October 2020 Proposed 2-Storey Residence

Bill of Materials

BILL OF MATERIALS

CONSTRUCTION OF 2 STOREY RESIDENCE


Block 1 Lot 3, Purok Phase V-A, Brgy. Dela Paz, Antipolo City

MR. JOMEL A. BRIOSO


OWNER

PREPARED BY:

AR. JAN EMILYN C. CATINDIG


PRC NO. : 0036829
VALIDITY : December 14, 2022
PTR NO. : 11952118
ISSUED ON : February 02, 2020
ISSUED AT : Las Pinas
TIN NO. : 494-742-591-000

1|Page
October 2020 Proposed 2-Storey Residence
Bill of Materials

BILL OF MATERIALS

A GENERAL REQUIREMENTS

1.0 Mobilization and Demobilization


2.0 Temporary facilities (barracks/storage/fencing)
3.0 Temporary Water and Electricity
Construction supervision/warehouse control
4.0
(foreman/bodegero/labor)
5.0 Site clearing works/grubbing
6.0 Layout
7.0 Hauling
8.0 Building and Occupancy Permits
Sub-total A: GENERAL
REQUIREMENTS 170,000.00

B STRUCTURAL WORKS

1.0 Earthworks
Wall Footing (formworks, rebar installation and
2.0
concreting)
Column Footing (formworks, rebar installation and
3.0
concreting)
Columns (formworks, rebar installation and
5.0
concreting)
Ground Floor Slab (formworks, rebar installation and
8.0
concreting)
Second Floor Slab (formworks, rebar installation and
9.0
concreting)
Ground Floor Beams (formworks, rebar installation
11.0
and concreting)
Second Floor Beams (formworks, rebar installation
12.0
and concreting)
Roof Beams (formworks, rebar installation and
13.0
concreting)
14.0 Stair (formworks, rebar installation and concreting)
Sub-total B: STRUCTURAL WORKS
570,000.00

C MASONRY WORKS

1.0 6" CHB wall including plastering


2.0 4" CHB wall including plastering
3.0 Rebars for CHB wall
Rebars for Lintel Beam (10mm x 6m Reinforcement
4.0
Bar)

2|Page
October 2020 Proposed 2-Storey Residence
Bill of Materials

Sub-total C: MASONRY WORKS


200,000.00

D FLOOR AND WALL FINISHES

1.0 Floor Tiles


86,400.00
2.0 Wall Tiles
25,000.00

Sub-total D: FLOOR AND WALL FINISHES


111,400.00

E CEILING FINISHES

4.5mm Fiber-cement board on metal frames for


1.0
CARPORT 19,200.00
12mm thk. gypsum board on metal framing for all
2.0
interior ceiling (except T&B's) 40,080.00
12mm thk. MR gypsum board on metal framing for
3.0
T&B and Powder rm. 3,575.00

Sub-total E: CEILING FINISHES


62,855.00

F MISCELLANEOUS WORKS

1.0 Granite Lavatory Countertop


10,000.00
Waterproofing 12,000.00
Supply and application of cementitious type
2.0
waterproofing at common
T&B and Balcony
3.0 Glass Railing 50,000.00
Sub-total F: MISCELLANEOUS WORKS
72,000.00

G CARPENTRY WORKS

1.0 Kitchen counter and overhead cabinets 20,000


2.0 Bedrooms Closet 30,000
3.0 Tangile Steps (Stairs) , 1"x10" planks 45,000.00
4.0 Stair Handrail (Stairs) 8800
Sub-total G: CARPENTRY WORKS
103,800.00

3|Page
October 2020 Proposed 2-Storey Residence
Bill of Materials

H DOORS AND WINDOWS


1.0 Doors
64,000.00
2.0 Windows
80,000.00
Sub-total H: DOORS AND WINDOWS
144,000.00

I PAINTING WORKS
1.0 Exterior
64,000.00
2.0 Interior
80,000.00
3.0 Ceiling 28350
Sub-total I: PAINTING WORKS
172,350.00

J PLUMBING
1.0 Plumbing Fixtures 25,000.00
2.0 Plumbing Works 70,000.00
Sub-total J: PLUMBING
95,000.00

K ELECTRICAL WORKS
Electrical Pipes and others, Wiring and Fixture
1.0
Materials

Sub-total K: ELECTRICAL WORKS


132,000.00

TOTAL PROJECT CONSTRUCTION COST 1,833,405.00