CENTRLINE DISTANCE 56.

00
NO OF T JUNCTIONS 8
RCC STRUCTURE
Measurements
S.No Detail of work(Description) No Unit Quantity Total Remarks
Length Breath Height/Depth
Total Length of center Line 56.00

1 Excavation in Foundation 1 50.80 1.3 1.3 M3 85.85 85.85 50.8

2 Cement Concrete in foundation 1 50.90 1.3 0.3 M3 19.85 50.9

3 Cement CONCRETE IN Columns 14 0.25 0.25 5.1 M3 4.46


(ABOVE GROUND LEVEL) 4 0.25 0.25 2 M3 0.50 4.96

4 CEMENT CONCRETE IN BEAMS M3 4.06 4.06

M3 `
4 Brick work in Superstructure Gr. Fl. 1 55 0.25 2.85 M3 39.19 39.19 55

5 2ND FLOOR BRICKWORK 1 10.7 0.25 2 M3 5.35 5.35


SLAB SIDE WALL 1 31.1 0.25 0.5 M3 3.89 3.89

6 Deduction for
Opening for Door D1 3 1 0.25 2.03 M3 1.52
Opening for Door D2 2 1.1 0.25 2.03 M3 1.12
2ND FLOOR DOOR 1 1 0.25 2 M3 0.50
OPENING 1 1.3 0.25 2.85 M3 0.93
Opening for Window W1 5 1.8 0.25 1.2 M3 2.70
Opening for Window W2 3 0.9 0.25 1.2 M3 0.81
VENT 1 0.6 0.25 0.6 M3 0.09 39.0225

TOTAL DEDUCTIONS 7.67


49.78
7 EARTH FILLING
DRAWING ROOM 1 3.5 3 0.25 M3 2.63
BEDROOM 1 4 3 0.25 M3 3.00
KITCHEN 1 3 2.5 0.25 M3 1.88
TOILET 1 2.2 2 0.25 M3 1.10
DINING 1 3.6 3.3 0.25 M3 2.97
STAIRCASE HALL 1 4 2 0.25 M3 2.00
PASSAGE 1 2.25 1.1 0.25 M3 0.62
VERANDAH 1 3 1.5 0.25 M3 1.13
TOTAL 14.19
8 STAIR CASE CONCRETE 20 0.9 0.25 0.15 M3 0.68

LANDING CONCRETE 1 2.6 1.3 0.15 M3 0.51

SLAB CONCRETE 1 90.52 0.15 M3 15.33

H1 6.85
H2 2.3
H3 3.3
H4 4.1
H5 3.3
H6 6.35
H= 26.2

V1 6.55
V2 8.25
V3 4.3
V4 2.5
V5 8.2
V= 29.8