2012 Introduction of A Wind Powered Pumped Storage System in The Isolated Insular Power System of Karpathos-Kasos

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

Applied Energy 97 (2012) 38–48

Contents lists available at SciVerse ScienceDirect

Applied Energy
journal homepage: www.elsevier.com/locate/apenergy

Introduction of a wind powered pumped storage system in the isolated


insular power system of Karpathos–Kasos
Dimitris Al. Katsaprakakis a,⇑, Dimitris G. Christakis a,1, Kosmas Pavlopoylos b,2, Sofia Stamataki c,3,
Irene Dimitrelou c,3, Ioannis Stefanakis d,4, Petros Spanos d,4
a
Wind Energy and Power Plants Synthesis Laboratory, Technological Educational Institute of Crete, Estavromenos, 710 04 Heraklion, Crete, Greece
b
Harokopeio University of Greece, Department of Geography, El. Venizelou Str 70, Athens 176 71, Greece
c
Laboratory of Applied Geophysics, National Technical University of Athens, Iroon Polytechniou 9, Zografou Campus, Athens 157 73, Greece
d
ENET S.A., Christou Lada 1, Karitsi Square, Athens 10561, Greece

a r t i c l e i n f o a b s t r a c t

Article history: This paper presents a power production system for the isolated insular power system of the islands
Received 12 July 2011 Karpathos and Kasos. Karpathos and Kasos are two small islands, located in the South-East Aegean Sea
Received in revised form 25 October 2011 (Dodecanese complex) that are not connected to the main power distribution network. Energy produc-
Accepted 25 November 2011
tion is based exclusively on an autonomous thermal power plant and a small wind park, installed on
Available online 24 December 2011
the island of Karpathos. The maximum annual power demand has been estimated to exceed 12 MW
by 2014. The mean specific annual energy production cost from the existing system has been calculated
Keywords:
at 0.249 €/kW h in 2008.
Wind turbine
Wind park
The proposed system aims at the maximisation of wind energy penetration and the minimisation of
Pumped storage imported fossil fuel use for the production of electricity.
Renewable energy The proposed system consists of a wind park and a pumped storage system (PSS). The introduced
Hybrid power systems power system aims to guarantee power production for certain hours per day. A thorough sitting of the
Isolated non-interconnected insular systems system is accomplished. Three different sites for the PSS installation are examined before the optimum
is selected. The available wind potential of the islands was evaluated using a wind mast installed within
the frame of the examined project’s feasibility study. The annual mean wind velocity at the wind park’s
installation site was measured to be higher than 11.5 m/s.
The introduced system’s set-up, and operation & maintenance cost parameters have been estimated.
The dimensioning of the system aims mainly at optimising the project’s economic indexes, following
the existing legislative framework. The annual guaranteed energy production has also been maximised.
An economic sensitivity analysis is performed. It is estimated that the proposed project can exhibit
attractive economic indexes, regardless of the availability of a subsidy, on the condition that the selling
price of energy should be configured at 0.3552 €/kW h and the selling price of guaranteed power should
be 127 €/kW year.
Under the above mentioned prerequisites, the project payback period is estimated at 5–6 years.
The present paper proves the economic feasibility of small scale wind powered pumped storage sys-
tems, not taking into account the undoubted environmental benefits.
Ó 2011 Elsevier Ltd. All rights reserved.

1. Introduction since 2006. In this legislation framework, the WP-PSS, defined as


hybrid power stations, are introduced as guaranteed power pro-
The wind powered pumped storage systems (WP-PSS) have duction plants in existing electricity systems. The scope of these
been introduced in the Greek legislation through a number of laws, hybrid stations is to provide the electricity production system with
pre-defined guaranteed power for certain time periods during a
⇑ Corresponding author. Tel.: +30 2810 379220; fax: +30 2810 319478. day. These time periods must include the daily time periods of
E-mail addresses: dkatsap@wel.gr (D.Al. Katsaprakakis), dimitris@wel.gr
peak power demand. Consequently, the ultimate scope of a hybrid
(D.G. Christakis), kpavlop@hua.gr (K. Pavlopoylos), stamat@metal.ntua.gr station introduced in a power system is to substitute the existing
(S. Stamataki), dimitrel@metal.ntua.gr (I. Dimitrelou), stefanakisi@enetsa.gr expensive power production from thermal generators during peak
(I. Stefanakis), spanosp@enetsa.gr (P. Spanos). power demand time periods. The price of guaranteed energy
1
Tel.: +30 2810 256191; fax: +30 2810 319478.
2
produced from WP-PSS is configured in terms of the annually aver-
Tel: +30 210 9549160; fax: +30 210 9514759.
3
Tel.: +30 210 772 2202; fax: +30 210 772 2203.
aged specific production cost of the existing electricity production
4
Tel.: +30 210 650 9150; fax: +30 210 654 0802. system during peak power demand periods.

0306-2619/$ - see front matter Ó 2011 Elsevier Ltd. All rights reserved.
doi:10.1016/j.apenergy.2011.11.069
D.Al. Katsaprakakis et al. / Applied Energy 97 (2012) 38–48 39

Since 2006, several investors have been applied to the Regula-  The maximisation of wind power penetration in the electricity
tory Authority of Energy (RAE) for the installation of WP-PSS production sector.
mainly in the Greek non-interconnected islands. A small number  The minimisation of imported fossil fuel consumption for elec-
of these applications have already been approved. Consequently, tricity production.
during the next years, the first WP-PSS will be constructed and
set in operation. The construction and the operation of WP-PSS These targets are approached through the pre-defined guaran-
in Greece constitutes the successful integration of the hard effort teed power production during the daily time periods of peak power
and time put in by a number of scientists and engineers [1–13] demand, substituting the existing expensive power production
to prove to the Greek political and social community that these from thermal generators.
systems are of the most promising solutions for the electrification
of the country, based on Renewable Energy Sources (RES). 2. The existing electricity production system
A large number of former studies investigate the issue of
introducing hybrid power systems based on Renewable Energy The electricity production at the examined islands is based on a
Sources for the electrification of non-interconnected insular sys- small thermal power plant and a small wind park, both of them in-
tems. Except WP-PSS, other proposed technologies are wind-diesel stalled on the island of Karpathos. The synthesis of the electricity
systems or wind-photovoltaic-batteries systems [14–16] and wind production system is presented in Table 1 [24].
compressed air systems (WCAS) [17,18]. The wind-photovoltaic Table 2 presents the electricity production and demand per
systems are usually proposed for small or medium size decentra- month in the examined system for the year 2008. As seen in
lised production (e.g. small settlements [14–16]). The introduction Table 2, the electricity demand exhibits intensive seasonal varia-
of WCAS is mainly examined and proposed in places with low- tion. These are imposed mainly by the tourist sector, which con-
price fossil fuels (e.g. Canada [17], Australia [18]). In such cases siderably increases power demand during the summer months.
they exhibit quite attractive economic features. The conventional In Table 3 the estimated electricity annual demand and maxi-
lead batteries is generally not proposed for large sized systems mum power demand is presented for the examined system until
(power demand higher than 1 MW), taking into account the short 2014.
life period and the important environmental impacts of their The insular non-interconnected power system in Karpathos and
disposal. Kasos encounters the well-known operational problems, com-
The WP-PSS features as the most economically and technically monly met in similar isolated systems of small size [25–28].
competitive technology in different geographical areas [19–22]. A System instability and dynamic security contingencies (e.g. power
major advantage of the WP-PSS is the improvement of the dynamic production loss) are usually met in the examined power system.
security of non-interconnected power systems, through the intro- These contingencies can cause several malfunctions to the normal
duction of the hydro turbines [23]. operation of the utility network, from power quality disturbances
In this work, the feasibility study for the introduction of a WP- (voltage drops, transients, etc) to total system black-outs. The wind
PSS in the non-interconnected islands of Karpathos and Kasos is power penetration is also restricted, for reasons regarding the
presented. Karpathos and Kasos are two small islands located in system’s security.
South-East Aegean Sea (Dodecanese complex) (Fig. 1). These is- The examined system’s dynamic security is improved with the
lands are electrically connected to each other. In total, they consti- thermal generators’ spinning reserve. However, the thermal gener-
tute a non-interconnected electricity system. ators’ spinning reserve and the low wind power penetration, lead
The ultimate scope of the proposed system is: to significant increases in the electricity production cost. This cost

Fig. 1. The map of the islands of Karpathos and Kasos and their position in the South East Aegean Sea.
40 D.Al. Katsaprakakis et al. / Applied Energy 97 (2012) 38–48

Table 1 power will be produced only by the hydro turbines, exploiting


The existing electricity production system on the islands of Karpathos–Kasos. the water stored volume in the PSS upper reservoir. The hydro tur-
Generator type Number of Maximum Minimum Fuel bines will be connected with the PSS upper reservoir with a sepa-
generators power output power output rated penstock, exclusively used for water fall.
(MW) (MW) The required power for the water storage in the PSS upper res-
Diesel engine 2 1.800 1.100 Diesel ervoir will be provided either:
Daihatsu oil
8DV-26
Diesel engine 1 0.600 0.400 Diesel
 By the hybrid station’s wind park, whenever wind power is
USSR G72 oil available. A separated penstock will be used exclusively for
Wartsila W 2 5.327 2.660 Diesel pumping water to the upper reservoir. The power produced
12V32 oil by the wind park will not be provided directly to the PSS pumps.
Wind park – 1.225 – –
On the contrary, the wind park produced power will penetrate
TOTAL 16.079 7.920
the utility network. At the same time, the PSS pumps motors
will consume power from the utility network, equal to the wind
power production. In this way, both the stability of the network
Table 2 and the normal power provision to the PSS pumps are ensured.
The monthly electricity production and demand on the islands of Karpathos–Kasos in  By the thermal generators, only during night time periods (low
2008.
power demand periods), in case there is a shortage of stored
Month Total net electricity Wind park electricity Net electricity water in the PSS upper reservoir and null wind power
production (MW h) production (MW h) demand production.
(MW h)
January 2583.052 183.215 2766.267 According to the Greek legislation, the annual energy from
February 2608.520 298.478 2906.998
existing thermal generators used for supplementing the upper
March 2090.510 214.632 2305.142
April 2167.604 154.927 2322.531 reservoir cannot exceed the 30% of the total annual energy storage
May 2390.270 213.659 2603.929 in the PSS upper reservoir.
June 2985.748 274.196 3259.944 The operation of the WP-PSS is presented graphically in Fig. 2.
July 3522.836 464.650 3987.486 From the above figure it is clear that the hybrid station’s wind
August 3876.378 478.530 4354.908
September 2935.600 532.122 3467.722
park is used only for energy storage. The produced wind power
October 2111.292 277.521 2388.813 cannot penetrate to the utility network either as a percentage of
November 2040.400 154.230 2194.630 the total guaranteed power production from the hybrid station,
December 2491.826 183.750 2675.576 nor as an independent non-guaranteed power production unit.
Total 31804.036 3429.910 35,233.946
The guaranteed power will be produced exclusively by the hydro
turbines.
In practice, the existing legislation does not prohibit the direct
Table 3 penetration of a hybrid station’s wind park as a non-guaranteed
Estimation for the annual electricity and maximum power demand on Karpathos–
power production unit, in case the utility network is able to absorb
Kasos until 2014.
the wind power production. However, the ability of the network to
Year Annual electricity demand Maximum annual power demand absorb the wind power production from the hybrid station’s wind
(MW h) (MW)
park is not easily predicted, since it depends on the wind power
2010 39,171 10.50 production of the already existing wind parks in the non-intercon-
2011 40,696 11.00 nected system. The calculation of the wind power production from
2012 42,199 11.50
2013 43,674 12.00
the existing wind parks requires the availability of annual wind
2014 45,114 12.50 velocity time-series measured on their installation sites. The lack
of this data can lead to inaccurate results that, in turn, may intro-
duce a considerable error in the investment’s economic evaluation.
The construction of two penstocks, one exclusively for water fall
is further increased by the expensive diesel oil, consumed by the and one exclusively for pumping water, enables the PSS flexible
installed thermal generators in the autonomous thermal power operation and maximises its contribution to the system’s stability
plant. The annual average specific electricity production cost is and dynamic security. This is achieved with either the hydro tur-
estimated equal to 0.249 €/kW h in 2008, taking into account the bines contribution to the system’s frequency regulation or the
fuel cost only. pumps loads cut in case of a sudden power production loss.
Finally, another major problem of the examined power system
is that the island of Kasos has no power production units of its
own but depends totally on the units installed in Karpathos. As 4. Sitting of the pumped storage system
such, Kasos is far more vulnerable to the system’s security prob-
lems and power quality disturbances. Power supply interruptions The PSS has been selected to be installed in the island of Kasos,
constitute a common problem for the citizens in Kasos. The most mainly to establish a power production balance between the two
extreme situation that the island of Kasos faced during the last dec- islands that will improve the system’s stability and security. As
ade was the total loss of power supply for 1 week, when the con- the required quantities of drinking water for the PSS operation in
nection cable between the two islands was cut by a trail net. Kasos cannot be met, seawater must be used. In this case, the
PSS lower reservoir will be the sea [29]. Consequently, the sitting
3. The introduced WP-PSS operation of the PSS focuses on the selection of the position for the construc-
tion of the upper reservoir and the design of the penstocks’ route.
According to Greek legislation, the introduced WP-PSS aims to The appropriate sitting of a pumped storage system is a multi-
guarantee power production during pre-defined hours every day, parameter procedure that requires the collaboration of engineers
including the peak power demand time periods. The guaranteed and scientists from different scientific fields (mechanical and civil
D.Al. Katsaprakakis et al. / Applied Energy 97 (2012) 38–48 41

Fig. 2. The operation of the examined wind powered pumped storage system.

engineers, mining engineers and metallurgists, geologists, hydro- Important geotechnical problems related to the stabilities of
geologists, etc). Moreover, the sitting of a PSS cannot be integrated rocky masses and wedge slip are located in the route of the pipe-
properly without visiting the candidate sites. The research team of line to the sea, as well as with their cohesion at the phase of exca-
the presented project visited the island of Kasos and examined vations. The most important problem deals with the intense relief
three different positions before settling on the chosen site for the slopes and in dips and dips direction of the thin-bedded lime-
PSS installation. The evaluation of the examined sites was per- stones, which are of similar inclination with dip slopes. For this
formed in terms of the following parameters: reason a thorough geotechnical study is required.
The coast in the potential place where the pipeline reaches the
 The geologic – geomorphologic features of the area. sea is steep, exposed to the erosive marine processes of waves and
 The available place for the PSS upper reservoir and the existence sea water impregnation, so that they are more susceptible to col-
of physical cavities that help the reservoir construction, reduc- lapses and slip of rocky masses.
ing the required digging works and consequently reducing the
construction cost.
 The available head height. 4.2. Technical features
 The total penstock length from the upper reservoir to the sea.
 The terrain morphology and the available routes for the pen- The basin of the artificial reservoir is shaped between the con-
stock installation. tours of 480 m and 465 m (Fig. 3), with excavations that lend form
 The accessibility of the area by land and by sea. of inverted truncated cone and with dip of conical surface 45°.
A synopsis for the reservoir’s basic technical features is pre-
Taking into account the above mentioned parameters, the re- sented in Table 4.
search team evaluated the visited sites and selected the optimum The penstock route follows the mountain’s incline to the north
one, presented in Fig. 3. coast of the island. The penstock length is estimated to 1450 m.
The site presented in Fig. 3 is located at the mountain Taking into account the available minimum head height (approxi-
‘‘Kapsalos’’, close to the north coast of the island. The characteristic mately 455 m including the water flow losses), the ratio of the
features of this site and the results of its evaluation are presented available head height over the penstock length is calculated Dh/
in the following sub-sections. L  1/3. This value is quite satisfactory, positively affecting several
parameters regarding the penstock construction and the PSS oper-
ation, such as the required pipelines diameter and width, the water
4.1. Geologic – geomorphologic features flow linear losses, the PSS total efficiency and finally the penstock
set-up cost and hence the economic indexes of the investment.
The limestone formations are tectonically strain with joint and The sectional view of the penstocks’ route from the upper reser-
fissures systems, karstified at places, making the excavation in the voir to the sea is presented in Fig. 4. In this figure it is seen that the
upper area of the artificial reservoir relatively easy, through the use penstock follows an underground route for approximately the first
of hammer and/or/ explosives. 260 m from the upper reservoir position. Excluding that part, the
42 D.Al. Katsaprakakis et al. / Applied Energy 97 (2012) 38–48

Fig. 3. The sitting of the pumped storage system at the mountain ‘‘Kapsalos’’ in the north coast of the island of Kasos.

rest of the penstock is installed on the surface of the mountain’s in- Table 4
cline. Special digging works and techniques (e.g. cut and cover) are Technical features of the PSS upper reservoir.
required in cases of abrupt changes of mountain slopes, as well as
Reservoir effective capacity (m3) 465,062
close to the corrosive coastal area, aiming at a secure penstock pas- Reservoir’s upper surface area (m2) 36,654
sage and grounding and the penstocks’ protection against the cor- Reservoir’s maximum depth (m) 15
rosive conditions caused by the seawater combined with the wind. Reservoir’s incline dip (o): 45
Minimum absolute altitude of the reservoir’s bottom (m) 465

5. Calculation data
The high wind potential available in the island of Kasos is de-
picted in the wind potential measurements presented in Table 6.
5.1. Data regarding the PSS installation site
It is worthy of mentioning that more than 150 wind measurement
masts have been installed in Greece by the Wind Energy Labora-
The calculation data regarding the PSS installation site are sum-
tory and their measurements have been processed by the authors
marised in Table 5.
of the present article. Comparing the measurements of the data
set from Kasos with that from other sites, it is revealed that the
5.2. Wind potential wind potential found in Kasos has not been met anywhere else un-
til today. Consequently, according to the wind potential data base
A 22.5 m height meteorological mast, installed at the wind of Wind Energy Laboratory, perhaps the largest wind potential data
park’s installation site, is used for the estimation of the available base in Greece, Kasos appears to be the windiest island in the Ae-
wind potential at the specific position. The recorded wind potential gean Sea.
measurements are presented in figs. 5 and 6. These results consti-
tute the data for the dimensioning and the sitting of the wind park, 5.3. Hydrodynamic machines efficiencies
as well as for the calculation of the annual electricity production
from the wind park. For the simulation of the PSS operation, the operational power –
The wind potential characteristics of the recorded measure- total efficiency curves, presented in Figs. 7 and 8, for the selected
ments are presented in Table 6. hydro turbine and pump models are introduced.
D.Al. Katsaprakakis et al. / Applied Energy 97 (2012) 38–48 43

Fig. 4. Sectional view of the penstock route.

Table 5
Calculation data for the PSS installation site.

Upper reservoir effective capacity (m3) 465,062


Minimum head height (m) 455
Penstock length (m) 1450

6. WP-PSS dimensioning

6.1. The dimensioning procedure

The WP-PSS dimensioning is performed with a software tool


developed by the Wind Energy and Power Plants Synthesis Labora-
tory. The following tasks are performed with this software:

 The simulation of the existing power production system opera-


tion at the examined islands.
 Introduction of the WP-PSS in the existing system and simula-
tion of its operation.
Fig. 5. Wind rose based on the wind potential measurements at the wind park’s
 Economic evaluation of the investment. installation site.
 Taking into account the PSS available head height and the upper
reservoir’s effective capacity, the software’s dimensioning aims
at:
 The maximisation of the guaranteed power produced by the
WP-PSS.
 The minimisation of the required wind park’s and pumps’ nom-
inal power, leading to minimisation of the project’s set-up cost.
 The maximisation of the daily time period of guaranteed power
production, leading to maximisation of the guaranteed energy
production by the WP-PSS.

The optimisation criterion for the WP-PSS dimensioning is the


optimisation of the investment’s economic indexes (payback peri-
od, internal rate of return, etc).

6.2. Main dimensioning results

The results from the dimensioning optimisation procedure are


presented in Table 7.
The wind park’s capacity factor, presented in Table 7, is defined Fig. 6. Wind velocity probability density Weibull distribution, based on the wind
as the ratio of the calculated annual electricity production from the potential measurements at the wind park’s installation site.
wind park over the maximum theoretical annual electricity
production from the wind park (the product of the wind park’s
nominal power with the total time period of 1 year).
The annual energy production and energy storage from the The mean annual PSS efficiency is defined as the ratio of the
examined WP-PSS are presented in Table 8. Taking into account annual guaranteed energy production by the hydro turbines over
the presented data in Table 3, the annual guaranteed energy the total annual energy storage by the pumps.
production from the WP-PSS, as presented in Table 8, corresponds The rejected wind energy is the energy not exploited by the PSS
to the 23.36% of the estimated annual electricity consumption in because either the upper reservoir is full or the wind power
Karpathos–Kasos in 2014. production is higher than the pumps nominal power.
44 D.Al. Katsaprakakis et al. / Applied Energy 97 (2012) 38–48

Table 6 Table 8
Wind potential characteristic features, based on the wind potential measurements at Annual energy production and storage from the WP-PSS.
the wind park’s installation site.
Wind park’s annual energy production (MW h) 21,617
Wind velocity mean annual value (m/s) 11.61 Annual guaranteed energy production from hydro turbines (MW h) 10,486
Weibull C parameter (m/s) 13.20 Annual energy storage from wind park (MW h) 16,840
Weibull k parameter 2.85 Annual energy storage from thermal generators (MW h) 0
Wind power density (W/m2) 1447 Annual total energy storage (MW h) 16,840
Measurements time period 14/5/2010–13/5/2011 Wind park’s annual energy rejection (MW h) 4777
12 months Annual energy storage from thermal generators percentage over 0.00
total annual energy storage (%)
Wind park’s annual energy rejection percentage over total annual 22.10
wind park’s energy production (%)
Mean annual PSS efficiency (%) 62.27

from the WP-PSS for certain time periods during a day is presented,
substituting thermal generators’ power production.

6.3. Hydrodynamic machines

For the PSS operation, a Pelton hydro turbine and a multi-staged


pump model are selected. The Pelton model is selected because it
exhibits constant and high efficiency for the 90% of the output
power range, low cost, robust construction and it is capable to in-
Fig. 7. Efficiency variation in terms of the normalised power production of the crease the power production within a few seconds. The last feature
selected hydro turbine model. is very important regarding the power system’s stability and dy-
namic security.
The multi-staged pump model was the only techno-economic
feasible solution for the operation with the available head height.
The pump’s power regulation will be performed with a cyclo-
converter.
Two horizontal axis Pelton hydro turbine units of nominal
2 MW each will be installed, giving a total hydro power of 4 MW.
Taking into account that the guaranteed power produced by the
hydro turbines is set at 3 MW, there will always be a hydro power
surplus of 1 MW. This power surplus can be exploited as power
production spinning reserve, contributing to the system’s fre-
quency regulation and to the improvement of the dynamic
security.
The required pumping water flow at the available head height
can be provided with a combination of eight pump units of
Fig. 8. Efficiency variation in terms of the normalised power consumption of the 560 kW nominal power each. The selected pump model is a five-
selected pump model.
stage pump with horizontal axis.
The above mentioned regarding the PSS hydrodynamic ma-
chines are summarised in Table 9. The characteristic curves of
Table 7 the selected pump models with the nominal operational point
Dimensioning of the examined WP-PSS. are presented in Fig. 10.
Guaranteed power production of the hybrid station 3.00
(MW)
Wind park nominal power (MW) 4.50 6.4. Penstocks
Hydro turbines total nominal power (MW) 4.15
Pumps total nominal power (MW) 4.48 The penstocks’ diameters are selected in order to reduce the
Penstock inner diameter for water fall (mm) 800
water flow losses. In Fig. 11, the water flow losses variations in
Penstock inner diameter for water pumping (mm) 800
Wind turbine selected model Enercon E-44/ terms of the penstocks’ diameter are presented. In Table 10 the
900 kW maximum flow losses for the penstocks’ selected diameter, exhib-
Wind park capacity factor (%) 52.76 iting for the nominal water flows, are presented.
Hydro turbines total nominal flow (m3/s) 0.74 Apart from the penstocks’ diameter, the construction material
Pumps total nominal flow (m3/s) 0.72
Daily time period of guaranteed power production 8:00–22:00
must be defined and the required widths must also be calculated.
Total daily hours of guaranteed power production 14 The required penstocks’ widths are calculated in terms of the max-
imum exhibiting pressure, configured by the hydrostatic pressure
and the maximum water hammer pressure.
The penstock will be constructed from Glass Reinforced Polyes-
The results presented in Table 8 have been calculated assuming ter (GRP) for nominal pressures lower than 32 bar as GRP is an
3% electricity transportation losses. excellent material for the transportation of seawater. Taking into
In Fig. 9, the power production synthesis is presented after the account that the maximum physical head height is 480 m, this im-
introduction of the WP-PSS, from 1 to 15 of August (high season plies the penstocks will be constructed with GRP tubes for altitudes
power demand). In this figure the guaranteed power production between 160 m and 480 m.
D.Al. Katsaprakakis et al. / Applied Energy 97 (2012) 38–48 45

Fig. 9. Power production synthesis after the introduction of the WP-PSS from 1 to 15 of August (high power demand season).

Table 9
Hydro turbines and pumps model and units numbers in the examined PSS.

Machine type Unit nominal power (kW) Units number Total installed power (kW)
Hydro turbines Pelton 2075 2 4150
Pumps Multi-stagedPower regulation with cyclo-converters 560 8 4480

7. Economic evaluation

The proposed WP-PSS economic evaluation is based on previous


statistical data from similar implemented projects [1–3,6,7,11,13,
29,30] and on the available quotation regarding the project’s main
equipment, provided by the corresponding construction compa-
nies. A relevant bibliography and market research concerning the
WP-PSS set-up and operational cost was also accomplished. The se-
lected information was used to develop a data base for the economic
evaluation of the examined power system. A computational model
was developed based on this data base. Some basic features of the
developed model and the results of the accomplished economic
evaluation are presented in the following sub-sections.

7.1. Set-up cost

The WP-PSS set-up cost is calculated taking into account the


following values, arising from the system’s dimensioning and
sitting:

 Wind park nominal installed power: 4.5 MW.


 Hydro turbines nominal installed power: 4.00 MW.
 Pumps nominal installed power: 4.48 MW.
 Total digging volume for the penstock installation 30% higher
than the total penstock outer volume: (1703 m3  1.30 =
2214 m3).
 Tunnel length: 260 m.
Fig. 10. The selected pump model curves with the nominal operational point.
 Total digging volume for the upper reservoir construction:
200,000 m3.
 Upper reservoir bottom’s total surface: 40,000 m2.
For altitudes between 0 m and 160 m the penstock will be  New roads total length: 6.5 km.
constructed from St52, exhibiting a yield point of 330 MPa. In order  New utility network length: 16 km.
to prevent the steel tubes from seawater corrosion, a thick film of
mixed phenol and epoxy resins, without dissolver, will be applied The lower penstock’s intake must be protected against high sea
in the inner surface of the tubes. waves with a precast concrete block breakwater. The upper reser-
The construction of the penstock is designed as presented in voir’s bottom should be configured and insulated properly in order
Table 11. to prevent seawater leakage [29].
46 D.Al. Katsaprakakis et al. / Applied Energy 97 (2012) 38–48

Table 12
WP-PSS set-up cost calculation.

No Set-up cost component Cost (€)


1 Wind park 4800,000
2 Hydro turbines and generators (hydro power plant) 2800,000
3 Pumps and motors (pumps station) 4240,000
4 Penstocks 2400,000
5 Upper reservoir 4300,000
6 New roads construction 600,000
7 New utility network 800,000
8 Several infrastructure works 900,000
9 Buildings 500,000
10 Secondary electromechanical equipment - SCADA 2200,000
11 Consultants fees 300,000
12 Several other costs 500,000
Total PSS set-up cost 17,540,000
Total hybrid station set-up cost 22,340,000

Fig. 11. Maximum water flow losses variations in terms of the penstocks’
diameters, for nominal water flows.
Table 13
Investment’s funding scheme.

Percentage (%) Amount (€)


Table 10
Maximum flow losses in penstocks, for maximum water flows. Equities 50.00 11,170,000
Long term loan 50.00 11,170,000
Water fall Water Subsidy (state contribution) 0.00 0
penstock pumping Total 100.00 22,340,000
penstock
Selected penstock inner diameter (m) 0.80 0.80
Maximum flow losses (m) 18.98 20.32
Maximum flow losses percentage over 4.17 4.47
Table 14
available minimum head height (%)
Investment’s total annual revenues.
Maximum water velocity in penstocks (m/s) 1.42 1.47
Revenues (€)
From guaranteed energy vending 3724,555
From guaranteed power vending 380,880
Table 11 Total 4105,435
The analysis of the construction of the PSS penstocks.

Absolute altitude Material Nominal pressure Length


(m) (bar) (m) Following the relevant legislation, the investment’s annual
480–420 GRP 6 379.83 revenues are calculated with the following sale price of energy
420–380 GRP 10 139.40 and power:
380–320 GRP 16 207.14
320–280 GRP 20 73.01
280–230 GRP 25 89.17
 Guaranteed energy price: 0.3552 €/kW h.
230–160 GRP 32 144.19  Guaranteed power price: 127 €/kW year.
160–100 Steel S355J2G4 (ST 38 119.40
52) Taking into account the total annual guaranteed energy produc-
100–30 Steel S355J2G4 (ST 45 235.18
tion (10486 MW h, presented in Table 8) and the guaranteed
52)
30 to 2 Steel S355J2G4 (ST 52 62.49 power production (3 MW, presented in Table 7), the total invest-
52) ment’s revenues are calculated and presented in Table 14.
Total GRP penstock length (m) 1032.74
Total steel penstock length (m) 417.07 7.4. Annual costs – net profit
Total length (m) 1449.81

The project’s operational and maintenance costs are calculated


The results for the WP-PSS set-up cost calculation are summa- following the Greek legislation and the statistical data base config-
rised in Table 12. ured from existing similar projects worldwide. The project’s annual
costs are analysed in the following:
7.2. Funding scheme
 Municipal taxation rate equal to 3% of the investment’s total
The project’s funding scheme is configured as presented in Ta- annual revenues.
ble 13.  Wind turbines’ annual maintenance cost equal to 0.012 €/kW h
The loan payback period and rate are set equal to 15 years and of produced electricity from the wind park.
6.5% respectively.  Pumped storage system’s annual maintenance cost equal to
100,000 €.
7.3. Revenues  Annual Loan payment.
 Cost of energy purchased from the system. The price of the
The investment’s revenues are based on: purchased energy is set in terms of the mean annual specific
cost of electricity production during night time period, in the
 the sale of guaranteed energy produced existing power production system. This cost is estimated to
 the sale of guaranteed power production 0.2842 €/kW h.
D.Al. Katsaprakakis et al. / Applied Energy 97 (2012) 38–48 47

Table 15
Economic indexes calculated over the investment’s equity.

Net present value – NPV (€) 9102,945


Internal rate of return – IRR (%) 17.58
Payback period (years) 5.46
Discounted payback period (years) 7.55
Return on equity – ROE (%) 233.67
Return on investment – ROI (%) 116.83
Annual mean energy production specific cost (€/kW h) 0.1355

Fig. 13. Payback period sensitivity analysis graph, in terms of characteristic


economic parameters.

8. Conclusions

A wind powered pumped storage system for the non-intercon-


nected islands of Karpathos and Kasos is investigated in this paper.
The proposed PSS is designed to utilise seawater while the sea is
used as the PSS lower reservoir in order to:
Fig. 12. I.R.R. sensitivity analysis graph, in terms of characteristic economic
parameters.  Maximise the available head height.
 Ensure the availability of the PSS working mean in an area (east-
ern Mediterranean) with relatively low annual rainfall level.
 Total annual salaries: 100,000 €.
 Equipment insurance: 4‰ of the project’s set-up cost. The dimensioning, the sitting and the economic evaluation of
 Other annual costs: 50,000 €. the proposed system lead to the following conclusions:
 Constant depreciation over 14 years.
 State taxation rate: 25%.  The wind potential measured with the installed meteorological
 Project’s life period: 20 years. mast proved that the island of Kasos exhibits the highest wind
 Discount rate: 8.0%. potential ever met in an Aegean Sea island. The installation site
of the proposed wind park exhibits a capacity factor of higher
Following the above presented assumptions, the project’s an- than 52%.
nual cash flows are calculated for a time period of 20 years. The  The proposed power production system may appear attractive
sum of the net profits over the total project’s life period is calcu- financial ratios following the defined in the relevant legislation.
lated equal to 42,521,060 €.  The guaranteed electricity production by the WP-PSS can
exceed 23% of the annual electricity consumption in Karpa-
7.5. Economic indexes thos–Kasos in 2014.
 The proposed system was thoroughly planned and the required
The investment’s economic indexes, calculated over the equi- works were studied with accuracy. This enabled the analytical
ties, are presented in Table 15. and accurate calculation of the required infrastructure works
Two sensitivity analysis graphs, for the investment equities’ and the system’s set-up cost.
I.R.R. and payback period, in terms of characteristic economic  The environmental benefits from the restriction of the fossil
parameters, are presented in Figs. 12 and 13 respectively. fuels consumption and the national economies enforcement,
From the graphs presenting the sensitivity analysis, the follow- not taken into account in the present study, will raise the attrac-
ing conclusions can be made: tiveness of the proposed power system.

 The investment equities’ indexes are significantly improved In the majority of isolated power production systems world-
with increasing the selling price of energy and the subsidy. wide, the electricity production is based on imported fossil fuels.
 The effect of increasing the selling price of guaranteed power on The peculiarities met in these systems result in expensive and
the economic indexes is not so intensive. unstable electricity production. Increasing fossil fuel prices
 Minor improvement on the economic indexes can be seen by a recorded during the last years raises the cost of electricity produc-
reduction in the loan rate. tion and negatively affects the local economies. Moreover, the
48 D.Al. Katsaprakakis et al. / Applied Energy 97 (2012) 38–48

sensitive ecosystems, frequently met in these areas, are negatively [12] Katsaprakakis DAl, Christakis DG. Experience from the wind parks operation in
Crete and perspectives towards the maximization of the wind power
influenced by the operation of thermal power plants.
penetration. In: Proceedings of 5th world wind energy conference &
The proposed wind powered PSS in this paper, may represent exhibition WWEC, Energy independence powered by wind, November 6–8,
highly promising solutions for an alternative, environmentally 2006, New Delhi, India.
friendly electrification of isolated power production systems, [13] Katsaprakakis DAl, Christakis DG, Pavlopoulos Kosmas, Dimitrelou Irene,
Stamataki Sofia. Maximisation of R.E.S. penetration in small non-
contributing in minimising consumption of imported fossil fuels. interconnected insular systems. The case study of Agios Efstratios. In: 4th
The proposed system, although its small size, proved to be national conference: the introduction of renewable energy sources towards an
technically and economically feasible. Finally, the exploitation of ambitious and reliable national action plan, May 10–12, 2010, Athens, Greece
[in Greek].
renewable, environmentally friendly energy sources may provide [14] Hessami Mir-Akbar, Campbell Hugh, Sanguinetti Christopher. A feasibility
one more chance for a sustainable, viable worldwide development. study of hybrid wind power systems for remote communities. Energy Policy
2011;39(2):877–86.
[15] Rehman Shafiqur, Alam MdMahbub, Meyer JP, Al-Hadhrami Luai M. Feasibility
Acknowledgement study of a wind–pv–diesel hybrid power system for a village. Renew Energ
2012;38(1):258–68.
Special thanks to construction company ENET S.A. for funding [16] Underwood CP, Ramachandran J, Giddings RD, Alwan Z. Renewable-energy
clusters for remote communities. Appl Energy 2007;84(6):579–98.
the presented work. [17] Ibrahim H, Younes R, Ilinca A, Dimitrova M, Perron J. Study and design of a
hybrid wind–diesel-compressed air energy storage system for remote areas.
References Appl Energy 2010;87(5):1749–62.
[18] Hessami Mir-Akbar, Bowly David R. Economic feasibility and optimisation of
an energy storage system for Portland wind farm (Victoria, Australia). Appl
[1] Katsaprakakis DAl, Betzios GCh, Christakis DG. Combined management of wind
Energy 2011;88(8):2755–63.
and water potential in Lesvos island, Anemologia, vol. 34, November–
[19] Varkani Ali Karimi, Daraeepour Ali, Monsef Hassan. A new self-scheduling
December 2005. p. 26–34 [in Greek].
strategy for integrated operation of wind and pumped-storage power plants in
[2] Katsaprakakis DAl, Christakis DG. Renewable energy sources penetration
power markets. Appl Energy 2011;88(12):5002–12.
maximization in Greek islands with the support of pumped storage systems.
[20] Dursun Bahtiyar, Alboyaci Bora. The contribution of wind-hydro pumped
Tehniki Epitheorisi 2008;47(March):26–33 [in Greek].
storage systems in meeting Turkey’s electric energy demand. Renew Sust
[3] Katsaprakakis D, Christakis DG, Kontaxakis K. Introduction of pumped storage
Energ Rev 2010;14(7):1979–88.
system into the existing power production system of crete. Technika Chronika
[21] Caralis G, Rados K, Zervos A. On the market of wind with hydro-pumped
2004;IV(1–2):57–80.
storage systems in autonomous Greek islands. Renew Sust Energ Rev
[4] Katsaprakakis Dimitris Al, Christakis Dimitris G, Voumvoulakis Emmanouel,
2010;14(8):2221–6.
Zervos Arthouros, Papantonis Dimitris, Voutsinas Spiros. The introduction of
[22] Tuohy A, O’Malley M. Pumped storage in systems with very high wind
wind powered pumped storage systems in isolated power systems with high
penetration. Energy Policy 2011;39(4):1965–74.
wind potential. Int J Distrib Energ Resour 2007;3(2):83–112.
[23] Daoutis LG, Dialynas EN. Impact of hybrid wind and hydroelectric power
[5] Katsaprakakis Dimitris Al, Christakis Dimitris G, Zervos Arthouros, Papantonis
generation on the operational performance of isolated power systems. Electr
Dimitris, Voutsinas Spiros. Pumped storage systems introduction in isolated
Power Syst Res 2009;79(10):1360–73.
power production systems. Renew Energ 2008;33(3):67–490.
[24] Power production corporation S.A., Department of insular power plants
[6] Kaldellis JK, Kapsali M, Kavadias KA. Energy balance analysis of wind-based
management. Technical and economic features for the non-interconnected
pumped hydro storage systems in remote island electrical networks. Appl
insular power system in Karpathos–Kasos, Athens; 2009.
Energy 2010;87(8):2427–37.
[25] Katsaprakakis Dimitris Al. Maximisation of wind power penetration in non-
[7] Kapsali M, Kaldellis JK. Combining hydro and variable wind power generation
interconnected power systems. National Technical University of Athens
by means of pumped-storage under economically viable terms. Appl Energy
Doctoral Thesis; March 2007.
2010;87(11):3475–85.
[26] Slootweg JG, Kling WL. The impact of large scale wind power generation on
[8] Anagnostopoulos John S, Papantonis Dimitris E. Pumping station design for a
power system oscillations. Electr Power Syst Res 2003;67(1):9–20.
pumped-storage wind-hydro power plant. Energy Convers Manage
[27] Papathanassiou Stavros A, Boulaxis Nikos G. Power limitations and energy
2007;48(11):3009–17.
yield evaluation for wind farms operating in island systems. Renew Energ
[9] Anagnostopoulos JS, Papantonis DE. Simulation and size optimization of a
2006;31(4):457–79.
pumped–storage power plant for the recovery of wind-farms rejected energy.
[28] Hatziargyriou N, Papadopoulos M. Consequences of high wind power
Renew Energ 2008;33(7):1685–94.
penetration in large autonomous power systems. In: Proceedings of CIGRÉ
[10] Dursuna Bahtiyar, Alboyaci Bora. The contribution of wind-hydro pumped
symposium, September 18–19, 1998, Neptum, Romania.
storage systems in meeting Turkey’s electric energy demand. Renew Sust
[29] Hiratsuka Akitaka, Arai Takashi, Yoshimura Tsukasa. Seawater pumped-
Energ Rev 2010;14(7):1979–88.
storage power plant in Okinawa island, Japan. Eng Geol 1993;35(3–4):237–46.
[11] Katsaprakakis D, Christakis DG. A wind parks, pumped storage and diesel
[30] Deane JP, Ó Gallachóir BP, McKeogh EJ. Techno-economic review of existing
engines power production hybrid system for the power production in
and new pumped hydro energy storage plant. Renew Sust Energ Rev
Astypalaia. In: Proceedings of EWEC conference & exhibition, 27 February–2
2010;14(4):1293–302.
March, 2006, Athens, Greece.

You might also like