Professional Documents
Culture Documents
Major Work Handled Which Best Illustration Our Qualificatons
Major Work Handled Which Best Illustration Our Qualificatons
TRANSLATION
KINGDOM OF SAUDI ARABIA
Ministry of Water and Electricity
Finance & Administration Affairs
Tenders & Purchasing dept.
Ref: 1214/24l1430
To: Regional Manager – Aitah – Nespak Engineering Consultant Co.
Al-Salam-Alaikum,
Reference to your offer no. A N/ASK/2 dated 13.4.1430 for the project for supervision of water.
Transmission line from Khulas/ Raabigh Dams to Jeddah (1st stage) in Makkah Region.
You are hereby awarded the work to supervise the captioned project: according to the terms and
specifications stipulated in the TOR.
Your total remuneration for the project shall be SR. 16,296,300. The supervision work shall have
to be completed in (36) months from the date of issue of this latter of award.
You are requested to co-ordinate with project Execution department and refer to tenders
Department to sign the contact within ten, (10) days from the date of issuance of this letter. A
bank guarantee of (%5) of the total value for (40) month from the data of signing of the contract,
shall have to be submitted to you.
Best regards.
Name of project : Water Transmission from Hali, Country : Kingdom of Saudi Arabia (KSA)
Yabah, Qanuna, Al-Laith Dams to Al-Shuaibah (All
Phases)
Project Location within County: Makkah Region Professional Staff provided by NESPAK: 9 No. Of
Man - Months: 780 (324+456)
Name of Client : Ministery of Environment, Water Project Cost:
and Agricultural USD 585.03 million (Rs. 78,070.33 Million)
Name of Financing Agency: Government of KSA
Starting Time: April Completion Time: Consultancy Fee:
2010 December 2019 USD 6.09 million (Rs. 812.15 Million)
Name of Associated Firm(s) if any: No. of Man-Months of Professional Staff provided
AITAH Consulting Engineering, KSA by Associated Firm (s): None
Job No.
PROJECT: Construction Supervision Project for
Transmission of Water from Hate-Yabah-
Qnuna-Al Laith Dams to Al-shoaiba in Makkah
Al-Mukarmah Region (Ph-1), KSA
PHASE-VIII, DHA
Yours Sincerely
For National Engineering Services Pakistan & Partners LLC
This is to certify, in accordance with Conditions of contract, that the Distribution Network in
Nakhal, Awabi & Wadi , Al-Maawi Wilayats for all eight areas Abyad, Taww, Lajal, Mahani,
Hubra, Nakhal, Awabi and stall has been automatically completed and has satisfactory passed
the final test as prescribed in the contract. The contractor has given undertaking to complete all
the outstanding and remedial works (snags included in substantial handing over report) within
the Defect Liability Period (365 days).
13 October 2013
Dear Sir,
TENDER 2/2013 – CONSULTANCY SERVICES FOR DESIGN AND SUPERVISION OF
ROADS AND INFRASTRUCTURE IN THE TOEN OF DUQM (PAKAGE 1)
LETTER OF ACEPTANCE
We refer of SEZAD, we are pleased to inform you that SEZAD is awarding the above tender to
NESPAK & Partners LLC as Consulting Engineer to carry out the consultancy and supervision
services.
The budget of SEZAD, we are pleased to be awarded is Rial Omani one million two hundred and
seventy five thousand four hundred five and basis thirty six only (OMR 1275405036).
The award is subject to validity of the submitted tender bond.
The duration of completion as per the tender:
Study and Preliminary Design stage and preliminary cost-twelve (12) weeks;
Detailed (final) design stage and detailed cost estimate – ten (10) weeks;
Presentation of complete sets of tender documents and tender cost estimate- two (2)
weeks and construction supervision – twenty four (24) months.
Commencement date of the contract shall be confirmed after singing of the contract
agreement.
The compliance requirement with omanizat on as stipulated in the tender is to be strictly adhered
to.
For contractual administration purpose, we would require a meeting with NESPAK & Partners
LLC to confirm the full understanding of the scope of words and required contractual obligation
(such as Project Schedule, staff Organization and personnel, etc.)
Kindly be available for a meeting with our Technical/Project team on: thu/31 Oct 2013, time
propose 1:00 PM.
SULTANATE OF OMAN
Second Edition
March 1987
Form of Agreement
This agreement made on the 21st day of December 2014 between the government of the Sultanate
of Oman, represented by SPECIAL ECONOMIC ZONE AUTHORITY AT DUQM (SEZAD)
(hereinafter called “the client”) of the one part and NATIONAL ENGINEERING SERVICES
PAKISTAN & PARTNERS LLC (NESPAK) (hereafter called “the consulting Engineer) whose
Registered office is at BOX P.O 3506, Postal Code 112, Ruwi, Sultanate of Oman of the other
part.
Whereas the client is desirous that consultancy services be rendered in accordance with the
conditions of Agreement as contained herein in accordance with the condition of agreement as
contained herein and the consulting Engineer is willing and capable to render the said services
and has submitted on offer and the client has accepted the same for following:
Project/s: CONSULTANCY SERVICES FOR DESIGN AND CONSTRUCTION
SUPERVISION OF ROADS AND INFRASTRUCTUREIN TOWN OF DUQM
(Package 1)
NATIONAL ENGINEERING
SERVICES PAKISTAN & PATNERS LLC
PO Box 3506, Ruwi Postal Code 112
Sultanate of Oman
(Tel:24799482; Fax: 24703702)
Attn: Nauman Ul-Haq, Regional Manager
Dear Sir,
TENDER 2/2013- CONSULTANCY SERVICES FOR DESIGN AND SUPERVISION OF
ROADS AND INFRASTRUCTURE IN THE TOWN DUQM (PACKAGE 1)
Subject: Order to commence and Rick off Meeting
We refer to the above tender and SEZAD’s letter of Acceptance dated 13 th October 2013
followed up by our meeting of the 4th November 2013.
By this letter, SEZAD instructs (being client’s Order to commence) NESPAK to commence the
work/services.
A project Kick-off Meeting will be held on Wednesday, 11 December 2013 9:00AM at SEZAD
Muscat Office, in the say (conference) Room.
For the kick off meeting, SEZAD request a presence of NESPAK project Manager and key
personnel that will be employed for that project.
SEZAD require NESPAK to prepare two request for Proposal (RFP); one for the Topographic
Survey and another for the Soil investigations. Please coordinate with SEZAD Contact and
Tender Department to finalize these RFP’s to be ready for approval during the kick off Meeting.
The actual date of the signing of the Contract Agreement will be separately advised by SEZAD.
Following is the proposed kick off Meeting agenda; however SEZAD reserves the right to
modify it before the meeting.
Project Kick off Meeting Agenda
1. Introduction
2. Project objectives
3. SEZAD Project Management Team.
4. NESPAK’s Project Team Members and organization Structure
5. The project schedule and /or programme.
6. The scope of work/service of the project.
7. The work/service Methodology
8. NESPAK’s authorized signatories.
9. The reporting and Meeting Schedules (at office or site) during the project site.
10. Payment’s Application procedure’
11. Quality Control
12. Environmental health and safety.
13. Permits and no Objection Certificate.
14. Request for proposal for Topographic Survey and Soil Investigation.
15. Environmental Impact Assessment (EIA)
16. Any other matters.
PROJECT INTERCHARDE
Special Economic Zone Authority Duqm
Sultanate of Oman
Fax: 24587400
Yours truly,
For National Engineering Services Pakistan and Partners LLC
NATIONAL ENGINEERING
SERVICES PAKISTAN & PATNERS LLC
PO Box 3506, Ruwi Postal Code 112
Sultanate of Oman
(Tel:24799482; Fax: 24703702)
C.R No: 1/60268, Email: nespak@omantel.net.om
Ref: Nespak/Mct/KHJ/121/448-18
On the behalf of special Economic Zone Authority at DUQM (SEZAD), we ae pleased to inform
you that SEZAD confirms to award the above tender, in response to your proposal/offer
submission in E tendering system on 01st May 2018, and hereby accepted by SEZAD Tender and
Contract as detailed below:
Contract Value: OMR 1,218,243.143
(Omani Rial One Million Two Hundred Eighteen Thousand Two Hundred
Forty Three, Bz 143/1000 only)
Contract Period: Mobilization Period = Thirty (30) calendar days
Construction Period = Seven (07) Months
Maintenance Period = Twelve (12) Months
Contract Dates: Commencement date : 22nd Feb 2019
Completion Date :21st Sep 2019
Employer’s Engr. Julius Pasia (Project In Charge PIC) / Mobile: +(968) 9928578
Representative Engr. Saif AlAmri (2nd Project In Charge 2PIC) / Mobile : +(968)
98055076
All future communication, co-ordination and /or liaison for this contract shall be through the PIC
and/or 2PIC and there shall be no direct communication and/or instrument from others.
Kick-off Meeting Date, time & venue: Tuesday /29 Jan 2019; 01.00 PM, SEZAD HQ, Duqn.
The award is subject to validity of the submitted Bid Bond, and as per the tender requirements,
you are requested to prepare and submitted the Performance Bond, Advance Bond / Guarantee
for advance payment and all essential insurance Policies (in compliance to the Tender and
Contractual requirements).
This LOA shall notwithstanding the yet-to-be signed contract Agreement, constitutes a binding
agreement for your commencement as per above; the commencement date being 22nd Feb 2019.
SEZAD Tenders and contract will advise separately on signing the Contract Agreement.
In addition, the attached ANNEXURES shall form part of this LOA, and shall be effective on
acceptance of this LOA.
a) Annexure – Kick off Meeting Agenda.
b) Annexure – Partnership and Development Department (PDD) Requirements.
c) Annexure – Environmental Assessment and Permits
d) Annexure – HSE Policy
Yours Sincerely,
CEO, SEZAD
Cc: Tatweer (Acting Sr. Manager)
SEZAD (GM Corporate Services)
SEZAD (GM Planning and Engineering)
SEZAD (GM One Stop Shop)
SEZAD (Manager, Environment Dept)
SEZAD – PDD and Tatweer – HSSE
NESPAK – Consultant/Engineer
MAJOR WORK HANDLED WHICH BEST
ILLUSTRATES OUR QUALIFICATION
Name of Project: “EIA, Design Review and Resident Country: Pakistan
Supervision for Provision of Clean Drinking Water, Sewerage
System, PCC of Streets and Allied Facilities in Various Areas
of Lahore.
Project Location within country: Lahore Professional Staff Provided
Name of Client: Water and Sanitation Agency (WASA), by our company: 12
LDA, Lahore. No. of Man – Months :216
Name of Financing Agency: Govt. of Punjab
Starting Date: Completion Date: Project cost: Rs 4500 Million
January, 2017 June, 2021 Consultancy Fee: Rs
75.661M
Name of associated firm(s) if any:- No of Man-Months of Professional Staff provided
by Associated Firm(s):-
Senior Staff involved and Functions Performed:
1. Mr. Muhammad Zubair Project Advisor
2. Mr. Khalid Mahmood Project Manager
3. Mr. Ahmad Hamdan Design Engineer
4. Mr. Muhammad Ikram Kakar Resident Engineer
Detailed Narrative Description of the project and services Provided:
Water and Sanitation Agency (WASA), Lahore has initiated a project for provision of physical
infrastructure by replacement of defective and outlived water supply, sewerage system and
provision of PCC in the congested areas of Lahore to meet the present and future requirements
for efficient and effective service delivery.
Brief scope of work include:
Review of WASA proposals and preliminary Engineering Design of the works.
Environmental Impact Assessment study.
Supervision of all construction activities of the project spread in different areas of
Lahore.
Detailed Description of Actual Services provided by NESPAK:
A brief of Service to be provided by NESPAK at the project included:
Design review of water supply and sewerage system proposed by WASA.
To supervise the works as per approved construction drawings and specifications.
To ensure quality testing of all construction materials according to establishment
criteria.
To advise and maintain proper safety measures at site.
Make recommendation to client regarding variation statements, claims, time extensions
of contractors.
Approval of material sources, shop drawings, construction methodologies.
Verify the contractor’s IPCs.
Monitoring of overall progress of project with respect to approved work plan.
EIA study.
WATER AND SANITATION AGENCY
(LAHORE DEVELOPMENT AUTHORITY)
M/S NESPAK
Add: I-C, Block N, Model Town Extension, Lahore
Tel: 92-42-99090000
Fax: 92-42-99231926, 99231950
Rawalakot:
The earthquake left Rawalakot city totally collapsed in terms of administrative and
institutional setup, NESPAK was engaged (ERRA) to develop a Master Plan for Municipal
area of Rawalakot. The Master Plan has 25 years plan period. To know the – condition various
census surveys were also conducted. On the basis of approved final Master Plan various short
term and long term projects were identified. Later, NESPAK also provided Infrastructural
(roads, water supply, sewerage, supervision Consultancy services for Rawalakot City
Development Projects.
M. Tahir
General Manager
NESPAK (Pvt) limited.
Islamabad.
Subject: SIGNING OF GENERAL CONSULTANCY AGREEMENT
Dear Sir:
The competent Authority has approved and signed the general Consultancy Agreement with
NESPAK. One original set complete in all respect is enclosed --- for your reference, record and
future use. Whereas the other original set has been kept with the ERRA.
Thanking you
Amendment 2 (Regarding Construction
Supervision of City Development Projects)
EARTHQUAKE RECONSTRUCTION AND REHABILATION AUTHORITY
(ERRA)
SCOPE OF WORK
AMENDMENT NO.02
TO
CONTRACT
Between
EARTHQUAKE RECONSTRUCTION AND REHABILATION AUTHORITY
And
National Engineering Services Pakistan (Pvt) Limited
For
GENERAL CONSULTANCY TO ERRA
FOR
RECONSTRCUTION AND REHABILATION OF EARTHQUAKE AFFECTED
AREAS
MAY 2009
Scope of work
For
General Consultancy Agreement
Amendment No. 2
URBAN DEVELOPMENT
Client’s Acknowledgement Regarding
Involvement of NESPAK in Various City
Development Projects of Earthquake
Affected Areas
Performance Certificate Issued by NESPAK
To Various Contractors for various Sub-
Project on Client’s Request
NATIONAL ENGINEERING SERVICES PAKISTAN (PVT) LIMITED
Disaster Management & Reconstruction Division
2777/334/AA/5 2.2/
M/s CXB
C/o EA MCDP Muzaffarabad
AZAD JAMMU & KASHMIR URBAN DEVELOPMENT PROGRAME
Muzaffarabad City Development Project-AJK
Lungerpura Bridge & Access Road, District Muzaffarabad
Issuance of Performance Certificate for
With reference to your letter No. FZX-LBA-1710427 dated November 10 2017, and the
employer’s letter No MCDP/2018 dated January 22. 2018 enclosed please find performance
Certificate (in original) for the subject Project as per Sub-Clause 11.9 of CoC.
PERFORMACE CERTIFICATE
Pursuant to the provision of Sub-Clause 11.9 of the Condition of Contract. The Engineer hereby
certificates that the Defects Notification Period for whole of the works has expired on September
25.2017 and that M/s China Xinjiang Beixin Construction & Engineering (Group) Co. Ltd the
contractor for the construction of the subject Project has completed his obligation to execute and
complete the work and remedied all defects to the satisfaction of the Engineer.
NATIONAL ENGINEERING SERVICES PAKISTAN (PVT) LIMITED
Disaster Management & Reconstruction Division
PERFORMACE CERTIFICATE
Pursuant to the provision of Sub-Clause 11.9 of the Condition of Contract. The Engineer hereby
certificates that the Defects Notification Period for whole of the works has expired on November
21.2017 and that M/s CXB the contractor of the Construction the subject Project has completed
his obligation to execute and complete the work and remedied all defects to the satisfaction of
the Engineer.
NATIONAL ENGINEERING SERVICES PAKISTAN (PVT) LIMITED
Disaster Management & Reconstruction Division
M/s CXB
C/o EA BCDP Bagh
PERFORMACE CERTIFICATE
Pursuant to the provision of Sub-Clause 11.9 of the Condition of Contract. The Engineer hereby
certificates that the Defects Notification Period for whole of the works has expired on September
29.2017 and that M/s CXB the contractor of the Construction the subject Project has completed
his obligation to execute and complete the work and remedied all defects to the satisfaction of
the Engineer.
NATIONAL ENGINEERING SERVICES PAKISTAN (PVT) LIMITED
Disaster Management & Reconstruction Division
M/s CXB
C/o EA BCDP Bagh
PERFORMACE CERTIFICATE
Pursuant to the provision of Sub-Clause 11.9 of the Condition of Contract. The Engineer hereby
certificates that the Defects Notification Period for whole of the works has expired on June
29.2017 and that M/s CXB the contractor of the Construction the subject Project has completed
his obligation to execute and complete the work and remedied all defects to the satisfaction of
the Engineer.
NATIONAL ENGINEERING SERVICES PAKISTAN (PVT) LIMITED
Disaster Management & Reconstruction Division
2778/334/AA/5.2.2
M/s CXB
C/o EA BCDP Muzaffarabad
PERFORMACE CERTIFICATE
Pursuant to the provision of Sub-Clause 11.9 of the Condition of Contract. The Engineer hereby
certificates that the Defects Notification Period for whole of the works has expired on October
06.2017 and that M/s China Xinjiang Beixin Construction & Engineering (Group) Co. Ltd the
contractor for the construction of the subject Project has completed his obligation to execute and
complete the work and remedied all defects to the satisfaction of the Engineer.
MAJOR WORK HANDLED WHICH BEST
ILLUSTRATE OUR QUALIFICATIONS
Name of Project: Quetta Water Supply and Environmental Country: Pakistan
Improvement Project (QWSEIP)
Project Location Within Country: Quetta Professional staff provided by our
Name of Client: Project Management Unit Government of Company: 50
Baluchistan, Pakistan. No of Man – Months: 1.290
Name of Financing agency: Federal Government & Government
of Baluchistan.
Starting Date: Completion Date: Cost of Project:
November 23, 2004 April, 2015 PKR 17052 Million
Value of Services:
PKR 265.00 Million
Name of Associated Firm (s) if any= None No of Man-Months of Professional Staff
provided by Association Firm(s): None
Senior Staff involved and Functions Performed:
1. Mr. MP Aftab Project Advisor
2. Mr. Muhammad Iqbal Malik Project Team Leader
3. Mr. Iftikhar Ali Group Leader
4. Mr. Tariq Masood Ansari Project Coordinator
5. Mr. Malik Iftikhar Ahmed Senior Engineer
6. Dr. Tahir Hayat Geotechnical Expert
7. Mr. Abdul Khaliq Hashmi Hydrological Expert
8. Dr. Mansoor Hashmi GIS Expert
9. Mr. Tariq Manzoor MIS Expert
Detailed Narrative Description of the Project:
The project was commended in December 2004 on the directive of the then Chief Executive of Pakistan. The
objectives of the project were to develop and utilize all possible water resources, both surface and underground, in
and around Quetta to meet the water requirements.
Projects comprises of the following components:
Rehabilitation of water supply Pipe lines.
Replacement of Shallow tube Walls
New Tube well in Hard Rock.
Laying of New Conduction and Description Water Pipe lines
Construction of Ground and Elavated Water Tanks.
Laying of Sewerage System
Construction of waste water treatment plans.
Rehabilitation of storm Water drainage channels (Nullahs)
Enhancement of Ground Water Recharge Measures.
Detailed Description of Actual Services provided by NESPAK:
Detailed Design for Rehabilitation and expansion of existing water supply network and reservoir
capacity, wastewater disposal and construction of recycling plants, enhancement of recharge measures, and
refurbishment for existing tubewells.
Other components of the project are construction the of WASA building, development of (GIS), Consumer
survey. Revenue Generation measures and awareness campaign regarding water conservation.
Construction Supervision.
PROJECT MANAGEMENT UNIT
QUETTA WATER SUPPLY & ENVIROMENTAL IMPROVEMWNT
PROJECT
2.6 MOBILIZATION
After signing of the agreement with client, the consultants will depute nominated team of
professionals who will be working on the said project and will mobilize the project to start the
project activities. Each key personnel will be assigned specific task(s) to be carried out. The
designated Team Leader will be deployed to organize the project activates.
2.7 PROJECT KICK OFF MEETING
At the outset, Project team would arrange a kick-off meeting with the client to better understand
the requirements of Client. It would be more advisable that other stakeholders, if any, may also
attend this kick off meeting.
2.8 RECONNAISSANCE SURVEY OF THE PROJECT AREA
A reconnaissance survey of Project area shall be carried out by Consultant proposed team of
experts comprising Water Treatment Expert, Water Supply Engineers, Hydrologist.
Environmentalist, Sociologist. Surveyors and Economist etc. to have the feel and general idea of
the project area as well as to know the surroundings and existing situations prevailing in the
project area. The team of Professionals will visit the site to perceive, but not limited to. The
following features of the project area:
a. General terrain, geology, and topography of the area:
b. Water source availability
c. Existing infrastructure in the study area: and
d. Existing structures condition in the area;
Collection review and analysis of existing data/reports/drawings and finding of
reconnaissance visit will help in project execution. During the site visit a comprehension plan
will be discussed and finalized with the client for on time completion of all project activities.
The treatment technologies commonly used for the treatment of surface water include;
a) In-line filtration
b) Direct Filtration
c) Conventional Water Treatment (Slow Sand Filtration and Rapid Gravity Filters); and
d) Membrane Filtration
2.18.2 Design Flows
The sizes and specific design factors for minimum, average, and maximum flow conditions of
the major treatment processes and waste handling systems will be determined.
2.18.3 Process Flow Diagram
The schematic process flow diagram for selected technology will be prepared indicating all
treatment units’ equipment for both the primary treatment process and waste handling systems.
2.18.4 Development of Layout Plan of Plant
The layout of plant showing the arrangement of treatment process units and others related
facilities such as Admin Building, Laboratory, Workshop, Staff residences, Chemical Handling
and Storage and water storage with respect to site topography will be prepared.
2.18.5 Development of Hydraulic Profile
The hydraulic profile indicating water levels through the plant components at normal and peak
flow rates, for both the primary treatment process and waste handling system will be prepared.
WPC PHB (1967) West Pakistan Code of Practice for Highway bridges
AASHTO LRFD Bridge Design Specifications, American Association of State Highway and
Transportation Officials.
ACI318-Latest Building Code Requirements for Reinforced Concrete Institute.
ASTM A615 Specification for Deformed and Plain Billet Steel Bars for Concrete
Reinforcement
ASTM C150 Specification for Portland cement.
ASTM C33 Specification for Concrete Aggregate
UBC 1997 Uniform Building Code of USA.
EM USR Relevant Manual of U.S Army Engineer
ACI 350R (Building Code Requirement for Water Retaining Structure)
ASCE 7-10 Minimum Design Loads for Buildings and other Structures.
ACI 371 R-08 Guide for the Analysis, Design and Construction of Elevated Concrete and
other Composite Steel-Structure Water Storage Rank.
Software
The following relevant latest engineering software will be used to carryout analysis of
various components.
a) ETABS (Extended Three Dimensional Analysis of Building System)
b) STAAD PRO ( Structure Analysis and Design Program
c) SAP ( Structural Analysis Program)
d) SAFE ( Slab Analysis Using Finite Element Method)
2.23 ELECTRICAL WOEKS
Electrical Distribution System (0.415/0.23kV) shall be analyzed and load be estimated for
specified CWTPs and allied structure through site surveys and in coordination with relevant
authority for proposing power distribution schemes for the said system.
The optimum electricity distribution plan shall be adopted to keep losses and the voltage profile
within prescribed limits. Cables sizing and panel configuring shall be finalized accordingly. The
services shall also include sizing of transformer/DG Set and LV cables.
The illustration of the same shall also be done as per lux requirements. Energy efficient fixtures
shall be proposed as per international standards.
Design Criteria will be assessed as per project specified requirements and electrical loading
sheets shall be reviewed and finalized accordingly.
The plan/layouts including single line diagram shall be evaluated in consideration with the
specified limits for voltage drop and losses allowed by the relevant power distribution authority
in the project premises.
2.24 MECHANICAL WORKS
2.24.1 Design of Gate Equipment for Intake
The design of new gate equipment for the intake (i.e gate leaf, embedded parts and hoisting
equipment) will be carried out considering simplicity, economic viability, employing best
materials of construction, coating requirement for corrosion protection ensuring long life proper
sealing arrangement to avoid leakages, local and remote operation employing modern
approaches wherever possible depending upon the local conditions. The type of the gate will be
selected for easy operation by one person. All the design loads including dead loads, hydrostatic
loads, wind loads, live loads and frictional forces due to sealing system will be taken into
account. The design will be on the basis of the established design criteria and international
standards i.e. ASME. ASTM, USBR, AISC, DIN, TSGP, SSPC, AWWA, API & HI etc.
Physical Environmental
Ambient Air Quality (NOx, Sox, CO, CO2, PM10, PM2.5 etc)
Prevailing Wind Direction and development of Wind Rose;
Soil and Water Contamination Assessment;
Climate;
Noise Assessment
Topography;
Geology;
Hydrology
Surface Water Drainage and Flooring pattern; and
Visual Pollution.
Ecological Environment
Flora and Fauna:
Vegetation and Forest
Game Reverse
Critical natural habitat;
Wetlands (if any)
Migratory species especially/vulnerable species); and
Aquatic life including fish resources if any)
Socio-Economic Environmental
Population;
Archaeology;
Settlements Distribution
Demographic features;
Community Study and employment opportunities
Stakeholders engagements;
Land use
Transportation and access
Utilities
Traffic load
Labour infux to project area;
Waste management services; and
Other public infrastructures (school, universities, markets, hospitals, shops, libraries,
mosque etc)
Curriculum Vitae
1. Proposed Position : Water Supply Expert / Team Leader
2. Name of Firm Pakistan : National Engineering Services
3. Name of Staff : MUSHTAQ AHMAD
4. Date of Birth : November 1961
5. CNIC No : 35200-1503769-9
6. Academic Qualification : B. Sc. Civil Engineering
Name of institute Year Degree
University of Engineering 1988 B.Sc. Civil Engineering
And Technology, Lahore,
Pakistan
7. Other Trainings
9. RELEVENT EXPERIENCE;
Summary of Activities
Employing Organization Country / Location performed Relevant to the
Duration Title/Position Assignment
Project: Consultancy service for Detailed Feasibility Studies, Detailed Design, Estimation, Tender
Documents and PC-I for Greater Water Supply Scheme, Kotli (Phase-II) Azad Jammu & Kashmir.
January, 2020 to NESPAK (Pvt) Limited Pakistan Activities/Responsibilities:
date General Manager / Responsible for Overall
Project Manager Project Management
coordination with Client
and other specialties
working on the project,
timely completion of all
deliverables including
inception Report, Pre-
Feasibility report Draft
Feasibility Report Final
Feasibility Report,
Preliminary Engineering
Design, Tender documents
and Engineer’s Cost
Estimate related to Design
of water supply system
and water treatment
Plant (Conventional
Surface Water
Treatment) having 12
MGD capacity.
Project: Detailed Design of Jalalpur Irrigation Project (JIP)
February 2019 to General Manager / Team Pakistan Scope of Service comprise
July, 2019 Leader design of water supply,
sewerage, and stormwater
Drainage system, Plumbing
System, Water Treatment
Plant (Slow Sand Filter)
and Wastewater treatment
Plant (Wastewater
Stabilization Ponds) for
PID Staff Colony at Pind
Dadan Khan.
Project: Water Supply to Newly Developed Areas of Bhala Wilayat in Sultanate Oman (Phase II)
June, 2009 to June, NESPAK (Pvt.) Limited Oman Preparation of Water
2009 Principal Engineer Supply Report/ Water
Transmission system, water
Distribution Networks and
Reserviors.
Project: Sinaw Water Supply Project, Sultanate of Oman
August, 2003 to NESPAK (Pvt.) Limited Oman Preparation of water
June, 2009 Principal Engineer/ Transmission System,
Project Manager Water Distribution
Networks and Services
Reservoirs.
Project: Construction Supervision of Transmission System of Nizwa - Manah and Bahla – Hamrah in
Sultanate of Oman.
August, 2003 to NESPAK (Pvt.) Limited Oman As senior water supply
June, 2009 Senior Engineer engineer designed the
following water supply
schemes and prepared
tender documents, cost
estimates
Project: Water Supply to Bahla Wilayat – Phase I, Sultanate of Oman
April 2001 to NESPAK (Pvt.) Limited Oman As senior water supply
August 2003 Senior Engineer engineer designed the
following water supply
schemes and prepared
tender documents, cost
equipment.
Project: Water supply to Al Ghalila Village, Sultanate of Oman
April 2001 to NESPAK (Pvt.) Limited Oman As senior water supply
August 2003 Senior Engineer engineer designed the
following water supply
schemes and prepared
tender documents, cost
equipment.
Project: Water Distribution Network for Sohar
June 1998 to April NESPAK (Pvt.) Limited Oman As senior water supply
2001 Senior Engineer engineer designed the
following water supply
schemes and prepared
tender documents, cost
equipment.
Project: Water Supply ans Sanitary Drainage System for Developed Areas of Al Kharj City, Kingdom
of Saudi Arabia
June, 1991 to NESPAK (Pvt.) Limited Kingdom of As Senior Engineer was
July,1997 Resident Engineer Saudi responsible for the
Arabia preparation of design and
tender documents for water
supply system.
Project: Water Distribution Network for Buraidah & Unaizah Cities, kingdom of Saudi Arabi.
June, 1991 to July, NESPAK (Pvt.) Limited Kingdom of As Senior Engineer was
1997 Resident Engineer Saudi responsible for the
Arabia preparation of design and
tender documents for water
supply system.
EMPLOYMENT RECORD:
Employer National Engineering Services Pakistan (Pvt.) Limited
Position held General Manager
Duration June, 2016 to date
Location Lahore Pakistan
Nature of Assignment Quality Assurance / Design Reports
Activities
As general manager worked on the following projects:
Consultancy Services for detailed Feasibility Studies, detailed design, estimation. Tender
documents and PC-I for Greater Water Supply Scheme, Kotli (Phase-II) Azad Jammu &
Kashmir.
Responsible for Overall Project Management, coordination with client and other
specialties working on the project, timely completion of all deliverables including
inception report, Pre-feasibility report, draft feasibility report, final feasibility report,
preliminary engineering design & PC-4, Detailed Engineering Design, Tender documents
and Engineering cost estimate related to Design of Water supply system and water
treatment plant (Conventional Surface Water Treatment) having 12MGD capacity.
Master Planning and Development of Ziara Town.
Responsibility for preparation of Design Report, Tender Document and PC-1
Feasibility study of present network of Karli Beggar Feeder and Keenjhar Lake and
suggesting measures for Upgradation to enhance water Requirement (1,200 cuses for K-
IV) project) from Keenjhar Lake to Karachi water sewerage board.
Scope of services comprises Population Forecasting & water Demand Calculation for
years 2050, study of water quality Assessment of Keenjhar, Hadero and Haleji Lakes and
Study of impact of combining three lakes (by interlinking or merging them to a single
lake) on the quality of water.
Detailed Design of Jalalpur Irrigation Project (JIP)
Scope of services comprise design of Water Supply, Sewerage and Storm water Drainage
system, Plumbing System. Water Treatment plant and waste water treatment Plant for
PID staff Colony at Pind Dadan Khan.
Engineering design of infrastructure work for Defense Housing Authority (DHA),
Gujranwala Scheme comprising integrated Water Supply System Sewerage and Storm
water Drainage system for housing project at Gujranwala. Responsible for preparation of
design Report, Tender Document and Engineer cost Estimate
Preparation of design report, tender document and engineer cost estimate for the project
tilted as Consultancy Services for Design & Construction Supervision of Model custom
Collectorate Gilgit, Director of CEPEC Transit Trade, E-Facilitation Centre Sost, Transit
Accommodation Sost, Barraks for Customs Sepoys at Sost & Custom Forensic
Laboratory.
Design of water supply and Sewerage System along with water Filtration Plant for
Trimmu Barrage staff colony under the project tilted as “Rehabilitation and Upgradation
of Trimmu
Barrage contract no TPBP/CB-31” encompassing the preparation of design reports,
tender document and engineer cost estimate.
Permanent Reconstruction Works in Miran Shah City Market and Makeen City Market,
North Waziristan Agency, FATA, Pakistan
Activities
As a Project coordinator/ Project Manager in Oman main responsibilities included delivering
technical assistance to design teams, resident engineers and coordination between Clients,
Contactor and Consultants for water supply and sewerage projects in sultanate of Oman.
Collection of pertinent data from the field as well as from various ministries/ agencies, selection
of sites, technical guidance to survey teams.
Water Supply Sector
Water Supply to Newly Developed Areas Bhala Wilayat in Sultanate Oman
The major components are transmission system, high ground service reservoir 1500cu.m
capacity, pumping stations, tanker filing stations and water distribution network of pipe sizes
100mm to 600mm diameter.
Sinaw Water Supply Project, Sultanate of Oman
The major components are transmission system, ground service reservoir 4000cu.m capacity,
pumping stations, tanker filing stations and elevated tanks of 900 cu.m & 700 cu.m capacities
and distribution network of pipe sizes 100mm to 600mm diameter.
Construction Supervision of Transmission system of Nizwa- Manah and Bahla- Hamrah in
sultanate of Oman
The major components consist of Ductile Iron transmission mains of 300 mm diameter of about
15 km high ground services reservoir of 3000cu.m capacity, tanker filling stations.
Sewerage Sector
Design and construction super vision of sewerage network system for Sumail Town-
Dakhilya Region, Sultanate of Oman
The major components comprises 65 Km gravity sewers, two lifting stations, pumping station
and sewage treatment plant of 2500 cu m / day capacity.
Upgrading and Rehabilitation of Sewage Treatment Plant and Sewerage Network System
at Nizwa, Sultanate of Oman
The major components consist of 94 km gravity sewers, seven lifting stations, two main pumping
section and sewage treatment plant of 5600m³ / day capacity.
Upgrading and Rehabilitation of Sewage Treatment Plant and Sewerage Network System
at Buraimi, Sultanate of Oman
The major components consist of 70 km gravity sewers, two lifting stations, one main pumping
section and sewage treatment plant of 3000cum / day capacity.
Upgrading and Rehabilitation of Sewage Treatment Plant and Sewerage Network System
at Sur, Sultanate of Oman
The major components consist of 30 km gravity sewers, two lifting stations, one main pumping
section and sewage treatment plant of 1400cum / day capacity.
Upgrading and Rehabilitation of Sewage Treatment Plant and Sewerage Network System
at Khasab, Sultanate of Oman
The major components consist of 25 km gravity sewers, two lifting stations, one main pumping
section and sewage treatment plant of 1250cum / day capacity.
Sewage Treatment Plant and Sewerage Network System for Misfat Al Abrean Al Hamrah
Wilayat, Sultanate of Oman
The major components consist of 6 km gravity sewers, five lifting stations/pumping section and
sewage treatment plant of 250cum / day capacity.
Activities
Water Distribution Network for Sohar
As senior water supply engineer main responsibilities include design and preparation of tender
document and engineer cost Estimate.
The scope of work include design and construction supervision. The design part included
preparation of preliminary design report, draft and final design report and tender document along
with engineer cost estimate.
Activities
Sewage Treatment Facilities Re-use and disposal of Treated Effluent and other Associated
Work at Ibri- Sultanate of Oman
As Resident Engineer was responsible for construction supervision and verification of payment
to the contractor of sewage treatment plant at Ibri-sultanate of Oman.
The sewage treatment plant consist of stabilization ponds such as anaerobic ponds, facultative
and maturation ponds, reed beds and grassy plots and for disinfection of treated sewage chlorine
contact tank and storage basin. The plant was lined with HDPE liners.
Activities
Water supply and Sanitary Drainage System for Developed Areas of Al Kharj City,
Kingdom of Saudi Arabia
The scope of work included preparation of preliminary design report, Draft & Final Design
Report and tender document along with engineer cost estimate for water supply and sanitary
drainage system for developed areas of Al Khraj City. Main responsibility included the
preparation of design and tender document for water supply system.
Water Distribution Network for Buraidah & Unaizah Cities, Kingdom of Saudi Arabia
The scope of work included evaluation of existing water supply system and integration of
existing system with the proposed distribution network, preparation of preliminary Engineering
Design Report. Main responsibilities was to prepare preliminary Engineering Design Report.
Housing Development Scheme in Punjab District- Pakistan
The scope of work included preparation of preliminary design report, Draft & Final Design
Report and tender document along with engineer cost estimate for water supply and sanitary
drainage system for developed areas of Al Khraj City. Main responsibility included the
preparation of design and tender document for water supply system.
Activities
Worked as Administrative Officer and supervised construction of new building, maintenance of
water supply network in the cantonment.
Activities
Worked on the following projects sponsored Government of Baluchistan, Financed by World
Bank
Ziarat Water Supply Scheme
The assignment included preparation of engineering design and tender document. Main
responsibility was to design the distribution network for Ziarat Town.
Baluchistan Township Water Supply and Sanitation Project
The scope of work included preparation of feasibility and preliminary engineering design Report
along with PC-1 Proforma of water supply facilities for 6 towns namely Hub, Gawadar, Turbat,
Kharan, Mastung and Loralai in addition to sanitation System for 16 towns namely Dera Murad
Jamli, Bellapt, Bhag, Lehri, Mastung, Kuchhalk, Ziarat, Loralai, Kharan, Nokundi, Hub, Turbat,
Gawadar, Pishukan, Ganz and Jiwani. The estimated cost was U.S $100 Million.
Main responsibility was to design the sanitary drainage network for Nokundi Town.
Curriculum Vitae
1. Proposed Position : Water Treatment Engineer
2. Name of Firm Pakistan : National Engineering Services
3. Name of Staff : MAHMOOD AHMAD
4. Date of Birth : November 01, 1972
5. CNIC No : 31101-1665166-9
6. Academic Qualification : B. Sc. Civil Engineering
Name of institute Year Degree
University of Engineering 1995 B.Sc. Civil Engineering
And Technology, Lahore,
Pakistan
7. Other Trainings
9. RELEVENT EXPERIENCE;
Summary of Activities
Employing Organization Country / Location performed Relevant to the
Duration Title/Position Assignment
Project 1:Design & Construction of water Treatment Plant and Water Transmission Lines from
Khulais and Rabigh Dam to Jeddah City
Project 2: Design & Construction of water Treatment Plants and Water Transmission lines from Halli,
Yubah, Qanuna and Al-Laith Dams to Shuaiba Phase-1, Phase-2, Phase-3, Phase-4, Phase,5
October 2009 to National Engineering Kingdom of Saudi Activities/Responsibilities:
2014 Services Pakistan Arabia Posted in Ministry of
(NESPAK) Environment Water and
Team Leader/ Hydraulic Agriculture head office, on
Engineer behalf of NESPAK Saudi
Arabia and as a Team
Leader responsible for
hydraulic and process
design review of the water
treatment plants and cross-
country water transmission
lines, building and road
works within plant site.
Also responsible for
coordination between
Nespak supervision staff,
contractor and the ministry
of Environment, Water and
Agriculture for approval of
Design, drawing and
construction issues,
handing and taking over
process, preparation of
progress reports, project
completion reports and to
deal with other contractual
issues.
Project: Preparation of PC-1 for Provision of Basic Utilities to the three industrial Zones along
Lahore-Sialkot Motorway.
2006-2007 National Engineering Pakistan As a project Manager /
Services Pakistan Team Leader worked on
Project Manager design of infrastructure
facilities involved in the
project. The responsibilities
included planning & design
works and construction
management,
correspondence and
coordination with client,
project planning,
preliminary and detailed
engineering design, cost
estimates, tender document
and PC-1 for this project.
Project: Planning and Design of water supply system of Gujrat city
From 2005 to 2006 National Engineering Lahore Pakistan As a project Manager /
Services Pakistan Team Leader worked on
Project Manager design of water supply
system of Gujrat City. The
responsibilities included
planning & design works
and construction
management,
correspondence and
coordination with client,
project planning,
preliminary and detailed
engineering design, cost
estimates, tender document
and PC-1 for this project.
Project: Design of water supply and sewerage works of International Housing Complex Faisalabad
From 2002 to 2003 National Engineering Faisalabad, Pakistan As a Junior Engineer
Services Pakistan involved in design of water
Junior Engineer supply and sewerage
system.
EMPLOYMENT RECORD:
Employer National Engineering Services Pakistan (Pvt.) Limited
Position held Project Coordinator / Hydraulic Engineer
Duration October 2009 till to date
Location Riyadh, Saudi Arabia
Nature of Assignment Design Review
Posted in Ministry of Environment Water and Agriculture head office, on behalf of Nespak
Saudis Arabia and responsible for hydraulic and process design review of the water treatment
Plants and cross country water transmission lines. Also responsible for coordination between
Nespak supervision staff, Contractor and the Ministry of Environment, Water and Agriculture for
approval of design, drawing and construction issues and have worked on the following projects.