SECTION-VI COMMISSIONING TESTS

6.1 GENERAL
DRPC Trf options , MV Swgr & cabling, Grounding
& Stn. Service Trf., RTDS, Sec VI modified

The term DRPC mentioned in this PTS refers to both Conventional DRPC and Hybrid
DESCRIPTION

DRPC unless otherwise specified.

A. A list, giving the details of the commissioning and site tests shall be prepared by the
CONTRACTOR and submitted to COMPANY for review and approval not less than Six
(6) months before the schedule date of tests.

B. The CONTRACTOR shall be responsible for providing all appropriate tools, test
NO.

equipment and temporary AC and DC power supplies needed to perform the


3

REVISIONS commissioning and site tests. All tests shall be performed in accordance with the
applicable IEC and ANSI Standards and established practices and procedures and
PREPARED BY: AAA /AMT latest revision of Company standard TCS-P-105.

C. The CONTRACTOR shall furnish a schedule of proposed commissioning tests at least


DATE: 06 May 2020 Four (4) months prior to scheduled date of tests with a list of test and commissioning
CHK’D BY: MLS
equipment to be used for the PROJECT. The list shall indicate whether each
equipment is owned or to be rented.

D. The CONTRACTOR shall be responsible for conducting additional tests if


recommended by the equipment manufacturers or by COMPANY.

E. The CONTRACTOR shall be responsible for commissioning the existing protection


scheme involved with the scope of the subject PROJECT.
APPROVED
F. Testing of medium voltage cable system shall be carried out to ensure that the
necessary design and operation specifications are achieved prior to placing the cable
Extra High Voltage
Engineering & Design Department system into service.
FACTS Projects Engineering
Engineering & Design Division
G. The CONTRACTOR shall be responsible to carry out all tests in a safe manner and
with pre-determined safe working procedure submitted to COMPANY.

H. In addition to the tests required in this standard, all tests required by the cable
CERTIFIED
manufacturer shall be performed. In the event of a conflict between the testing
requirements of this standard and those of the cable manufacturer, COMPANY shall
be the sole judge as to which tests shall take precedence.

I. All site testing and commissioning will be done under COMPANY witness. Witnessing
of testing/commissioning by COMPANY does not mean acceptance of test results.
BY: Ahmad M Al-Zahrani Test results will be reviewed and approved by COMPANY separately after
DATE: 06 May 2020
CONTRACTOR submits the same for review and approval.

J. Field tests and commissioning results shall be submitted to COMPANY as per latest
revision of Company standard TCS-P-105.
THIS DOCUMENT IS NOT TO
BE USED FOR K. This section is common for DRPC and Capacitor Bank installations. Testing and
CONSTRUCTION OR FOR
ORDERING MATERIALS commissioning shall be performed for both DRPC & Capacitor Bank installations as
UNTIL CERTIFIED AND
DATED applicable even if not specifically mentioned below.

PTS- 20WM319 Final_R1


SCOPE OF WORK & TECHNICAL SPECIFICATION FOR PLANT NO. INDEX DOCUMENT NO. PAGE NO. REV.
INSTALLATION OF DYNAMIC REACTIVE POWER
COMPENSATION (DRPC) AT TABUK 380kV BSP PTS- 126
JOB ORDER NO.
Of 01
TABUK SAUDI ARABIA SE0437 A 20WM319
133

A
CERT.
‫الشركة السعودية للكهرباء‬

AMZ
SAUDI ELECTRICITY COMPANY
CHK’ D APP’ D

6.2 DRPC STATION EQUIPMENT


AMT
The CONTRACTOR shall perform all the applicable site commissioning tests of the
DRPC Trf options , MV Swgr & cabling, Grounding

new equipment installed under this PROJECT in accordance with applicable sections
of COMPANY Construction Standard TCS-P-105, Commissioning Test and Checks of
& Stn. Service Trf., RTDS, Sec VI modified

Power Transmission Network Equipment".6.3


DESCRIPTION

6.3 TESTING OF HIGH & LOW VOLTAGE CABLES

The CONTRACTOR shall perform the entire applicable site commissioning test for
High & Low Voltage Cables installed under this PROJECT in accordance with
applicable sections of COMPANY Construction Standards TCS-P-105, “Pre-
Commissioning Tests/procedures for COMPANY Transmission electrical Installations”.
NO.

REVISIONS
All the SF6 Gas Works and High Voltage Testing for the existing GIS related to cable
connection/disconnection for new DRPC projects, circuit modifications etc., shall be
PREPARED BY: AAA /AMT
carried out under the GIS Manufacturer's supervision or by the Manufacturer itself.

DATE: 06 May 2020


6.4 SPECIFIC TESTING & COMMISSIONING REQUIREMENTS FOR DRPC
CHK’D BY: MLS
INSTALLATIONS

Dynamic Reactive Power Compensation Installation

A. General

Inspection and test requirements consist of design verification, testing at works


(type and routine tests), site acceptance tests (SAT) for main components and
sub-systems, commissioning tests, performance verification and acceptance
APPROVED
tests, as well as extended performance acceptance tests, according to the
Extra High Voltage
relevant IEC and IEEE standards. The IEEE STD 1303, IEEE Guide for Static
Engineering & Design Department
VAR Compensator Field Tests, shall be followed in the testing of the complete
FACTS Projects Engineering DRPC system.
Engineering & Design Division

Type test assessment reports for all main equipment shall be provided.

General procedures consist of the development and submission of Test Plans to


CERTIFIED
the COMPANY for review and comments, successful completion of the tests by
the CONTRACTOR (witnessed by the COMPANY), and the submission of test
reports by performing each test, in accordance with the requirements of this
specification and the General Conditions of Contract.

General procedures involve the provision of:


BY: Ahmad M Al-Zahrani

DATE: 06 May 2020


1 Site Acceptance Test Plan,

2 Commissioning Test Plan,

3 Performance Acceptance Test Plan,


THIS DOCUMENT IS NOT TO
BE USED FOR
CONSTRUCTION OR FOR
ORDERING MATERIALS 4 Extended Performance Acceptance Test Plan.
UNTIL CERTIFIED AND
DATED

The scope and details of items above shall be submitted to the COMPANY six
weeks after contract award, where after the final scope and details of all testing
shall be agreed with the COMPANY within ten weeks after contract award. In
PTS- 20WM319 Final_R1
SCOPE OF WORK & TECHNICAL SPECIFICATION FOR PLANT NO. INDEX DOCUMENT NO. PAGE NO. REV.
INSTALLATION OF DYNAMIC REACTIVE POWER
COMPENSATION (DRPC) AT TABUK 380kV BSP PTS- 127
JOB ORDER NO.
Of 01
TABUK SAUDI ARABIA SE0437 A 20WM319
133

A
CERT.
‫الشركة السعودية للكهرباء‬

AMZ
SAUDI ELECTRICITY COMPANY
CHK’ D APP’ D

addition to the tests called for, the CONTRACTOR shall submit proposals for
AMT
tests to demonstrate the capability of the complete DRPC to meet the required
duty.
DRPC Trf options , MV Swgr & cabling, Grounding

The CONTRACTOR shall supply all necessary labor and test equipment to
& Stn. Service Trf., RTDS, Sec VI modified

perform all tests and inspections that are the CONTRACTOR's responsibility.
DESCRIPTION

B. Testing Responsibilities

The CONTRACTOR shall perform all testing including the performance


verification, acceptance tests and the extended performance acceptance tests,
which will be conducted by the COMPANY. All tests that require connection of
the DRPC/Capacitor Banks to the COMPANY's main transmission system (e.g.
NO.

DRPC HV bus) shall be done under the supervision of the COMPANY and in
REVISIONS accordance with the COMPANY's safety requirements and operating
regulations. Energized system testing shall be kept to a minimum.
PREPARED BY: AAA /AMT

The CONTRACTOR shall provide energisation procedures as part of the


Commissioning Test Plan.
DATE: 06 May 2020

CHK’D BY: MLS


The tests shall be performed in a fashion to minimize unanticipated disturbances
on the power system. These tests may have to be performed during the low load
periods. Low load periods are defined as nights, weekends and vacation and
winter seasons as may be deemed appropriate by the COMPANY. Such tests by
the CONTRACTOR shall not be considered to be commissioning tests.

C. Site Acceptance Tests (SAT)

Tests on completion of erection (after all the plant and material has been
APPROVED
installed and set up on site), shall be carried out by the CONTRACTOR in
Extra High Voltage
accordance with the relevant COMPANY Standards and for the requirements
Engineering & Design Department
listed below. The site acceptance test plan must be reviewed by the COMPANY
FACTS Projects Engineering before any plant and material is installed at the site. The purpose of these tests
Engineering & Design Division
is to:

1. Provide the COMPANY with comparative plant and material data for a
benchmark;
CERTIFIED
2. To verify that no shipping damage has occurred;
3. To verify that the plant and material or system was assembled correctly;
4. To ascertain the plant and material is ready for energised testing.
D. SAT Requirements
BY: Ahmad M Al-Zahrani
All tests that require interfacing to the COMPANY's plant and material shall be
DATE: 06 May 2020 conducted jointly with the COMPANY staff. These tests shall include, but not be
limited to the following:

1. SAS, SCADA & HMI


THIS DOCUMENT IS NOT TO
BE USED
CONSTRUCTION OR FOR
FOR 2. DRPC HV Yard interlocking
ORDERING MATERIALS
UNTIL CERTIFIED AND
DATED
3. DRPC HV yard interfacing

4. Substation Auxiliary system

PTS- 20WM319 Final_R1


SCOPE OF WORK & TECHNICAL SPECIFICATION FOR PLANT NO. INDEX DOCUMENT NO. PAGE NO. REV.
INSTALLATION OF DYNAMIC REACTIVE POWER
COMPENSATION (DRPC) AT TABUK 380kV BSP PTS- 128
JOB ORDER NO.
Of 01
TABUK SAUDI ARABIA SE0437 A 20WM319
133

A
CERT.
‫الشركة السعودية للكهرباء‬

AMZ
SAUDI ELECTRICITY COMPANY
CHK’ D APP’ D

5. Remote control and indication


AMT
6. 132kV GIS/AIS Switchgear
DRPC Trf options , MV Swgr & cabling, Grounding

7. Protection Functions
& Stn. Service Trf., RTDS, Sec VI modified
DESCRIPTION

The SAT tests shall include, but not be limited to the following:

1. Cable and Cable Termination Inspection and Testing

2. Busbars and Busbar Clamps Inspection and Testing

3. DRPC Transformers and Reactors


NO.

REVISIONS 4. Current Transformers

PREPARED BY: AAA /AMT


5. Voltage Transformers

6. 132kV GIS/AIS Switchgear


DATE: 06 May 2020

7. MV Switchgear
CHK’D BY: MLS

8. Indication

Functional and calibrated verification checks of all alarms, flow rate


monitors, liquid level switches, temperature indicators, conductivity meters,
density monitors, pressure switches, and associated settings. All points shall
be checked from their point of origin, actual or simulated operation of each
device due to mechanical action, pressure, temperature, conductivity, and
APPROVED operating positions.
Extra High Voltage
Engineering & Design Department 9. Identification and Nameplates
FACTS Projects Engineering
Engineering & Design Division 10. Verification of accuracy of nameplate information and application.

11. Fibre Optic Connectors and Cables

CERTIFIED 12. DRPC MV Busbar capacitance measurements

13. Capacitors

14. Control and Protection

BY: Ahmad M Al-Zahrani


15. Auxiliary Systems
DATE: 06 May 2020
16. Cooling System

17. Communication system, including the complete testing of all signals through
the Substation Control System Interface.
THIS DOCUMENT IS NOT TO
BE USED FOR
CONSTRUCTION OR FOR 18. DRPC/Capacitor Bank HV Yard control, protection and indication.
ORDERING MATERIALS
UNTIL CERTIFIED AND
DATED
19. Battery chargers and batteries.

20. Disturbance Recorder, Power Quality Monitor (VQR) and DSM.


PTS- 20WM319 Final_R1
SCOPE OF WORK & TECHNICAL SPECIFICATION FOR PLANT NO. INDEX DOCUMENT NO. PAGE NO. REV.
INSTALLATION OF DYNAMIC REACTIVE POWER
COMPENSATION (DRPC) AT TABUK 380kV BSP PTS- 129
JOB ORDER NO.
Of 01
TABUK SAUDI ARABIA SE0437 A 20WM319
133

A
CERT.
‫الشركة السعودية للكهرباء‬

AMZ
SAUDI ELECTRICITY COMPANY
CHK’ D APP’ D

21. Low voltage energisation test


AMT
The CONTRACTOR shall perform low voltage energisation test to check
the entire DRPC/Capacitor Bank system prior to full voltage energisation.
DRPC Trf options , MV Swgr & cabling, Grounding

The test will assure that the overall phase relation of the power circuit,
& Stn. Service Trf., RTDS, Sec VI modified

firing pulse circuit, proper monitoring, and fault annunciation for all
DESCRIPTION

thyristors and thyristor electronic circuits is correct. Wave shape of


currents and voltages shall be checked during the test.

E. Commissioning Tests

The CONTRACTOR shall provide experienced prequalified test personnel


as well as an experienced and competent test engineer to undertake and
NO.

supervise the entire site commissioning tests on a full-time basis. The test
REVISIONS engineer shall work in conjunction with the COMPANY's representatives
on site and shall co-operate at all times with these representatives,
PREPARED BY: AAA /AMT particularly in coordinating tests that will involve plant and material
supplied under other contracts. The commissioning tests shall only
commence after all the SAT have been completed successfully and
DATE: 06 May 2020
accepted by the COMPANY.
CHK’D BY: MLS

The COMPANY reserves the right to act interactively with the


CONTRACTOR during the testing and the commissioning period.

The CONTRACTOR's test engineer shall be available in Saudi Arabia for a


period of at least 4 weeks after the completion of the contract works so as
to assist the COMPANY's site representatives in carrying out complete
operational checks of the overall substation control, protection and tele
control plant and material including the DRPC/Capacitor Banks. The cost
APPROVED
of the CONTRACTOR's test engineer remaining on site for this period and
Extra High Voltage
assisting the COMPANY's site representatives shall be included in the
Engineering & Design Department
contract price.
FACTS Projects Engineering
Engineering & Design Division
Commissioning Tests include all tests that require connection of the
DRPC/Capacitor Banks to the COMPANY's main transmission system.
Final energisation authority and outage co-ordination will be the
responsibility of the COMPANY. The CONTRACTOR shall submit a
CERTIFIED
request for an outage at least 14 days prior to any energised testing.
These tests are under the jurisdiction of the COMPANY's Grid Network
Control Centre and may be delayed or discontinued if required by system
conditions. All operational tests shall receive verification by the COMPANY
that the tests have been performed and the results were acceptable. The
commissioning program shall last at least 3 weeks unless agreed by the
BY: Ahmad M Al-Zahrani
COMPANY. Final energisation shall only commence after all the pre-
DATE: 06 May 2020 energisation tests have been completed and accepted by the COMPANY

If the DRPC/Capacitor Banks should fail any test and/or modifications or


changes are made, the COMPANY may elect to restart the commissioning
THIS DOCUMENT IS NOT TO
tests or request the CONTRACTOR to repeat any test without
BE USED
CONSTRUCTION OR FOR
FOR
compensation to the CONTRACTOR.
ORDERING MATERIALS
UNTIL CERTIFIED AND
DATED
As a minimum, the following shall be included as commissioning tests:

PTS- 20WM319 Final_R1


SCOPE OF WORK & TECHNICAL SPECIFICATION FOR PLANT NO. INDEX DOCUMENT NO. PAGE NO. REV.
INSTALLATION OF DYNAMIC REACTIVE POWER
COMPENSATION (DRPC) AT TABUK 380kV BSP PTS- 130
JOB ORDER NO.
Of 01
TABUK SAUDI ARABIA SE0437 A 20WM319
133

A
CERT.
‫الشركة السعودية للكهرباء‬

AMZ
SAUDI ELECTRICITY COMPANY
CHK’ D APP’ D

1. Verify the DRPC/Capacitor banks operation at nominal voltage, current,


AMT
power and frequency.

2. Verify the automatic shutdown sequences and the manual shutdown


DRPC Trf options , MV Swgr & cabling, Grounding
& Stn. Service Trf., RTDS, Sec VI modified

3. Verify DRPC/Capacitor Banks performance during simulated equipment


DESCRIPTION

failures and degraded modes.

4. Verify the automatic sequences of blocking and unblocking the valves

5. Verify the performance of the DRPC/Capacitor Banks with normal


system conditions and with acceptable line and transformer outages.
NO.

6. Measure the harmonic distortion performance indicators.


3

REVISIONS
7. Measure the audible sound in the DRPC Building (valve halls, control
PREPARED BY: AAA /AMT room, etc.) and at the boundary of the DRPC/Capacitor Banks area
fence / wall over the range of DRPC/Capacitor Banks operation.

DATE: 06 May 2020 8. Full load test -maximum capacitive output (or as allowed by the Network
CHK’D BY: MLS
Control Centre) for at least 4hours during the day, followed by maximum
continuous inductive output for at least 4hours during the day, until
thermal stability is reached, i.e., power transformer oil temperature rise
less than 3°C over 1 hour.

9. Measure the current unbalance in individual phases.

10. Measure the protection control functions e.g. current limitation.

APPROVED 11. Conduct thermal scans on DRPC and Capacitor equipment supplied
under this contract
Extra High Voltage
Engineering & Design Department

FACTS Projects Engineering


12. Other control functions as specified.
Engineering & Design Division

13. Conduct step response test with final DRPC control system parameters
(gain, slope etc.) Small signal «1%) and large signal disturbance (-10%)
shall be performed.
CERTIFIED

14. Conduct testing of the transfer scheme for the auxiliary supply with the
DRPC in service

15. Conduct testing of the transfer between the redundant DRPC controls
systems with the DRPC in service.
BY: Ahmad M Al-Zahrani

16. Measure the circulating currents induced by TCR/TSR.


DATE: 06 May 2020

Detailed test procedures shall be provided for each of the test to be


performed. The procedures shall be submitted to COMPANY for approval.
No testing shall be performed until the test procedures are approved.
THIS DOCUMENT IS NOT TO
BE USED FOR
CONSTRUCTION OR FOR
ORDERING MATERIALS
F. Performance Acceptance Tests (System Commissioning Tests):
UNTIL CERTIFIED AND
DATED

After successful completion of all of the SAT and Commissioning Tests,


the performance verification and acceptance tests shall be conducted in
accordance with the COMPANY developed and CONTRACTOR reviewed
PTS- 20WM319 Final_R1
SCOPE OF WORK & TECHNICAL SPECIFICATION FOR PLANT NO. INDEX DOCUMENT NO. PAGE NO. REV.
INSTALLATION OF DYNAMIC REACTIVE POWER
COMPENSATION (DRPC) AT TABUK 380kV BSP PTS- 131
JOB ORDER NO.
Of 01
TABUK SAUDI ARABIA SE0437 A 20WM319
133

A
CERT.
‫الشركة السعودية للكهرباء‬

AMZ
SAUDI ELECTRICITY COMPANY
CHK’ D APP’ D

test plan. The CONTRACTOR shall include a minimum of 2 weeks for the
AMT
COMPANY to conduct these tests as part of the total project schedule.

The system, including transmission lines and shunt devices that are
DRPC Trf options , MV Swgr & cabling, Grounding

available, will be configured to produce the most severe test condition. In


& Stn. Service Trf., RTDS, Sec VI modified

the performance of these tests, the DRPC and protective plant and
DESCRIPTION

material shall be required to function in accordance with the requirements


detailed in these specifications.

The COMPANY will provide test and recording equipment and personnel
for conducting the tests.

The CONTRACTOR will be notified of the type and time that a


NO.

performance acceptance test is to be performed by the COMPANY. The


REVISIONS CONTRACTOR shall have a representative present to act as a technical
advisor should test or plant and material problems be encountered. These
PREPARED BY: AAA /AMT tests are under the jurisdiction of the COMPANY's Grid Network Control
Centre and may be delayed or discontinued if required by system
conditions. This test program which will be developed by the COMPANY
DATE: 06 May 2020
will include but is not limited to the following:
CHK’D BY: MLS

1. Staged fault tests on the medium voltage bus, if allowed by the


COMPANY Network Control Centre

2. Staged fault tests on the DRPC HV bus, if allowed by the COMPANY


Network Control Centre

3. Staged fault tests on the filters, power semiconductors, reactors,


capacitor, or any other location where a fault could occur, if allowed by
APPROVED
the COMPANY Network Control Centre
Extra High Voltage
Engineering & Design Department
4. Tests of control system malfunctions and recovery
FACTS Projects Engineering
Engineering & Design Division
If plant and material supplied or systems designed and/or specified
furnished by the CONTRACTOR fails during the performance
verification testing, it shall be repaired and defective parts replaced or
redesigned and replaced without any compensation to the
CERTIFIED
CONTRACTOR. However, after determination of a major failure and
failure review, it may be necessary to perform additional commissioning
and performance verification and acceptance tests to verify that the
design meets the intended application.

G. Extended Performance Acceptance Tests


BY: Ahmad M Al-Zahrani

DATE: 06 May 2020 It is not possible due to system constraints to test all facets of the system
function as part of the system commissioning tests specified above. Actual
operating experience will be documented through sequence of events
recorders, oscillographs, digital fault recorders and other system
monitoring equipment capable of identifying system disturbances and
THIS DOCUMENT IS NOT TO
BE USED
CONSTRUCTION OR FOR
FOR associated system performance. Documented failure or malfunction of any
ORDERING
UNTIL
MATERIALS
CERTIFIED AND
system component during the Guarantee Period shall be deemed as a
DATED
failure of the system commissioning or performance acceptance tests and
the CONTRACTOR shall, at no expense to the COMPANY, make the
necessary repairs, replacements, modifications or adjustment to prevent
the same failure or malfunction from occurring again. The replacement of
PTS- 20WM319 Final_R1
SCOPE OF WORK & TECHNICAL SPECIFICATION FOR PLANT NO. INDEX DOCUMENT NO. PAGE NO. REV.
INSTALLATION OF DYNAMIC REACTIVE POWER
COMPENSATION (DRPC) AT TABUK 380kV BSP PTS- 132
JOB ORDER NO.
Of 01
TABUK SAUDI ARABIA SE0437 A 20WM319
133

A
CERT.
‫الشركة السعودية للكهرباء‬

AMZ
SAUDI ELECTRICITY COMPANY
CHK’ D APP’ D

certain system components, in response to a system failure, may


AMT
necessitate, at the discretion of the COMPANY, the duplication of certain
system commissioning tests, which shall be performed at the
CONTRACTOR's expense.
DRPC Trf options , MV Swgr & cabling, Grounding
& Stn. Service Trf., RTDS, Sec VI modified

If system conditions prevent completion of the performance acceptance


DESCRIPTION

tests following the commissioning and functional tests, the COMPANY


may choose to perform additional performance acceptance tests during
commissioning or at any time during the 12 month period following
completion.

Time needed to conduct these tests will not delay acceptance. These tests
could include, but not be limited to:
NO.

REVISIONS 1. Staged fault tests on the supporting racks and Performance tests.

PREPARED BY: AAA /AMT

DATE: 06 May 2020

CHK’D BY: MLS


**** END OF SECTION VI ****

****END OF SOW/TS ****

APPROVED

Extra High Voltage


Engineering & Design Department

FACTS Projects Engineering


Engineering & Design Division

CERTIFIED

BY: Ahmad M Al-Zahrani

DATE: 06 May 2020

THIS DOCUMENT IS NOT TO


BE USED FOR
CONSTRUCTION OR FOR
ORDERING MATERIALS
UNTIL CERTIFIED AND
DATED

PTS- 20WM319 Final_R1


SCOPE OF WORK & TECHNICAL SPECIFICATION FOR PLANT NO. INDEX DOCUMENT NO. PAGE NO. REV.
INSTALLATION OF DYNAMIC REACTIVE POWER
COMPENSATION (DRPC) AT TABUK 380kV BSP PTS- 133
JOB ORDER NO.
Of 01
TABUK SAUDI ARABIA SE0437 A 20WM319
133