Professional Documents
Culture Documents
Vol. 1 - Main Report (Accompanying Measures)
Vol. 1 - Main Report (Accompanying Measures)
Vol. 1 - Main Report (Accompanying Measures)
Client: Consultant:
Financed by
Implementing consortium
Implementing consortium
The objective of the Accompanying Measures Project (AMP) is to achieve improved capacity
of PLN in strategic and sustainable development and implementation of hydropower projects.
The service was contracted by PLN to a consortium of the German utility Uniper Kraftwerke,
consulting firms GFA Consulting Group and AF-Consult, supported by PT Kwarsa Hexagon.
The overall duration of 42 months is split in five phases with different core activities:
• Phase I: Project Inception and Needs Assessment (3 months)
• Phase II: Theoretical Training – Part 1 (6 months)
• Phase III: Practical Training – Parallel On-the-Job (15 months)
• Phase IV: Theoretical Training – Part 2 (9 months)
• Phase V: Independent Working Phase (9 months)
20 experts are assigned over the duration of 42 months: 8 key-experts (45 person months),
9 pool & backstopping experts (15 months) and 3 national experts (31 months).
Implementing consortium
Knowledge and learning Existing KMS and LMS were identified and assessed, incl.
management systems interviews with involved departments à Volume III
Technical English Courses Started on 15th October with 41 participants and will
continue until 21st December.
Technical Training Modules Proposal for topics and schedule for the first technical
trainings in Phase 2 was developed.
Implementing consortium
Implementing consortium
Implementing consortium
Implementing consortium
è A course schedule (training plan) was developed for Phase II, primarily aiming at providing
a solid basis for subsequent deepened trainings in Phase III (in-the-job) and Phase IV (2nd
theoretical training).
Implementing consortium
Implementing consortium
Implementing consortium
Implementing consortium
Implementing consortium
Implementing consortium
Implementing consortium
• Training of
• Coach staff
• Develop &
pilot course
trainers Roll members
Dev ToT • Train • Training of
• Develop
trainer multipliers out staff
members
• .....
Why ToT?
• sustainability and local ownership: trainers at PLN need to internalize topics
continue provision of the trainings at a later stage without support
• too many: some relevant target groups (e.g. health and safety) are very big à need
for training of trainers for multipliers (limited outreach with eLearning)
• limited project resources: not all relevant target groups can be reached by project
Implementing consortium
Implementing consortium
Implementing consortium
• Since the development of the Project’s ToR (PLN and KfW, 2016) a KMS
was developed for corporate-wide use and a new LMS was rolled out by
CorpU in 2017.
• Both systems were centralised at DIVSTI in the third quarter of 2018,
Assessment coinciding with the start of the Project.
• Numerous meetings were held with DIVSTI, Pusdiklat LMS staff, DIVHCMS
and DIVORG, incl. joint meeting on 02.10.18
• A solid understanding of current IT system infrastructure (SAP HR,
centralization process) and current KMS/LMS was gained.
Implementing consortium
In early 2017 a new LMS has been commissioned by CorpU, covering the
basic requirements of PLN and of the Project. Challenges for the Project to
LMS contribute as the different modules are developed from scratch by inhouse
staff. User requirements appear to be fluctuating and internal time schedule
time is not entirely clear.
è It is suggested that the Project’s IT consultants (K8 or NK08) carries out a mission to assess
further system development in April/May 2019 to re-access options for eLearning in Phase IV.
Implementing consortium
Implementing consortium
Construction phase
• PLTA Jatigede
• PLTA Peusangan
Operational projects
• PLTA Musi
• PLTA Cirata
• PLTA Saguling
• PLTA Jatiluhur
• PLTM Dago Bengkok
All projects are known to the Consultant. For these projects under development or
construction latest reports were received from PLN.
Site visits to these projects are planned for early December 2018.
Implementing consortium
Implementing consortium
Implementing consortium
Implementing consortium