Download as pdf or txt
Download as pdf or txt
You are on page 1of 15

ESSO EXPLORATION &

PRODUCTION CHAD INC. ECS 1-1-2


EQUIPMENT, INSTRUMENTATION
Page 1 of 14
AND LINE DESIGNATION

SPECIFICATION Rev. 4 May 2010

Prepared By Reviewed By Approved By


Rev. Date
No. Discipline Engineering Project
Engineer Manager Engineer / Manager
1 DEC 1995 BM SB MM
2 OCT 2000 WPM MRG CAE/MAJ
3 FEB 2009 Carl Stienbarger Matt Vines David J. Slagle
4 May 2010 Carl Stienbarger Pier Mane David J. Slagle

Revision 4 Memo

Dec 1995 Original Issue

FEB 2009 Revised 3.4b Added Area Number 61, 62 & 64, and revised 3.5 - Added T for Timbre
Revised Table 2 – to align Manifold designations with currently installed units.
May 2010 Revise Table two to add additional manifolds

H:\Data\UD Downloads\ECS 1-1-2 Rev 4.doc


ESSO EXPLORATION &
PRODUCTION CHAD INC. ECS 1-1-2
EQUIPMENT, INSTRUMENTATION
Page 1 of 14
AND LINE DESIGNATION

SPECIFICATION Rev. 4 May 2010

TABLE OF CONTENTS

SCOPE ................................................................................................................................... 2

SUMMARY OF ADDITIONAL REQUIREMENTS .................................................................2

INSTRUMENT DESIGNATIONS ............................................................................................ 2

PROCESS EQUIPMENT DESIGNATION .............................................................................. 4

PIPING LINE IDENTIFICATION ............................................................................................8

PIPELINE IDENTIFICATION .................................................................................................10

LINE LISTS ............................................................................................................................11

ELECTRICAL EQUIPMENT DESIGNATION ........................................................................11

LIST OF TABLES AND FIGURES

TABLE 1 .................................................................................................................................2

TABLE 2 .................................................................................................................................5

TABLE 3 .................................................................................................................................7

TABLE 4 .................................................................................................................................13

FIGURE 1 ...............................................................................................................................14

H:\Data\UD Downloads\ECS 1-1-2 Rev 4.doc


ESSO EXPLORATION &
PRODUCTION CHAD INC. ECS 1-1-2
EQUIPMENT, INSTRUMENTATION
Page 2 of 14
AND LINE DESIGNATION

SPECIFICATION Rev. 4 May 2010

SCOPE

1.1 This document contains mandatory requirements governing equipment, piping,


pipelines, and instrument designations (letter, numbers and symbols) to be used on
drawings and other project documents for the Chad Doba Development Project.

1.2 An asterisk (*) indicates that additional information is provided by ESSO in an addendum
to this specification.

1.3 A pound sign (#) indicates that ESSO review/approval is required before design is
finalized or equipment is purchased.

SUMMARY OF ADDITIONAL REQUIREMENTS

2.1 Table 1 lists the codes, standards and specifications which shall be used with this
specification.

2.2 The equipment and materials used shall conform to the latest editions, revisions and
addenda of the codes, standards and regulations listed in Table 1.

TABLE 1

ESSO Chad Specifications


ECS 1-1-1 Document Numbering
ECS 1-1-3 Drawing Standards
ECS 3-30-0 Standard Piping Classes - Table of Contents
ANSI/ASME Codes and Standards
B31.1 Power Piping
B31.3 Chemical Plant and Petroleum Refinery Piping
B31.4 Liquid Transportation System for Hydrocarbons, Liquid
Petroleum Gas, Anhydrous Ammonia and Alcohols
B31.8 Gas Transmission and Distribution Piping Systems
ISA Standard
S5.1 Instrumentation Symbols and Identification

2.3 Any designation used which is not specified or otherwise covered in this specification,
shall be explained on the drawings.

INSTRUMENT DESIGNATIONS

3.1 Each instrument measurement or control loop shall be identified by an alphanumeric


code or tag number.

H:\Data\UD Downloads\ECS 1-1-2 Rev 4.doc


ESSO EXPLORATION &
PRODUCTION CHAD INC. ECS 1-1-2
EQUIPMENT, INSTRUMENTATION
Page 3 of 14
AND LINE DESIGNATION

SPECIFICATION Rev. 4 May 2010

3.2 The instrument designations shall follow ISA Standards S5.1 with specific options
adopted by ESSO.

3.3 The Instrument Tag Numbering System shall be based on a full serial loop numbering
system.

3.4 The instrument tag number for all facilities, except well sites, shall have the format:
AA-XXXXX-0000 S
which is defined as follows:
AA Area Number
10 Bolobo Gathering Station
20 Miandoum Gathering Station
30 Kome Gathering station
35 Kome Pump Stations
KP-1 = 35 XXXXX 1000S
KP-2 = 35 XXXXX 2000S
40 Central Treating Facility
50 Power Plant General and Utilities
51 Power Plant Gas Turbine Generators
52 Power Plant Diesel Generators
55 Power Transmission System
61 Moundouli Field
62 NYA Site
63 Poutouguem (Maikeri) Field
64 Timbre Field
70 Chad Field Loading
71 Pump Station # 1
85 CTF Utilities

XXXXX ISA Type Letter Description for Instruments up to 5 characters. i.e.,


PAHH, LC, TB, etc.

Note: These letters should be limited to two characters on any tag that
will be on a controller face plate. Refer to P&ID Standard Legend
Drawing No. 7400-G000-50D2-0003 (see ECS 1-1-3).

0000 Four digit Loop Number

S Alpha Character Suffix, used to separate different instruments that are


part of the same loop.

Example: A high high pressure differential switch at the Bolobo


Gathering Station would be numbered 10 PDSHH 1000.

3.5 The instrument tag numbers for well sites shall have the format:

AWWW-XXXXX-00-S
H:\Data\UD Downloads\ECS 1-1-2 Rev 4.doc
ESSO EXPLORATION &
PRODUCTION CHAD INC. ECS 1-1-2
EQUIPMENT, INSTRUMENTATION
Page 4 of 14
AND LINE DESIGNATION

SPECIFICATION Rev. 4 May 2010

which is defined as follows:

A 1 character describing the location of the facilities as follows:

G General (Total Area)


K Kome Field
M Miandoum Field
B Bolobo Field
C Operations Center
D Moundouli
N Nya
P Poutouguem (Maikeri)
T Timbre Field

WWW Well Number

XXXXX ISA Type Letter description for Instruments up to 5 characters

00 Two Digit Loop Number

S Alpha Character suffix, used to separate different instruments that are


part of the same loop.

Example: A high high pressure switch at Kome Well 101 would be numbered
K101-PSHH-01.

3.6 Tag numbers that appear on a DCS face plate shall be limited to eight characters.

3.7 All other tag numbers shall be limited to twelve characters without exception.

3.8 All instruments within a loop shall have the same instrument loop number and the same
first letter of the ISA type.

3.9 General instrument symbols, function symbols, or function block designations shall be
shown as indicated on Standard Legend - Instrument Designations and Symbols for
P&ID's Drawing No. 7400-G000-50D2-0003 (see ECS 1-1-3). ISA Standards shall be
followed for less commonly used symbols.

PROCESS EQUIPMENT DESIGNATION

4.1 Equipment designations shall consist of symbols, letters and numbers as follows:

a. Equipment symbols per Standard Legend - Equipment Symbols, Drawing No.


7400-G000-50D2-0002 (see ECS 1-1-3).

b. Process equipment shall be numbered using the format:

WABBB-CCC-DDD E

which is defined as follows:


H:\Data\UD Downloads\ECS 1-1-2 Rev 4.doc
ESSO EXPLORATION &
PRODUCTION CHAD INC. ECS 1-1-2
EQUIPMENT, INSTRUMENTATION
Page 5 of 14
AND LINE DESIGNATION

SPECIFICATION Rev. 4 May 2010

W Letter W, only used when designating wellsite equipment

A 1 character describing the location of the facilities as follows:

G General (Total Area)


K Kome Field
M Miandoum Field
B Bolobo Field
C Operations Center
D Moundouli
N Nya
P Poutouguem (Maikeri)
T Timbre Field

BBB 3 characters describing the type of facilities as follows:

000 General
100 Wellsites
150-199 Well Manifold & Testing Facilities
200 Infield Pipelines
250 Trunklines
300 Gathering Stations
330 Kome Produced Wwater Beneficial Reuse
350 Bolobo Pump Station BP-1
351 Kome Pump Station KP-1
352 Kome Pump Station KP-2
400 Central Treating Facilities
500 Power Generation
550 Power Distribution/Transmission
575 Crude Oil Topping Plant
600 Electrical Substations
650 Control Stations/Rooms
700 Housing/Community
750 Airfield
800 Roads
850 Utilities/Support Facilities
900 Communications Facilities
950 Temporary Facilities

Notes:

1. For each wellsite, the well number shall be used for BBB
2. For each field Manifold Site & Testing Facilities, the designations listed in Table 2
shall be used for BBB.

CCC 1 to 3 characters representing the equipment identification codes in Table 3.

DDD Sequential numbers

H:\Data\UD Downloads\ECS 1-1-2 Rev 4.doc


ESSO EXPLORATION &
PRODUCTION CHAD INC. ECS 1-1-2
EQUIPMENT, INSTRUMENTATION
Page 6 of 14
AND LINE DESIGNATION

SPECIFICATION Rev. 4 May 2010

E Letter identifier distinguishing multiple equipment items in the same service.

Example: Two pumps in the same service at the Kome Gathering Station would be
numbered K300-P-101 A/B.

TABLE 2

Field Manifold Designation

Manifold Site Location

K151 Wellsite K41


K152 Wellsite K36
K153 Wellsite K222
K154 Wellsite K27
K155 Wellsite K19
K156 Wellsite K14
K157 Wellsite K9
K158 Wellsite K4
K159 Wellsite K304
K160 Wellsite K404
K161 Kome Gathering Station
Water Injection Manifold K162
K162
RSV Site K163 (002 & 003)
K163
RSV Site K152 (002, 003, 004,
K164
005) RSV Site K153 (007)
Water Injection Manifold K165
K165
Water Injection Manifold K166
K166
Water Injection Manifold K167
K167
K168 Polymer Pilot Manifold K168
K169 South East Water Injection K169
K170 New manifold for additional wells
Bolobo Well Site B34
B151
Bolobo Well Site B10
B152
Bolobo Gathering Station
B153

H:\Data\UD Downloads\ECS 1-1-2 Rev 4.doc


ESSO EXPLORATION &
PRODUCTION CHAD INC. ECS 1-1-2
EQUIPMENT, INSTRUMENTATION
Page 7 of 14
AND LINE DESIGNATION

SPECIFICATION Rev. 4 May 2010

D151 Moundouli Site


Miandoum Wellsite M033
M151
Miandoum Wellsite M059
M152
Miandoum Gathering Station
M153
M154 Miandoum Well Site M060
M155 Miandoum Water Injection
Manifold
N151 NYA Site

P151 Poutouguem (Maikeri) Site

TABLE 3

Process Equipment Identification Codes


Equipment Type (1) Equipment Identifier
Battery BAT
Burn/Drain Pit BD
Building Exhaust Fan BEF
Blower BL
Ball Mill BLM
Building BU
Pressure Vessels - Columns C
Centrifuge CF
Combustion Gas Turbine Genset CTG
Diesel Engine DE
Diesel Genset DG
De-aerator DH
Air Coolers EA
Heat Exchangers - Plate EP
Heat Exchangers - Shell and Tube ES
Evaporator EV
Fan FAN
Filter FIL
Flare Stack FS

H:\Data\UD Downloads\ECS 1-1-2 Rev 4.doc


ESSO EXPLORATION &
PRODUCTION CHAD INC. ECS 1-1-2
EQUIPMENT, INSTRUMENTATION
Page 8 of 14
AND LINE DESIGNATION

SPECIFICATION Rev. 4 May 2010

Process Equipment Identification Codes


Equipment Type (1) Equipment Identifier
Fired Heaters H
Induced Gas Flotation Units IGF
Inert Gas Generator IGG
Incinerator INC
Compressors K
Static Mixer MIX
Muffler MU
Pumps - Pipeline P
Pumps - Process P
Pumps - Service P
Pumps - Chemical PCI
Packaged Units PK
Settling Basin SB
Scraper Launchers/Receivers SCR
Sump SMP
Stack STK
Tanks - Ambient Temperature T
Tanks - Heated T
Free Water Knockouts - Unheated V
Pressure Vessels - Emulsion Treaters V
Pressure Vessels - Separator V
Free Water Knockouts - Heated VH
Waste Heat Exchanger WH

Note:

1. Equipment identifications not listed here shall be as per Standard Legend -


Equipment Identification Letters and Line Service Designations, Drawing No.
7400-G000-50D2-0004 (see ECS 1-1-3).

PIPING LINE IDENTIFICATION

5.1 All line identification information shall be shown on each line on P&ID drawings, line lists
H:\Data\UD Downloads\ECS 1-1-2 Rev 4.doc
ESSO EXPLORATION &
PRODUCTION CHAD INC. ECS 1-1-2
EQUIPMENT, INSTRUMENTATION
Page 9 of 14
AND LINE DESIGNATION

SPECIFICATION Rev. 4 May 2010

and any other documents requiring line designation numbers.

5.2 The following is the identification system to be used to identify a line (Refer to Standard
Legend - Piping Components and Instrument Lines, Drawing No. 7400-G000-50D2-
0001, ECS 1-1-3):

4 - CAAG2 - NG - 0101 - 25 H E
│ │ │ │ │ │ │
│ │ │ │ │ │ └───── Tracer Type
│ │ │ │ │ └─────── Insulation Type
│ │ │ │ └────────── Insulation Thickness (mm)
│ │ │ └────────────── Line Number
│ │ └─────────────────── Line Service Designation
│ └───────────────────────── Piping Class
└────────────────────────────── Nominal Pipe Size (NPS)

5.2.1 The piping class shall be per ECS 3-30-0.

5.2.2 The letter(s) used to designate a line shall be as per Line Service Designations on
Drawing No. 7400-G000-50D2-0004 (see ECS 1-1-3).

5.2.3 The following procedures shall be adhered to when numbers are assigned to lines:

a. All lines shall be assigned with a number regardless of size or length with the
following exceptions:

• control valve bypasses


• instrument tubing
• tracing lines
b. A four digit line number, starting with 0000 upward when practical, shall be
assigned sequentially according to flow direction for each service.

c. Once a line number is assigned, it is not to be revised or reused to accommodate


additional lines.

d. Line numbers shall be changed with change of service designation, pipe class,
pipe size, insulation or tracing requirements.

5.2.4 The type of insulation shall be represented by the following codes:

Code Type

A Acoustical
C Cold
F Freeze Protection
H:\Data\UD Downloads\ECS 1-1-2 Rev 4.doc
ESSO EXPLORATION &
PRODUCTION CHAD INC. ECS 1-1-2
EQUIPMENT, INSTRUMENTATION
Page 10 of 14
AND LINE DESIGNATION

SPECIFICATION Rev. 4 May 2010

H Hot
P Personnel Protection

5.2.5 Insulation type coding is omitted from line numbers if no insulation is required.

5.2.6 The type of tracer shall be represented by the following codes:

Code Type

E Electric
G Glycol-water
H Hot oil
S Steam

5.2.7 Tracer type coding is omitted from line numbers if no tracing is required.

PIPELINE IDENTIFICATION

6.1 Pipelines shall be numbered using the format:


ABBB-CC-DDXXXXYYYY
which is defined as follows:
A 1 character describing the field:

K Kome Field
M Miandoum Field
B Bolobo Field
D Central Treating Facilities (CTF)
T Timbre Field

BBB 3 characters describing the type of pipeline

200 Emulsion Flowline


210 Emulsion Gathering Line
220 Gas Condensate Line
230 Water Injection Line
250 Emulsion Trunk Line
260 Water Trunk Line
270 Gas Trunk Line
280 Condensate Line

CC PL (Pipeline designation)

DD Pipe NPS

XXXX Pipeline Source ID (up to four characters)


H:\Data\UD Downloads\ECS 1-1-2 Rev 4.doc
ESSO EXPLORATION &
PRODUCTION CHAD INC. ECS 1-1-2
EQUIPMENT, INSTRUMENTATION
Page 11 of 14
AND LINE DESIGNATION

SPECIFICATION Rev. 4 May 2010

YYYY Pipeline Destination ID (up to four characters). If the site has an inlet
manifold, use the manifold ID rather than the site ID.

Example: 4" Flow Line within Kome field going from well K15 to Manifold site K156
would be numbered K200-PL-4K15K156.

LINE LISTS

7.1 Line Lists shall contain the following identifying information for each line.

a. Nominal pipe size and wall thickness.


b. Piping class.
c. Line service designation.
d. Line number.
e. Insulation type and thickness.
f. Heat tracer type.
g. Amount of x-ray.
h. Stress relief requirement.
i. Origin and termination.
j. Design and operating temperatures and pressures.
k. Test pressure.
l. If allowances for variations from normal operations is being made per ANSI
B31.3 par. 302.2.4, indicate the pressure-temperature condition which governs
the design and identify the situation causing these conditions.

m. Process flow conditions (rate, pressure drop, type of fluid, etc.).


n. Piping metal temperatures used for flexibility check (indicate more than one
temperature if multiple temperature conditions apply).

o. Identify the governing conditions for piping flexibility design, such as maximum-
minimum operating temperatures, equipment or line steam-out, line bypassed,
regeneration, steam tracing, tank nozzle rotation.

# 7.2 The standard line lists format shall be as per Figure 1. Modifications to this format shall
be approved by ESSO.

ELECTRICAL EQUIPMENT DESIGNATION

8.1 Electrical equipment designations shall consist of symbols, letters and numbers as per
"All Facilities Standard Legend" drawings (see ECS 1-1-3):

7400-G000-90D0-0001
H:\Data\UD Downloads\ECS 1-1-2 Rev 4.doc
ESSO EXPLORATION &
PRODUCTION CHAD INC. ECS 1-1-2
EQUIPMENT, INSTRUMENTATION
Page 12 of 14
AND LINE DESIGNATION

SPECIFICATION Rev. 4 May 2010

7400-G000-90D0-0002

8.2 Electrical apparatus shall be numbered using the format:


ABBB-ZZCCC-DDD E
which is defined as follows:
A 1 character describing the location of the facilities as follows:
G General (Total Area)
K Kome Field
M Miandoum Field
B Bolobo Field
D Doba Operations Centre (DOC)
T Timbre Field

BBB 3 characters describing the type of facilities as follows:


000 General
100 Wellsites
150 Well Manifold and Testing Facilities
200 Infield Pipelines
250 Trunklines
300 Gathering Stations
350 Pump Stations
351 Kome Pump Station KP-1
352 Kome Pump Station KP-2
400 Central Treating Facilities
500 Power Generation
550 Power Distribution/Transmission
600 Electrical Substations
650 Control Stations/Rooms
700 Housing/Community
750 Airfield
800 Roads
850 Utilities/Support Facilities
900 Communications Facilities

ZZ 1 to 3 characters representing process equipment identification codes as per


Table 3. In some cases, no characters will be used for ZZ if the electrical
equipment item is not associated with process equipment.

CCC 1 to 3 characters representing the equipment identification codes in Table 4.

DDDD Sequential Numbers

E Letter identifier distinguishing multiple equipment items in the same


service.

Examples: Hot oil pump motor at the Kome gathering Station would be numbered
K300-PM-401 A.
H:\Data\UD Downloads\ECS 1-1-2 Rev 4.doc
ESSO EXPLORATION &
PRODUCTION CHAD INC. ECS 1-1-2
EQUIPMENT, INSTRUMENTATION
Page 13 of 14
AND LINE DESIGNATION

SPECIFICATION Rev. 4 May 2010

A transformer at the Kome Gathering Station would be numbered


K300-TNS-001 A.

TABLE 4

Electrical Equipment Identification Codes


Equipment/Device Identification
Generators GE
Electric Motor M
Transformers TNS
Circuit Breakers (Power) BKR
Switchgears SGR
Motor Control Centers MCC
Disconnect Switches (Power) SW
Potential Transformers PT
Current Transformers CT
Contactor C
Grounding Resistors R
Grounding Transformers TNS
(Distribution Type)
Lighting Panels LP
Batteries BAT
Battery Chargers BC
Uninterruptable Power Supplies UPS
Space Heaters HTR

H:\Data\UD Downloads\ECS 1-1-2 Rev 4.doc


ESSO EXPLORATION &
PRODUCTION CHAD INC. ECS 1-1-2
EQUIPMENT, INSTRUMENTATION
Page 14 of 14
AND LINE DESIGNATION

SPECIFICATION Rev. 4 May 2010

FIGURE 1

Line List

H:\Data\UD Downloads\ECS 1-1-2 Rev 4.doc

You might also like