CHK’ D APP’ D
addition to the tests called for, the CONTRACTOR shall submit proposals for
AMT
tests to demonstrate the capability of the complete DRPC to meet the required
duty.
DRPC Trf options , MV Swgr & cabling, Grounding
The CONTRACTOR shall supply all necessary labor and test equipment to
& Stn. Service Trf., RTDS, Sec VI modified
perform all tests and inspections that are the CONTRACTOR's responsibility.
DESCRIPTION
B. Testing Responsibilities
DRPC HV bus) shall be done under the supervision of the COMPANY and in
REVISIONS accordance with the COMPANY's safety requirements and operating
regulations. Energized system testing shall be kept to a minimum.
PREPARED BY: AAA /AMT
Tests on completion of erection (after all the plant and material has been
APPROVED
installed and set up on site), shall be carried out by the CONTRACTOR in
Extra High Voltage
accordance with the relevant COMPANY Standards and for the requirements
Engineering & Design Department
listed below. The site acceptance test plan must be reviewed by the COMPANY
FACTS Projects Engineering before any plant and material is installed at the site. The purpose of these tests
Engineering & Design Division
is to:
1. Provide the COMPANY with comparative plant and material data for a
benchmark;
CERTIFIED
2. To verify that no shipping damage has occurred;
3. To verify that the plant and material or system was assembled correctly;
4. To ascertain the plant and material is ready for energised testing.
D. SAT Requirements
BY: Ahmad M Al-Zahrani
All tests that require interfacing to the COMPANY's plant and material shall be
DATE: 06 May 2020 conducted jointly with the COMPANY staff. These tests shall include, but not be
limited to the following:
A
CERT.
الشركة السعودية للكهرباء
AMZ
SAUDI ELECTRICITY COMPANY
CHK’ D APP’ D
7. Protection Functions
& Stn. Service Trf., RTDS, Sec VI modified
DESCRIPTION
The SAT tests shall include, but not be limited to the following:
7. MV Switchgear
CHK’D BY: MLS
8. Indication
13. Capacitors
17. Communication system, including the complete testing of all signals through
the Substation Control System Interface.
THIS DOCUMENT IS NOT TO
BE USED FOR
CONSTRUCTION OR FOR 18. DRPC/Capacitor Bank HV Yard control, protection and indication.
ORDERING MATERIALS
UNTIL CERTIFIED AND
DATED
19. Battery chargers and batteries.
A
CERT.
الشركة السعودية للكهرباء
AMZ
SAUDI ELECTRICITY COMPANY
CHK’ D APP’ D
The test will assure that the overall phase relation of the power circuit,
& Stn. Service Trf., RTDS, Sec VI modified
firing pulse circuit, proper monitoring, and fault annunciation for all
DESCRIPTION
E. Commissioning Tests
supervise the entire site commissioning tests on a full-time basis. The test
REVISIONS engineer shall work in conjunction with the COMPANY's representatives
on site and shall co-operate at all times with these representatives,
PREPARED BY: AAA /AMT particularly in coordinating tests that will involve plant and material
supplied under other contracts. The commissioning tests shall only
commence after all the SAT have been completed successfully and
DATE: 06 May 2020
accepted by the COMPANY.
CHK’D BY: MLS
A
CERT.
الشركة السعودية للكهرباء
AMZ
SAUDI ELECTRICITY COMPANY
CHK’ D APP’ D
REVISIONS
7. Measure the audible sound in the DRPC Building (valve halls, control
PREPARED BY: AAA /AMT room, etc.) and at the boundary of the DRPC/Capacitor Banks area
fence / wall over the range of DRPC/Capacitor Banks operation.
DATE: 06 May 2020 8. Full load test -maximum capacitive output (or as allowed by the Network
CHK’D BY: MLS
Control Centre) for at least 4hours during the day, followed by maximum
continuous inductive output for at least 4hours during the day, until
thermal stability is reached, i.e., power transformer oil temperature rise
less than 3°C over 1 hour.
APPROVED 11. Conduct thermal scans on DRPC and Capacitor equipment supplied
under this contract
Extra High Voltage
Engineering & Design Department
13. Conduct step response test with final DRPC control system parameters
(gain, slope etc.) Small signal «1%) and large signal disturbance (-10%)
shall be performed.
CERTIFIED
14. Conduct testing of the transfer scheme for the auxiliary supply with the
DRPC in service
15. Conduct testing of the transfer between the redundant DRPC controls
systems with the DRPC in service.
BY: Ahmad M Al-Zahrani
A
CERT.
الشركة السعودية للكهرباء
AMZ
SAUDI ELECTRICITY COMPANY
CHK’ D APP’ D
test plan. The CONTRACTOR shall include a minimum of 2 weeks for the
AMT
COMPANY to conduct these tests as part of the total project schedule.
The system, including transmission lines and shunt devices that are
DRPC Trf options , MV Swgr & cabling, Grounding
the performance of these tests, the DRPC and protective plant and
DESCRIPTION
The COMPANY will provide test and recording equipment and personnel
for conducting the tests.
DATE: 06 May 2020 It is not possible due to system constraints to test all facets of the system
function as part of the system commissioning tests specified above. Actual
operating experience will be documented through sequence of events
recorders, oscillographs, digital fault recorders and other system
monitoring equipment capable of identifying system disturbances and
THIS DOCUMENT IS NOT TO
BE USED
CONSTRUCTION OR FOR
FOR associated system performance. Documented failure or malfunction of any
ORDERING
UNTIL
MATERIALS
CERTIFIED AND
system component during the Guarantee Period shall be deemed as a
DATED
failure of the system commissioning or performance acceptance tests and
the CONTRACTOR shall, at no expense to the COMPANY, make the
necessary repairs, replacements, modifications or adjustment to prevent
the same failure or malfunction from occurring again. The replacement of
PTS- 20WM319 Final_R1
SCOPE OF WORK & TECHNICAL SPECIFICATION FOR PLANT NO. INDEX DOCUMENT NO. PAGE NO. REV.
INSTALLATION OF DYNAMIC REACTIVE POWER
COMPENSATION (DRPC) AT TABUK 380kV BSP PTS- 132
JOB ORDER NO.
Of 01
TABUK SAUDI ARABIA SE0437 A 20WM319
133
A
CERT.
الشركة السعودية للكهرباء
AMZ
SAUDI ELECTRICITY COMPANY
CHK’ D APP’ D
Time needed to conduct these tests will not delay acceptance. These tests
could include, but not be limited to:
NO.
REVISIONS 1. Staged fault tests on the supporting racks and Performance tests.