Professional Documents
Culture Documents
GP 43-47-Pipeline Commissioning and Handover To Operations
GP 43-47-Pipeline Commissioning and Handover To Operations
GP 43-47-Pipeline Commissioning and Handover To Operations
GP 43-47
Applicability Group
Date 28 September 2005
GP 43-47
BP GROUP
ENGINEERING TECHNICAL PRACTICES
28 September 2005 GP 43-47
Guidance on Practice for Pipeline Commissioning and Handover to Operations
Foreword
This is the first issue of Engineering Technical Practice (ETP) BP GP 43-47. This Guidance on
Practice (GP) is not derived from any heritage documents.
Copyright 2005, BP Group. All rights reserved. The information contained in this
document is subject to the terms and conditions of the agreement or contract under which
the document was supplied to the recipient’s organization. None of the information
contained in this document shall be disclosed outside the recipient’s own organization
without the prior written permission of the Director of Engineering, BP Group, unless the
terms of such agreement or contract expressly allow.
Page 2 of 20
28 September 2005 GP 43-47
Guidance on Practice for Pipeline Commissioning and Handover to Operations
Table of Contents
Page
Foreword.......................................................................................................................................... 2
Introduction...................................................................................................................................... 5
1. Scope...................................................................................................................................... 6
2. Normative references.............................................................................................................. 6
3. Terms and definitions.............................................................................................................. 6
4. Symbols and abbreviations.....................................................................................................7
5. Commissioning scope............................................................................................................. 7
6. Commissioning planning......................................................................................................... 8
6.1. General........................................................................................................................ 8
6.2. Roles and responsibilities.............................................................................................9
7. Pre-line fill activities...............................................................................................................11
7.1. General...................................................................................................................... 11
7.2. Completions documentation.......................................................................................11
7.3. Interim Right of Way surveillance and integrity monitoring.........................................11
7.4. Operating manuals.....................................................................................................12
7.5. Operations and maintenance staff training.................................................................12
7.6. Emergency response systems...................................................................................12
7.7. Emergency exercise...................................................................................................12
7.8. Voice communications...............................................................................................13
7.9. Spares, repair equipment, and support contracts.......................................................13
7.10. Temporary commissioning facilities............................................................................13
7.11. Pipeline operation scheduling systems.......................................................................13
7.12. Notification to regulatory and fiscal authorities...........................................................13
7.13. Third party notifications (landowners).........................................................................14
7.14. Product accounting systems.......................................................................................14
7.15. Tax authorities/insurers..............................................................................................14
8. Line fill activities.................................................................................................................... 14
8.1. Line fill prerequisites...................................................................................................14
8.2. Risk assessment........................................................................................................15
8.3. Initial condition........................................................................................................... 15
8.4. Selection of first fill product and line fill methodology.................................................15
8.5. Soak test.................................................................................................................... 17
9. Post line fill activities............................................................................................................. 18
9.1. Handover process......................................................................................................18
9.2. Functional testing.......................................................................................................18
9.3. Emergency exercise...................................................................................................20
9.4. ESIA verification.........................................................................................................20
Page 3 of 20
28 September 2005 GP 43-47
Guidance on Practice for Pipeline Commissioning and Handover to Operations
Page 4 of 20
28 September 2005 GP 43-47
Guidance on Practice for Pipeline Commissioning and Handover to Operations
Introduction
Commissioning of a pipeline system follows the same general principles applied to any other process
plant. However, with the geographically dispersed nature of a pipeline and its associated facilities, the
diverse range of potential interfaces and interested third parties introduces a number of additional
factors that shall be addressed to ensure safe commissioning.
Page 5 of 20
28 September 2005 GP 43-47
Guidance on Practice for Pipeline Commissioning and Handover to Operations
1. Scope
This GP provides guidance on practice for the commissioning of pipelines and their subsequent
handover to the operator for ongoing operations.
2. Normative references
The following normative documents contain requirements that, through reference in this text,
constitute requirements of this technical practice. For dated references, subsequent amendments to, or
revisions of, any of these publications do not apply. However, parties to agreements based on this
technical practice are encouraged to investigate the possibility of applying the most recent editions of
the normative documents indicated below. For undated references, the latest edition of the normative
document referred to applies.
BP
GP 32-20 Guidance on Practice for Site Inspection, Testing, and Precommissioning
of New Plant.
GP 43-04 Guidance on Practice for QA/QC for Pipeline Projects.
GP 43-06 Guidance on Practice for Responsibilities of a Pipeline Operator.
GP 43-24 Guidance on Practice for GIS and Mapping.
GP 43-46 Guidance on Practice for Pipeline Pressure Testing and Pre-
commissioning.
GP 43-49 Guidance on Practice for Pipeline Integrity Management Systems.
GP 43-53 Guidance on Practice for Pipeline Intervention and Repair.
GP 48-01 Guidance on Practice for HSSE Review of Projects.
For the purposes of this GP, the following terms and definitions apply:
Commissioning
The range of activities after pre-commissioning to allow introduction of hydrocarbon or process fluid
and electrical power to prime movers to prepare the pipeline for handover to the pipeline operator to
assume normal operations
Commissioning Authority
The single point of authority responsible for managing the commissioning process and handover of the
pipeline system to the Operator
Handover
The processes enabling the transfer of responsibility for the pipeline asset from the project team to the
pipeline operator to assume ongoing operations
Mechanical Completion
The status of the pipeline system and associated mechanical, electrical, control, and instrumentation
systems at completion of pre-commissioning activities
Operator
The organisation assigned the role described in GP 43-06 that is normally responsible for leading the
management of pipeline commissioning
Page 6 of 20
28 September 2005 GP 43-47
Guidance on Practice for Pipeline Commissioning and Handover to Operations
Pre-commissioning
The range of activities (as described in GP 43-46) carried out by the project team to demonstrate the
completion status and structural integrity of the pipeline before introduction of hydrocarbon or process
fluid
Project
The organisation tasked with constructing and delivering the pre-commissioned pipeline asset ready
for commissioning
For the purpose of this GP, the following symbols and abbreviations apply:
QA Quality Assurance
QC Quality Control
5. Commissioning scope
a. The commissioning and handover process addressed by this document shall only
commence on successful completion of the range of activities described in GP 43-46 and
successful completion of a pre-commissioning PHSSER review in accordance with
GP 48-01.
b. Pipeline pre-commissioning and commissioning activities shall be carried out and
documented in accordance with GP 32-20.
c. Commissioning and handover of a pipeline system shall include, but not be limited to the
following:
1. Filling of the pipeline with hydrocarbon or process fluid.
2. Verifying the integrity and correct functioning of mechanical components including,
valves, valve actuators, flanges, pumps, pig trap end closures, etc.
3. Verifying the integrity and correct functioning of electrical components and power
supplies including motors, switchgear, transformers, etc.
4. Verifying the integrity and correct functioning of offshore and subsea components of
the pipeline system.
5. Calibration and functional verification of instrumentation.
6. Verification of the correct functioning of control systems and instrumentation
including the SCADA system, data communications system, local control facilities,
plant protective devices, and shutdown systems, etc.
Page 7 of 20
28 September 2005 GP 43-47
Guidance on Practice for Pipeline Commissioning and Handover to Operations
6. Commissioning planning
6.1. General
a. Planning for commissioning shall be considered throughout a pipeline project lifecycle
from early conceptual work (CVP Appraise/Select phases) through detailed design (CVP
Define/Execute phases) to ensure that necessary permanent and temporary facilities are
incorporated to facilitate safe and efficient commissioning.
b. The commissioning planning process shall be carried out in close cooperation with and
involvement of the pipeline operator.
c. The planning process shall deliver a comprehensive commissioning and handover plan
covering as a minimum the following key areas.
1. Overall management plan, procedures, and schedule for commissioning activities.
2. Detailed man-power plan including definitions of roles and responsibilities.
3. Regulatory and Permit to Operate (PTO) considerations.
4. Detailed procedures for functional verification of the various parts of the facilities.
5. Detailed procedures for filling the pipeline with fluid.
6. Mechanisms for recording the results and progress of the commissioning of the
facilities.
7. Lists of materials, consumables, spares, equipment, documentation, procedures, and
other resources necessary for safe and efficient commissioning of the pipeline.
8. Definition of interfaces, resources. and facilities required from third parties including
platforms, refineries, terminals, utilities, suppliers, etc.
9. Description of measures to ensure the safety of the general public and personnel
involved in commissioning.
10. Description of incident and emergency response plans for use during commissioning.
11. Communications systems and procedures.
12. Consideration of the impact of the commissioning process of any adjacent plant or
facilities.
Page 8 of 20
28 September 2005 GP 43-47
Guidance on Practice for Pipeline Commissioning and Handover to Operations
13. Consideration of the transition from construction work permit processes to operator
managed permit to work systems.
14. Identification of key risks and measures to mitigate or eliminate risk.
d. The commissioning plan and procedures shall be developed and be in place sufficiently in
advance of commencement of commissioning to allow procurement of any long lead time
items or key support contracts (e.g. oil spill response equipment/contracts, pipeline repair
equipment, safety support vessels, inspection equipment, etc.).
6.2.1. General
a. The commissioning planning process shall produce a clear definition of roles and
responsibilities for those parties contributing to the commissioning process.
b. The Operator shall be assigned a prominent role in both the planning and execution of
commissioning activities.
c. The Operator should be responsible for preparing both commissioning procedures and
normal operations manuals albeit that the overall coordination of the commissioning
process is normally carried out under the execution management framework applied by the
project team.
6.2.6. Partners
The commissioning planning processes shall identify the role and any requirements for input
from BP partners in the project that may influence the overall pipeline commissioning process.
Page 9 of 20
28 September 2005 GP 43-47
Guidance on Practice for Pipeline Commissioning and Handover to Operations
7.1. General
a. The following sections define the range of activities that shall be completed prior to
allowing introduction of first line fill product.
b. The commissioning planning process shall identify key systems, documents, facilities,
permitting, and services that need to be confirmed to be in place before commencement of
commissioning activities and introduction of process fluids.
Page 10 of 20
28 September 2005 GP 43-47
Guidance on Practice for Pipeline Commissioning and Handover to Operations
b. Pressure of the inerting fluid in the pipeline shall be monitored between pre-
commissioning and line fill to confirm that no breach of containment occurs before
introduction of process fluids.
c. This key operational duty shall precede normal handover of responsibility to the Operator
and shall be specifically identified and allocated during the handover from pre-
commissioning to commissioning.
Page 11 of 20
28 September 2005 GP 43-47
Guidance on Practice for Pipeline Commissioning and Handover to Operations
Page 12 of 20
28 September 2005 GP 43-47
Guidance on Practice for Pipeline Commissioning and Handover to Operations
c. Approved operating and maintenance procedures and management systems have been
established for the pipeline and associated facilities, and operating personnel are trained
and experienced.
d. Communications systems are in place and tested across the whole of the pipeline system.
e. Emergency procedures, personnel, vessels, and equipment are in place to deal with
accidental loss of fluid from the pipeline, discovery of a defect or damage to the pipeline,
or any other emergency affecting the pipeline.
f. A Management of Change (MOC) process is in use.
g. Approved commissioning and handover procedures are in place in full compliance with
gHSSEr.
h. Peer Reviews and PHSSER findings have been addressed and risk mitigation measures
taken to give BP full assurance that commissioning can safely commence.
8.4.1. General
a. The selection of first fill product and fill methodology shall form a key part of the risk
assessment outlined in clause above.
b. In pipelines transporting a range of products, options may be exercised to make a selection
that significantly reduces safety risks or product contamination risks associated with the
line fill process.
c. If permanently installed process pumps or compressors are used to propel line fill fluids,
operation shall take place within the specified operating envelope for the unit.
d. No permanent damage shall be introduced to seals or rotating shafts due to temporary
process operating conditions or presence of abnormal levels of contaminants.
e. The need for further cleaning of the pipeline and its components in addition to that
performed immediately after pipeline installation shall be considered particularly if there
Page 13 of 20
28 September 2005 GP 43-47
Guidance on Practice for Pipeline Commissioning and Handover to Operations
8.4.2. Liquid/liquid
a. Liquid/liquid line fill methodology in which a liquid process fluid displaces a liquid pre-
commissioning inerting fluid may be encountered when there is a short period between
hydro-test and line fill and hydro-test water is left in the pipeline and water contamination
of the process fluid is not an issue.
b. Line fill procedure in this case, shall specifically address:
1. Receipt, storage, and disposal of pre-commissioning water, meeting gHSSEr and
ESIA requirements.
2. Impact of passing test water through downstream processing equipment or filters or
sprung pipe hangers designed for lighter hydrocarbon service.
3. Potential for exceeding pipeline MAOP due to increased static head from higher
density water.
4. Receipt and disposal of the water/product interface.
5. Insertion of a separating pig between the process fluid and displaced test water.
c. The location of any discharge point for displaced test water shall be reviewed with respect
to groundwater hydrology, environmental impact, or impact on water courses to confirm
that the discharge rate and water quality will have minimum impact on the surrounding
environment.
Page 14 of 20
28 September 2005 GP 43-47
Guidance on Practice for Pipeline Commissioning and Handover to Operations
8.4.4. Gas/gas
a. Line fill procedure shall particularly address the venting of displaced gas and initial flaring
of the gas interface, the objective to be to minimise or ideally prevent flaring.
b. If the pre-commissioning completion condition provides a pipeline containing air and the
interface of air with the process fluid would create an explosive mixture then a volume of
inert gas shall be inserted to form the interface with the process fluid.
c. In general, procedures shall address the key areas identified in 8.4.3 above.
Page 15 of 20
28 September 2005 GP 43-47
Guidance on Practice for Pipeline Commissioning and Handover to Operations
9.2.1. General
a. In addition to the pre-commissioning tests, functional testing shall be implemented
following line fill to confirm that the overall pipeline system can be operated in accordance
with the design, operating, and maintenance (O&M) philosophy and operations manuals.
b. The initial priority should be on the calibration and testing of the key instrumentation,
process isolation, and emergency shutdown valves required to maintain the safety and
structural and operational integrity of the pipeline system.
c. A detailed test plan shall be defined before commencement of testing with clear test
procedures and acceptance criteria.
d. The test plan shall be approved by the Operator. A suitable senior operator’s representative
shall be identified for sign off of test results.
e. Due to the geographically dispersed nature of most pipelines test plans shall address the
processes to provide a centralised record of test status for all sites to ensure potential
interaction of tests is fully understood.
f. Protective devices including safety critical instrumented systems shall be confirmed and
recorded as fully functional and calibrated before commencement of any pipeline function
tests.
9.2.2. Start-up
Functional test to confirm that the pipeline can be successfully started up in accordance with the
operations manuals shall be carried out.
9.2.3. Shutdown
Functional test to confirm that the pipeline can be successfully and safely shut down in
accordance with the operations manuals shall be carried out.
Page 16 of 20
28 September 2005 GP 43-47
Guidance on Practice for Pipeline Commissioning and Handover to Operations
Page 17 of 20
28 September 2005 GP 43-47
Guidance on Practice for Pipeline Commissioning and Handover to Operations
Page 18 of 20
28 September 2005 GP 43-47
Guidance on Practice for Pipeline Commissioning and Handover to Operations
Page 19 of 20
28 September 2005 GP 43-47
Guidance on Practice for Pipeline Commissioning and Handover to Operations
Bibliography
BP
[1] GP 06-32 Guidance on Practice for Cathodic Protection of Onshore Pipelines.
Page 20 of 20