Professional Documents
Culture Documents
MAI 05 - Final Inspection and Testing - DJ - v1
MAI 05 - Final Inspection and Testing - DJ - v1
1. PURPOSE
The purpose of this procedure is to describe the method to be used to ensure that all works upon
completion have been inspected and tested and all non-conformances have been resolved satisfactorily.
2. SCOPE
This procedure shall apply to all works on the Project site which are under the supervision of PMM
(including work by direct labor and contractors).
The procedure shall apply to overall completion of the works as defined under the Contract.
The procedure shall apply to all goods, materials and equipment once these items have been installed in
their final position in the building.
3. TERMINOLOGY
Punch list: a listing recording details of items of the works which may be damaged, defective, missing,
dirty or incomplete.
QA : Quality Assurance
SE : Site Engineer
4. REFERENCES
5. ACTIONS
5.1 General
5.1.1 Final inspection includes inspection and, where specified, testing which is directed towards ensuring
that the completed works (either a part of the works defined in the Contract Documents, i.e. phased
completion, or the entire works) comply with specified requirements.
5.1.2 Final inspection activities shall include systematic checks of the following:-
5.1.3 When required by the Contract, the Client’s systems for preparing punchlists may be incorporated into
or replace this procedure provided that PMM is represented when the punchlists are being prepared
and agreed.
QUALITY MANAGEMENT PROCEDURES
Doc. No.: MAI 05
Rev. No.: A
FINAL INSPECTION AND TESTING Date: 01 September 2019
Page: 3 of 7
IDENTIFY DEFICIENCIES
PREPARE PUNCHLISTS
(3)
RECTIFY DEFICIENCIES
NO
INSPECTION
SATISFACTORY? O
YES
FILE RECORDS
(7)
HANDO
VER
Flowchart
Activity Documentation Responsibility
Item No.
1 DEVELOP PROGRAMME AND
RESPONSIBILITIES FOR PUNCHLISTING
ACTIVITIES
Develop a punchlisting programme Punchlisting Nominated
identifying by headings the breakdown of Programme Project Staff / QA
the Project into the areas to be punchlisted Coordinator
Punchlisting
Nominate Project staff members responsible Punchlisting Manager in
for punchlisting activities Programme charge of Project
Flowchart
Activity Documentation Responsibility
Item No.
8 COLLATE AND CHECK QUALITY
ASSURANCE RECORDS FOR COMPLIANCE
Notes:
a) Where possible, the punchlist should be prepared in conjunction with the approving organization (e.g.
Client, Engineer)
(b) Sufficient provision shall be made by the custodian to store documents in the filing system. Typically the
provisions shall consist of clearly labeled and sub-divided lever arch files.
Documents shall be placed within each file in a consistent and predetermined manner (using either
registration numbers placed on the document, dates and / or file subdivisions) to allow efficient
retrieval.
(c) Concurrent with punchlisting, the Quality Assurance Coordinator shall check and collate all quality
records to ensure conformance with Contract requirements.
Previously completed Quality Records Registers, other registers and similar used to monitor inspection
and test status may be used by the Quality Assurance Coordinator to readily check the availability of
records verifying that Inspection and Test Plan requirements have been complied with.
(d) The Quality Assurance Coordinator shall prepare a list of outstanding records still considered necessary
to obtain and provide the list to the respective Project staff member responsible for obtaining the
outstanding records.
Deficiencies identified during the check of records may be treated as punchlist items and recorded on the
appropriate punchlist. The items may then be controlled and signed off similarly to other punchlist items.
QUALITY MANAGEMENT PROCEDURES
Doc. No.: MAI 05
Rev. No.: A
FINAL INSPECTION AND TESTING Date: 01 September 2019
Page: 6 of 7
COMMENCEMENT OF MAINTENANCE
PERIOD
DEFECTS IDENTIFIED BY
CLIENT
(2)
COMMENCEMENT OF MAINTENANCE
PERIOD
RE
CTIFY DEFECTS
NO
INSPECTION
SATISFACTORY?
YES
6. ATTACHMENTS