Department of Public Works and Highways (DPWH) : Contract ID Contract Name Location of Contract
Department of Public Works and Highways (DPWH) : Contract ID Contract Name Location of Contract
PARTICULAR %WT IST QUARTER 2ND QUARTER 3RD QUARTER 4TH QUARTER
Submitted by:
Position
Date
Department of Public Works and Highways (DPWH)
Contract ID 21JA0020
Contract Name REPAIR OF DENTAL BUILDING, CAMP DON BASILIO NAVARRO, CALARIAN, ZAMBOANGA CITY
Location of Contract ZAMBOANGA CITY
SUMMARY SHEET
EQUIPMENT RATES MANPOWER Rates MATERIAL COST
Name Rate/Day/Hr Name Rate in PHP Name Unit Price Name Unit Price
Dumptruck 12,000.00 Foreman 500.00 Surveying Instrument Unit 1,000.00 WOODEN FRAMES, DOOR JAMBS set 5,100.00
One Bagger Mixer 500.00 Safety Officer 450.00 Stakes kg 40 WOODEN FLUSH DOORS SQ.M 603.39
Bar Cutter 1,758.00 Skille Laborer 380.00 PPE lot 15,000.00 Door Knobs pcs. 550.00
Welding Machine 337.00 Unskilled Laborer 316.00 First Aid Kit unit 3,000.00 Door Jamb pcs. 1,280.00
Geometric Engineer 700.00 First Aid Medicines lot 5,000.00 Hinge 4x4 pcs. 250.00
Survey Aide 350.00 Barricades and signages lot 10,000.00 2"dia. X 6m GI Pipe SCH.40 pcs. 380.00
Embankment Materials cu.m 650.00 4.5mm THK Fiber Cement Board sq.m 135.24
Cement bags 260.00 Prepainted Metal Panel Ceiling SQ.M 198.00
Sand cu.m 1,435.00 PVC Ceiling sq.m 85.00
Gravel cu.m 1,310.00 4.5mm Fiber Cement Board sq.m 172.24
Reinforcing Steel Bars Grade 40 kgs 40.00 UNGLAZED CERAMIC TILES sq.m. 1,152.25
#16 G.I. Tie Wire kgs 100.00 Adhesive bags 550.00
Ordinary Plywood 1/4"x 4" x 8" pcs. 450.00 Grout kgs. 80.00
Coco lumber bd.ft 105.00 Gloss Latex Paint liters 720.00
Submitted by: Nails kgs. 100.00 Paint Flat Latex liters 560.00
4" CHB pcs. 15.00 Masonry putty liters 165.00
10mm dia. X 6m Rebars pcs. 160.00 Skimcoat liters 115.00
ALUMINUM FRAMED GLASS DOOR SLIDING TYPE SQ.M 7,148.00 PAINT ROLLER pcs. 520.00
Owner/Manager ALUMINUM FRAMED GLASS DOOR SWING TYPE SQ.M 5,890.00 PAINT BRUSH 4" pcs. 65.00
ALUMINUM GLASS WINDOWS, SLIDING TYPE SQ.M 2,950.00 Enamel Flatwall liters 650.00
ALUMINUM GLASS WINDOWS, AWNING TYPE SQ.M 14,785.00 Enamel Semi-gloss liters 675.00
ALUMINUM GLASS WINDOWS, (FIXED TYPE) SQ.M 2,500.00 Red Oxide Primer gal 650.00
Corrugated GI Sheet pcs 690.00 Enamel Paint gal 675.00
GA #26 PL. GI Gutter pcs 550.00 Pre-painted Flashing, GA 24 (0.701 mm) x 2.44m LN.M. 350.00
Roffing Nails kilo 90.00 Pre-painted Gutter, GA 24(0.701 mm) x 2.44m ln.m 351.00
Roof Paint tin 2,400.00 2"x4"x6m C-PURLINS pcs. 450.00
12mm dia. Turnbuckle each 185.00 METAL STRUCURE ACCESSORIES, CROSS BRACING kgs. 120.00
METAL STRUCUTRE ACCESSORIES, SAG RODS kgs. 150.00 4" uPVC Pipe pcs. 2,400.00
DETAILED UNIT PRICE ANALYSIS
ITEM : B.3
DESCRIPTION : PERMITS AND CLEARANCES INCLUDING PROFESSIONAL FEES
Quantity : 1.00
Unit : L.S.
NAME OF EQUIPMENT No. of Unit Unit Unit Rate Total Cost (Pesos)
1
-
-
TOTAL EQUIPMENT COST -
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
Labor -
ITEM : B.5
DESCRIPTION : PROJECT BILLBOARD
Quantity : 2.00
Unit : EA
NAME OF EQUIPMENT No. of Unit Unit Unit Rate Total Cost (Pesos)
1
Equipment
-
-
TOTAL EQUIPMENT COST -
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
Labor -
Foreman 1.00 1.00 500.00 500.00
Skilled Worker 1.00 1.00 380.00 380.00
Unskilled Laborer 1.00 1.00 316.00 316.00
ITEM : B.4(10)
DESCRIPTION : MISCELLANEOUS SURVEY AND STAKING
Quantity : 1.00
Unit : L.S.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E Surveying Instrument 1 5.00 1,000.00 5,000.00
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 5,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Geometric Engineer 1 20.00 700.00 14,000.00
A Survey Aide 2 20.00 350.00 14,000.00
B
O
R
ITEM : B.7(2)
DESCRIPTION : OCCUPATIONAL SAFETY AND HEALTH PROGRAM
Quantity : 1.00
Unit : L.S.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST -
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Safety Officer 1 195.00 450.00 87,750.00
A
B
O
R
-
TOTAL MATERIAL COST 33,000.00
4 Estimated Direct Cost (1 + 2 + 3) 120,750.00
5 Contractor's OCM (10% of 4) 12,075.00
6 Contractor's Profit (10% of 4) 12,075.00
7 Value Added Tax, (5% of 4+5+6) 7,245.00
8 Total Cost (4 + 5 + 6 + 7 ) 152,145.00
9 Unit Cost of Item 152,145.00
ITEM : B.9
DESCRIPTION : MOBILIZATION/DEMOBILIZATION
Quantity : 1.00
Unit : L.S.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E Mobilization and Demobilization 1 L.s. 50,000.00 50,000.00
Q of equipments
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 50,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L
A
B
O
R
ITEM : 801(1)
DESCRIPTION : REMOVAL OF STRUCTURES AND OBSTRUCTION
Quantity : 1.00
Unit : L.S.
ITEM : 803(1)a
DESCRIPTION : STRUCTURE EXCAVATION
Quantity : 6.48
Unit : CU.M.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST -
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 3.00 500.00 1,500.00
A Unskilled Laborers 3 3.00 316.00 2,844.00
B
O
R
TOTAL LABOR COST 4,344.00
ITEM : 804(1)a
DESCRIPTION : EMBANKMENT FROM STRUCTURE EXCAVATION
Quantity : 3.23
Unit : CU.M
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q Dumptruck 1 1.00 12,000.00 12,000.00
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 12,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 7.00 500.00 3,500.00
A Unskilled Laborers 3 7.00 316.00 6,636.00
B
O
R
TOTAL LABOR COST 10,136.00
ITEM : 804(4)
DESCRIPTION : GRAVEL FILL
Quantity : 4.64
Unit : CU.M.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q Dump Truck 1 1.00 12,000.00 12,000.00
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 12,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 4.00 500.00 2,000.00
A Unskilled Laborers 3 4.00 316.00 3,792.00
B
O
R
TOTAL LABOR COST 5,792.00
ITEM : 900(1)c1
DESCRIPTION : STRUCTURAL CONCRETE, CLASS A, 28 DAYS (3000PSI)
Quantity : 7.62
Unit : CU.M.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q One Bagger Mixer 1 8.00 500.00 4,000.00
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 4,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 8.00 500.00 4,000.00
A Skilled Laborer 3 8.00 380.00 9,120.00
B Unskilled Laborer 3 8.00 316.00 2,528.00
O
R
ITEM : 902(1)a1
DESCRIPTION : REINFORCING STEEL (DEFORMED) GRADE 40
Quantity : 336.00
Unit : KG.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E Bar Cutter 1 10.00 1,758.00 17,580.00
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 17,580.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 15.00 500.00 7,500.00
A Skilled Worker 2 15.00 380.00 11,400.00
B Unskilled Worker 2 15.00 316.00 9,480.00
O
R
ITEM : 903(2)
DESCRIPTION : FORMS AND FALSEWORKS
Quantity : 25.00
Unit : SQ.M.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST -
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 15.00 500.00 7,500.00
A Skilled Laborers 2 15.00 380.00 11,400.00
B Unskilled Laborers 2 15.00 316.00 9,480.00
O
R
ITEM : 1046(2)a1
DESCRIPTION : 100MM CHB NON LOAD BEARING WALL (INCLUDING REINFORCING STEEL)
Quantity : 62.74
Unit : SQ.M
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST -
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 10.00 500.00 5,000.00
A Skilled Laborers 3 10.00 380.00 11,400.00
B Unskilled Laborers 3 10.00 316.00 9,480.00
O
R
ITEM : 1007(1)a
DESCRIPTION : ALUMINUM FRAMED GLASS DOOR SLIDING TYPE
Quantity : 14.70
Unit : SQ.M.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST -
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L
A Skilled Laborers 2 7.00 380.00 5,320.00
B Unskilled Laborers 2 7.00 316.00 4,424.00
O
R
ITEM : 1007(1)b
DESCRIPTION : ALUMINUM FRAMED GLASS DOOR SWING TYPE
Quantity : 6.30
Unit : SQ.M.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST -
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L
A Skilled Laborers 1 7.00 380.00 2,660.00
B Unskilled Laborers 2 7.00 316.00 4,424.00
O
R
ITEM : 1008(1)a
DESCRIPTION : ALUMINUM GLASS WINDOWS, SLIDING TYPE
Quantity : 31.48
Unit : SQ.M.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST -
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L
A Skilled Laborers 3 7.00 380.00 7,980.00
B Unskilled Laborers 6 7.00 316.00 13,272.00
O
R
ITEM : 1008(1)c
DESCRIPTION : ALUMINUM GLASS WINDOWS, AWNING TYPE
Quantity : 1.80
Unit : SQ.M
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST -
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L
A Skilled Laborers 1 3.00 380.00 1,140.00
B Unskilled Laborers 2 3.00 316.00 1,896.00
O
R
ITEM : 1008(1)d
DESCRIPTION : ALUMINUM GLASS WINDOWS, (FIXED TYPE)
Quantity : 48.59
Unit : SQ.M.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST -
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 10.00 500.00 5,000.00
A Skilled Laborers 4 10.00 380.00 15,200.00
B Unskilled Laborers 10 10.00 316.00 31,600.00
O
R
ITEM : 1010(1)
DESCRIPTION : WOODEN FRAMES, DOOR JAMBS
Quantity : 9.00
Unit : SET
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST -
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 3.00 500.00 1,500.00
A Skilled Laborers 2 3.00 380.00 2,280.00
B Unskilled Laborers 4 3.00 316.00 3,792.00
O
R
ITEM : 1010(2)a
DESCRIPTION : WOODEN FLUSH DOORS
Quantity : 15.33
Unit : SQ.M.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST -
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 2.00 500.00 1,000.00
A Skilled Laborers 2 2.00 380.00 1,520.00
B Unskilled Laborers 4 2.00 316.00 2,528.00
O
R
ITEM : 1004(2)
DESCRIPTION : FINISHING HARDWARE (LOCKSETS AND HINGES)
Quantity : 1.00
Unit : L.S.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST -
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 2.00 500.00 1,000.00
A Skilled Laborers 1 2.00 380.00 760.00
B Unskilled Laborer 2 2.00 316.00 1,264.00
O
R
ITEM : 1057(6)
DESCRIPTION : RAILINGS (RAMP)
Quantity : 1.00
Unit : L.S.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E Minor Tools 1 3.00 3,500.00 10,500.00
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 10,500.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 7.00 611.92 4,283.44
A Skilled Laborers 2 7.00 443.20 6,204.80
B Unskilled Laborers 3 7.00 342.24 7,187.04
O
R
ITEM : 1027(1)
DESCRIPTION : PLAIN CEMENT PLASTER FINISH
Quantity : 79.00
Unit : SQ.M.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST -
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 5.00 500.00 2,500.00
A Skilled Laborers 2 5.00 380.00 3,800.00
B Unskilled Laborers 2 5.00 316.00 3,160.00
O
R
ITEM : 1003(1)a1
DESCRIPTION : 4.5mm THICK FIBER CEMENT BOARD CEILING ON METAL FRAME
Quantity : 209.01
Unit : SQ.M.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q Minor Tools 1 1.00 5,000.00 5,000.00
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 5,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 8.00 500.00 4,000.00
A Skilled Laborers 3 8.00 380.00 9,120.00
B Unskilled Laborers 6 8.00 316.00 15,168.00
O
R
ITEM : 1003(1)e2
DESCRIPTION : PREPAINTED METAL PANEL CEILING ON METAL FRAME
Quantity : 94.13
Unit : SQ.M.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E Minor Tools 1 1.00 5,000.00 5,000.00
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 5,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 7.00 500.00 3,500.00
A Skilled Laborers 2 7.00 380.00 5,320.00
B Unskilled Laborers 2 7.00 316.00 4,424.00
O
R
ITEM : 1003(1)g2
DESCRIPTION : PVC CEILING ON METAL FRAME
Quantity : 10.28
Unit : SQ.M.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E Minor Tools 1 1.00 5,000.00 5,000.00
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 5,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 3.00 500.00 1,500.00
A Skilled Laborers 1 3.00 380.00 1,140.00
B Unskilled Laborers 2 3.00 316.00 1,896.00
O
R
ITEM : 1003(2)a1
DESCRIPTION : 4.5MM THK FIBER CEMENT BOARD WALL ON METAL FRAME DOUBLE WALL PARTITION
Quantity : 136.77
Unit : SQ.M.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E Minor Tools 1 1.00 5,000.00 5,000.00
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 5,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 10.00 500.00 5,000.00
A Skilled Laborers 2 10.00 380.00 7,600.00
B Unskilled Laborers 4 10.00 316.00 12,640.00
O
R
ITEM : 1003(17)
DESCRIPTION : CARPENTRY AND JOINERY WORKS ( CABINETS)
Quantity : 1.00
Unit : L.S.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E Minor Tools 1 2.00 5,000.00 10,000.00
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 10,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 10.00 500.00 5,000.00
A Skilled Laborers 2 10.00 380.00 7,600.00
B Unskilled Laborers 2 10.00 316.00 6,320.00
O
R
ITEM : 1018(2)
DESCRIPTION : UNGLAZED CERAMIC TILES
Quantity : 30.28
Unit : SQ.M.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E Minor Tools 1 1.00 5,000.00 5,000.00
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 5,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 12.00 500.00 6,000.00
A Skilled Laborers 2 12.00 380.00 9,120.00
B Unskilled Laborers 4 12.00 316.00 15,168.00
O
R
ITEM : 1018(5)
DESCRIPTION : GLAZED CERAMIC TILES
Quantity : 232.00
Unit : SQ.M
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q Minor Tools 1 2.00 5,000.00 10,000.00
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 10,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 15.00 500.00 7,500.00
A Skilled Laborers 2 15.00 380.00 11,400.00
B Unskilled Laborers 4 15.00 316.00 18,960.00
O
R
ITEM : 1032(1)a
DESCRIPTION : MASONRY/CONCRETE PAINTING
Quantity : 195.80
Unit : SQ.M.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST -
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 12.00 500.00 6,000.00
A Skilled Laborers 3 12.00 380.00 13,680.00
B Unskilled Laborers 3 12.00 316.00 11,376.00
O
R
ITEM : 1032(1)b
DESCRIPTION : WOOD PAINTING
Quantity : 600.81
Unit : SQ.M.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST -
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 20.00 500.00 10,000.00
A Skilled Laborers 3 20.00 380.00 22,800.00
B Unskilled Laborers 3 20.00 316.00 18,960.00
O
R
ITEM : 1032(1)c
DESCRIPTION : STEEL PAINTING (ANTI-RUST ON PURLINS)
Quantity : 247.84
Unit : SQ.M.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST -
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 15.00 500.00 7,500.00
A Skilled Laborers 2 15.00 380.00 11,400.00
B Unskilled Laborers 2 15.00 316.00 9,480.00
O
R
ITEM : 1014(1)b2
DESCRIPTION : PREPAINTED METAL SHEETS, RIB TYPE, LONG SPAN
Quantity : 368.50
Unit : SQ.M
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q
U
I
P
M
E
ITEM : 1013(2)a2
DESCRIPTION : FABRICATED METAL ROOFING ACCESSORY, FASCIA/FLASHING
Quantity : 61.22
Unit : LN.M.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q Minor Tools 1 1.00 5,000.00 5,000.00
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 5,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 15.00 500.00 7,500.00
A Skilled Laborers 2 15.00 380.00 11,400.00
B Unskilled Laborers 4 15.00 316.00 18,960.00
O
R
ITEM : 1013(2)b1
DESCRIPTION : FABRICATED METAL, ROOFING ACCESSORY GUTTER
Quantity : 38.70
Unit : LN.M
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q Minor Tools 1 1.00 5,000.00 5,000.00
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 5,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 10.00 500.00 5,000.00
A Skilled Laborers 2 10.00 380.00 7,600.00
B Unskilled Laborers 2 10.00 316.00 6,320.00
O
R
ITEM : 1047(2)b
DESCRIPTION : STRUCTURAL STEEL PURLINS
Quantity : 1,425.29
Unit : kgs.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q Minor Tools 1 1.00 5,000.00 5,000.00
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 5,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 8.00 500.00 4,000.00
A Skilled Laborers 2 8.00 380.00 6,080.00
B Unskilled Laborers 2 8.00 316.00 5,056.00
O
R
ITEM : 1047(3)c
DESCRIPTION : METAL STRUCTURE ACCESSORIES, TURNBUCKLE
Quantity : 28.00
Unit : EACH
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q Minor Tools 1 1.00 5,000.00 5,000.00
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 5,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 8.00 500.00 4,000.00
A Skilled Laborers 2 8.00 380.00 6,080.00
B Unskilled Laborers 2 8.00 316.00 5,056.00
O
R
ITEM : 1047(4)
DESCRIPTION : METAL STRUCURE ACCESSORIES, CROSS BRACING
Quantity : 147.80
Unit : KGS.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q Minor Tools 1 1.00 5,000.00 5,000.00
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 5,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 12.00 500.00 6,000.00
A Skilled Laborers 2 12.00 380.00 9,120.00
B Unskilled Laborers 4 12.00 316.00 15,168.00
O
R
ITEM : 1047(4)
DESCRIPTION : METAL STRUCUTRE ACCESSORIES, SAG RODS
Quantity : 46.22
Unit : kgs.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q Minor Tools 1 1.00 5,000.00 5,000.00
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 5,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 10.00 500.00 5,000.00
A Skilled Laborers 2 10.00 380.00 7,600.00
B Unskilled Laborers 2 10.00 316.00 6,320.00
O
R
ITEM : 1001(5)a
DESCRIPTION : CATCH BASIN
Quantity : 9.00
Unit : EACH
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q Minor Tools 1 1.00 5,000.00 5,000.00
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 5,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 15.00 500.00 7,500.00
A Skilled Laborers 4 15.00 380.00 22,800.00
B Unskilled Laborers 2 15.00 316.00 9,480.00
O
R
ITEM : 1001(8)
DESCRIPTION : SEWER LINE WORKS
Quantity : 1.00
Unit : L.S.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q Minor Tools 1 1.00 5,000.00 5,000.00
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 5,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 7.00 500.00 3,500.00
A Skilled Laborers 2 7.00 380.00 5,320.00
B Unskilled Laborers 4 7.00 316.00 8,848.00
O
R
ITEM : 1001(9)
DESCRIPTION : STORM DRAINAGE AND DOWNSPOUT
Quantity : 1.00
Unit : L.S.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q Minor Tools 1 1.00 5,000.00 5,000.00
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 5,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 7.00 500.00 3,500.00
A Skilled Laborers 2 7.00 380.00 5,320.00
B Unskilled Laborers 4 7.00 316.00 8,848.00
O
R
ITEM : 1001(11)
DESCRIPTION : SEPTIC VAULT
Quantity : 1.00
Unit : L.S.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q Minor Tools 1 1.00 5,000.00 5,000.00
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 5,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 7.00 500.00 3,500.00
A Skilled Laborers 2 7.00 380.00 5,320.00
B Unskilled Laborers 4 7.00 316.00 8,848.00
O
R
ITEM : 1002(4)
DESCRIPTION : PLUMBING FIXTURES
Quantity : 1.00
Unit : L.S.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST -
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 7.00 500.00 3,500.00
A Skilled Laborers 2 7.00 380.00 5,320.00
B Unskilled Laborers 4 7.00 316.00 8,848.00
O
R
ITEM : 1002(24)
DESCRIPTION : COLD WATER LINES
Quantity : 1.00
Unit : L.S.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q Minor Tools 1 1.00 5,000.00 5,000.00
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 5,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 7.00 500.00 3,500.00
A Skilled Laborers 2 7.00 380.00 5,320.00
B Unskilled Laborers 4 7.00 316.00 8,848.00
O
R
ITEM : 1100(10)
DESCRIPTION : CONDUITS,BOXES AND FITTINGS
Quantity : 1.00
Unit : L.S.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST -
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 5.00 500.00 2,500.00
A Skilled Laborers 2 5.00 380.00 3,800.00
B Unskilled Laborers 4 5.00 316.00 6,320.00
O
R
ITEM : 1101(33)
DESCRIPTION : WIRES AND WIRING DEVICES
Quantity : 1.00
Unit : L.S.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST -
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 5.00 500.00 2,500.00
A Skilled Laborers 2 5.00 380.00 3,800.00
B Unskilled Laborers 4 5.00 316.00 6,320.00
O
R
ITEM : 1102(1)
DESCRIPTION : PANELBOARDS WITH MAIN AND BRANCH BREAKERS
Quantity : 1.00
Unit : L.S.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q Minor Tools 1 1.00 5,000.00 5,000.00
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 5,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 7.00 500.00 3,500.00
A Skilled Laborers 2 7.00 380.00 5,320.00
B Unskilled Laborers 4 7.00 316.00 8,848.00
O
R
ITEM : 1103(1)
DESCRIPTION : LIGHTING FIXTURES AND LAMPS
Quantity : 1.00
Unit : L.S.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q Minor Tools 1 1.00 5,000.00 5,000.00
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 5,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 10.00 500.00 5,000.00
A Skilled Laborers 2 10.00 380.00 7,600.00
B Unskilled Laborers 4 10.00 316.00 12,640.00
O
R
ITEM : 1200(13)a
DESCRIPTION : AIRCONDITIONING WINDOW TYPE
Quantity : 1.00
Unit : L.S.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q Minor Tools 1 1.00 5,000.00 5,000.00
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 5,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 10.00 500.00 5,000.00
A Skilled Laborers 2 10.00 380.00 7,600.00
B Unskilled Laborers 4 10.00 316.00 12,640.00
O
R
ITEM : 1202(6)a1
DESCRIPTION : FIRE EXTINGUISHER 10LBS ABC WITH BRACKET
Quantity : 2.00
Unit : SETS
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q Minor Tools 1 1.00 5,000.00 5,000.00
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 5,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 7.00 500.00 3,500.00
A Skilled Laborers 2 7.00 380.00 5,320.00
B Unskilled Laborers 4 7.00 316.00 8,848.00
O
R
ITEM : 1201(8)
DESCRIPTION : WATER TANK INCLUDING FLATFORM (RAINWATER COLLECTOR)
Quantity : 1.00
Unit : L.S.
No. of
NAME OF EQUIPMENT No. of Unit Unit Rate Total Cost (Pesos)
1 Days
E
Q Minor Tools 1 1.00 5,000.00 5,000.00
U
I
P
M
E
N
T
TOTAL EQUIPMENT COST 5,000.00
No. of
Designation of Personnel No. of Unit Unit Rate Total Cost (Pesos)
2 Days
L Foreman 1 7.00 500.00 3,500.00
A Skilled Laborers 2 7.00 380.00 5,320.00
B Unskilled Laborers 4 7.00 316.00 8,848.00
O
R
TOTAL AMOUNT BID: THREE MILLION EIGHT HUNDRED SEVEN THOUSAND FOUR HUNDRED
NINETY THREE PESOS & 82/100 (Php 3,807,493.82)
\ Submitted by:
Owner/Manager
Contract ID : 21JA0020
Contract Name : REPAIR OF DENTAL BUILDING, CAMP DON BASILIO NAVARRO, CALARIAN, ZAMBOANGA CITY
BILL OF QUANTITIES
In words: In words:
In words: In words:
MISCELLANEOUS SURVEY FORTY TWO THOUSAND FIVE HUNDRED FORTY TWO THOUSAND FIVE HUNDRE
B.4(10) L.S. 1.00
AND STAKING EIGHTY EIGHT PESOS PESOS
In words: In words:
OCCUPATIONAL SAFETY ONE HUNDRED FIFTY TWO THOUSAND ONE HUNDRED FIFTY TWO THOUSAND
B.7(2) L.S. 1.00
AND HEALTH PROGRAM ONE HUNDRED FORTY FIVE PESOS FORTY FIVE PESOS
In words: In words:
MOBILIZATION/DEMOBILIZA
B.9 L.S. 1.00 SIXTY THREE THOUSAND PESOS SIXTY THREE THOUSAND P
TION
In words: In words:
FORTY THREE THOUSAND TWO
REMOVAL OF STRUCTURES FORTY THREE THOUSAND TWO HUND
801(1) L.S. 1.00 HUNDRED SEVENTY THREE PESOS &
AND OBSTRUCTION THREE PESOS & 44/100
44/100
In Figures: 43,273.44 In Figures:
THREE HUNDRED TWENTY ONE THOUSAND FOUR HUNDRED THIRTEEN
Sub Total (In words)
PESOS & 40/100
Php
Submitted By;
Position
Name of Bidder
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS (DPWH)
Contract ID : 21JA0020
Contract Name :
REPAIR OF DENTAL BUILDING, CAMP DON BASILIO NAVARRO, CALARIAN, ZAMBOANGA CITY
Location of the Contract : ZAMBOANGA CITY
BILL OF QUANTITIES
EIGHT HUNDRED FORTY FOUR PESOS & FIVE THOUSAND FOUR HUNDRED SE
803(1)a STRUCTURE EXCAVATION CU.M. 6.48
66/100 PESOS & 44/100
In words: In words:
EMBANKMENT FROM NINE THOUSAND FOUR HUNDRED FIFTY THIRTY THOUSAND FIVE HUNDRED TH
804(1)a CU.M 3.23
STRUCTURE EXCAVATION FOUR PESOS & 09/100 & 73/100
In words: In words:
In words: In words:
STRUCTURAL CONCRETE, SIX THOUSAND NINE HUNDRED EIGHTY FIFTY THREE THOUSAND TWO HUNDR
900(1)c1 CU.M. 7.62
CLASS A, 28 DAYS (3000PSI) NINE PESOS & 19/100 PESOS & 68/100
In words: In words:
REINFORCING STEEL TWO HUNDRED TWENTY THREE PESOS & SEVENTY FIVE THOUSAND TWO HUN
902(1)a1 KG. 336.00
(DEFORMED) GRADE 40 87/100 TWO PESOS & 01/100
In words: In words:
TWO THOUSAND ONE HUNDRED FORTY FIFTY THREE THOUSAND SIX HUNDRE
903(2) FORMS AND FALSEWORKS SQ.M. 25.00
SEVEN PESOS & 29/100 PESOS & 30/100
In words: In words:
100MM CHB NON LOAD
ONE THOUSAND ONE HUNDRED TWENTY SEVENTY THOUSAND FOUR HUNDRED
1046(2)a1 BEARING WALL (INCLUDING SQ.M 62.74
TWO PESOS & 63/100 PESOS
REINFORCING STEEL)
In Figures: 1,122.63 In Figures:
Sub Total THREE HUNDRED ELEVEN THOUSAND TWENTY FOUR PESOS & 08/100
Submitted By:
Position
Bidder
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS (DPWH)
Contract ID : 21JA0020
Contract Name : REPAIR OF DENTAL BUILDING, CAMP DON BASILIO NAVARRO, CALARIAN, ZAMBOANGA CITY
BILL OF QUANTITIES
ALUMINUM FRAMED GLASS NINE THOUSAND EIGHT HUNDRED ONE HUNDRED FORTY FOUR THOUSAN
1007(1)a SQ.M. 14.70
DOOR SLIDING TYPE FORTY ONE PESOS & 67/100 SEVENTY TWO PESOS & 69
In words: In words:
ALUMINUM FRAMED GLASS EIGHT THOUSAND SIX HUNDRED FIFTY FOUR THOUSAND TWO HUNDRE
1007(1)b SQ.M. 6.30
DOOR SWING TYPE SIXTEEN PESOS & 80/100 PESOS & 84/100
In words: In words:
ALUMINUM GLASS FOUR THOUSAND FIVE HUNDRED SIXTY ONE HUNDRED FORTY THREE THOU
1008(1)a SQ.M. 31.48
WINDOWS, SLIDING TYPE SEVEN PESOS & 62/100 HUNDRED EIGHTY EIGHT PESOS
In words: In words:
ALUMINUM GLASS SIXTEEN THOUSAND SIX HUNDRED TWENTY NINE THOUSAND NINE HUN
1008(1)c SQ.M. 1.80
WINDOWS, AWNING TYPE FIFTY PESOS & 20/100 PESOS & 36/100
In words: In words:
WOODEN FRAMES, DOOR NINE THOUSAND SIX HUNDRED TWO EIGHTY SIX THOUSAND FOUR HUNDRE
1010(1) SET 9.00
JAMBS PESOS & 88/100 PESOS & 92/100
In Figures: 9,602.88 In Figures:
In words: In words:
ONE THOUSAND ONE HUNDRED
1010(2)a WOODEN FLUSH DOORS SQ.M. 15.33 EIGHTEEN THOUSAND FIFTEEN PES
SEVENTY FIVE PESOS & 17/100
In Figures: 1,175.17 In Figures:
SIX HUNDRED NINETY FIVE THOUSAND FOUR HUNDRED EIGHTY FIVE PESOS &
Sub Total
48/100
Submitted By:
Position
Bidder
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS (DPWH)
Contract ID : 21JA0020
Contract Name : REPAIR OF DENTAL BUILDING, CAMP DON BASILIO NAVARRO, CALARIAN, ZAMBOANGA CITY
BILL OF QUANTITIES
FINISHING HARDWARE TWELVE THOUSAND SIX HUNDRED TWELVE THOUSAND SIX HUNDRED SE
1004(2) L.S. 1.00
(LOCKSETS AND HINGES) SEVENTEEN PESOS & 65/100 & 65/100
In Figures: 12,617.65 In Figures:
In words: In words:
FORTY THREE THOUSAND SIX HUNDRED FORTY THREE THOUSAND SIX HUND
1057(6) RAILINGS (RAMP) L.S. 1.00
SEVENTY EIGHT PESOS & 23/100 EIGHT PESOS & 23/100
In Figures: 43,678.23 In Figures:
In words: In words:
PLAIN CEMENT PLASTER THREE HUNDRED SIXTY FIVE PESOS & TWENTY EIGHT THOUSAND NINE HU
1027(1) SQ.M. 79.00
FINISH 87/100 PESOS & 40/100
In Figures: 365.87 In Figures:
In words: In words:
4.5mm THICK FIBER
THREE HUNDRED SEVENTY ONE PESOS & SEVENTY SEVEN THOUSAND FIVE HU
1003(1)a1 CEMENT BOARD CEILING ON SQ.M. 209.01
07/100 EIGHT PESOS & 68/100
METAL FRAME
In Figures: 371.07 In Figures:
In words: In words:
PREPAINTED METAL PANEL FOUR HUNDRED NINETY THREE PESOS & FORTY SIX THOUSAND FOUR HUND
1003(1)e2 SQ.M. 94.13
CEILING ON METAL FRAME 68/100 PESOS & 98/100
In Figures: 493.68 In Figures:
In words: In words:
PVC CEILING ON METAL ONE THOUSAND TWO HUNDRED THIRTEEN THOUSAND ONE HUNDRED
1003(1)g2 SQ.M. 10.28
FRAME SEVENTY FIVE PESOS & 90/100 & 35/100
In Figures: 1,275.90 In Figures:
In words: In words:
4.5MM THK FIBER CEMENT
BOARD WALL ON METAL FOUR HUNDRED NINETY FIVE PESOS & SIXTY SEVEN THOUSAND SEVEN HUN
1003(2)a1 SQ.M. 136.77
FRAME DOUBLE WALL 60/100 FOUR PESOS & 53/100
PARTITION
In Figures: 495.60 In Figures:
Sub Total (In words) TWO HUNDRED NINETY THOUSAND ONE HUNDRED THIRTY PESOS & 82/100 Php
Submitted By;
Position
Name of Bidder
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS (DPWH)
Contract ID : 21JA0020
Contract Name : REPAIR OF DENTAL BUILDING, CAMP DON BASILIO NAVARRO, CALARIAN, ZAMBOANGA CITY
BILL OF QUANTITIES
CARPENTRY AND JOINERY EIGHTY SEVEN THOUSAND THREE EIGHTY SEVEN THOUSAND THREE HU
1003(17) L.S. 1.00
WORKS ( CABINETS) HUNDRED SIXTY TWO PESOS & 10/100 TWO PESOS & 10/100
In Figures: 87,362.10 In Figures:
In words: In words:
In words: In words:
SEVEN HUNDRED FORTY SIX PESOS & ONE HUNDRED SEVENTY THREE THO
1018(5) GLAZED CERAMIC TILES SQ.M. 232.00
87/100 HUNDRED SEVENTY FIVE PESOS
In Figures: 746.87 In Figures:
In words: In words:
MASONRY/CONCRETE SEVEN HUNDRED TWENTY FIVE PESOS & ONE HUNDRED FORTY ONE THOUSAND
1032(1)a SQ.M. 195.80
PAINTING 08/100 SEVENTY ONE PESOS & 76
In Figures: 725.08 In Figures:
In words: In words:
In words: In words:
STEEL PAINTING (ANTI- TWO HUNDRED EIGHTY TWO PESOS & SIXTY NINE THOUSAND NINE HUND
1032(1)c SQ.M. 247.84
RUST ON PURLINS) 40/100 PESOS & 48/100
In Figures: 282.40 In Figures:
In words: In words:
PREPAINTED METAL
SIX HUNDRED FIFTY FOUR PESOS & TWO HUNDRED FORTY ONE THOUSAN
1014(1)b2 SHEETS, RIB TYPE, LONG SQ.M. 368.85
17/100 PESOS & 20/100
SPAN
In Figures: 654.17 In Figures:
ONE MILLION FIFTY ONE THOUSAND TWO HUNDRED THIRTY THREE PESOS &
Sub Total (In words)
28/100 Php
Submitted By;
Position
Name of Bidder
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS (DPWH)
Contract ID : 21JA0020
Contract Name : REPAIR OF DENTAL BUILDING, CAMP DON BASILIO NAVARRO, CALARIAN, ZAMBOANGA CITY
BILL OF QUANTITIES
In words: In words:
FABRICATED METAL,
ONE THOUSAND TWO HUNDRED FORTY SEVEN THOUSAND TWO HUNDR
1013(2)b1 ROOFING ACCESSORY LN.M. 38.70
TWENTY ONE PESOS & 05/100 PESOS & 66/100
GUTTER
In Figures: 1,221.05 In Figures:
In words: In words:
In words: In words:
METAL STRUCTURE THREE THOUSAND ONE HUNDRED SIX NINE THOUSAND THREE HUNDRED T
1047(3)c EACH 28.00
ACCESSORIES, TURNBUCKLE PESOS AND 88/100 AND 64/100
In Figures: 1,139.22 In Figures:
In words: In words:
METAL STRUCTURE
FOUR HUNDRED FIFTY TWO PESOS & SIXTY SIX THOUSAND EIGHT HUNDRE
1047(4) ACCESSORIES, CROSS KGS. 147.80
03/100 24/100
BRACING
In Figures: 452.03 In Figures:
In words: In words:
METAL STRUCTURE EIGHT HUNDRED FORTY ONE PESOS & THIRTY EIGHT THOUSAND EIGHT HUN
1047(7)b KGS. 46.22
ACCESSORIES, SAG RODS 08/100 FOUR PESOS & 78/100
In Figures: 841.08 In Figures:
In words: In words:
Sub Total (In words) FOUR HUNDRED THOUSAND EIGHT HUNDRED SEVEN PESOS & 62/100 Php
Submitted By;
Position
Name of Bidder
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS (DPWH)
Contract ID : 21JA0020
Contract Name : REPAIR OF DENTAL BUILDING, CAMP DON BASILIO NAVARRO, CALARIAN, ZAMBOANGA CITY
BILL OF QUANTITIES
SIXTY SIX THOUSAND THREE HUNDRED SIXTY SIX THOUSAND THREE HUNDR
1001(8) SEWER LINE WORKS L.S. 1.00
SIXTY ONE PESOS & 68/100 PESOS & 68/100
In Figures: 66,361.68 In Figures:
In words: In words:
STORM DRAINAGE AND SIXTY TWO THOUSAND FOUR HUNDRED SIXTY TWO THOUSAND FOUR HUNDR
1001(9) L.S. 1.00
DOWNSPOUT FORTY NINE PESOS & 38/100 PESOS & 38/100
In Figures: 62,449.38 In Figures:
In words: In words:
FIFTY NINE THOUSAND EIGHT HUNDRED FIFTY NINE THOUSAND EIGHT HUNDR
1001(11) SEPTIC VAULT L.S. 1.00
NINE PESOS & 68/100 & 68/100
In Figures: 59,809.68 In Figures:
In words: In words:
SIXTY SIX THOUSAND THREE HUNDRED SIXTY SIX THOUSAND THREE HUNDR
1002(4) PLUMBING FIXTURES L.S. 1.00
SIXTY ONE PESOS & 68/100 PESOS & 68/100
In Figures: 66,361.68 In Figures:
In words: In words:
In words: In words:
CONDUITS,BOXES AND FORTY SEVEN THOUSAND FOUR FORTY SEVEN THOUSAND FOUR HUND
1100(10) L.S. 1.00
FITTINGS HUNDRED ONE PESOS & 20/100 & 20/100
In Figures: 47,401.20 In Figures:
In words: In words:
WIRES AND WIRING FORTY ONE THOUSAND ONE HUNDRED FORTY ONE THOUSAND ONE HUNDRE
1101(33) L.S. 1.00
DEVICES ONE PESOS & 20/100 20/100
In Figures: 41,101.20 In Figures:
FOUR HUNDRED THREE THOUSAND FIVE HUNDRED FORTY SIX PESOS &
Sub Total (In words)
50/100 Php
Submitted By;
Position
Name of Bidder
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS (DPWH)
Contract ID : 21JA0020
Contract Name : REPAIR OF DENTAL BUILDING, CAMP DON BASILIO NAVARRO, CALARIAN, ZAMBOANGA CITY
BILL OF QUANTITIES
PANELBOARDS WITH MAIN SIXTY SIX THOUSAND THREE HUNDRED SIXTY SIX THOUSAND THREE HUNDR
1102(1) L.S. 1.00
AND BRANCH BREAKERS SIXTY ONE PESOS & 68/100 PESOS & 68/100
In Figures: 66,361.68 In Figures:
In words: In words:
LIGHTING FIXTURES AND SEVENTY FIVE THOUSAND NINE SEVENTY FIVE THOUSAND NINE HUND
1103(1) L.S. 1.00
LAMPS HUNDRED TWO PESOS & 40/100 & 40/100
In Figures: 75,902.40 In Figures:
In words: In words:
AIRCONDITIONING SEVENTY FIVE THOUSAND NINE SEVENTY FIVE THOUSAND NINE HUND
1200(13)a L.S. 1.00
WINDOW TYPE HUNDRED TWO PESOS & 40/100 & 40/100
In Figures: 75,902.40 In Figures:
In words: In words:
FIRE EXTINGUISHER 10LBS TWENTY TWO THOUSAND NINE FORTY FIVE THOUSAND NINE HUNDRE
1202(6)a1 SETS 2.00
ABC WITH BRACKET HUNDRED SIXTY TWO PESOS & 24/100 PESOS & 48/100
In Figures: 22,962.24 In Figures:
In words: In words:
WATER TANK INCLUDING
FIFTY THREE THOUSAND SEVEN ONE HUNDRED SEVENTY TWO THOU
1201(8) FLATFORM (RAINWATER L.S. 1.00
HUNDRED SIXTY ONE PESOS & 68/100 FOUR PESOS AND 00/10
COLLECTOR)
In Figures: 53,761.68 In Figures:
Submitted By;
Position
Name of Bidder
EPARTMENT OF PUBLIC WORKS AND HIGHWAYS (DPWH)
BILL OF QUANTITIES
Amount
(Pesos)
(6)
18,900.00
1,506.96
42,588.00
152,145.00
63,000.00
43,273.44
321,413.40
Date
Page 1 of 8
EPARTMENT OF PUBLIC WORKS AND HIGHWAYS (DPWH)
BILL OF QUANTITIES
Amount
(Pesos)
(6)
5,473.44
30,536.73
22,417.92
53,257.68
75,222.01
53,682.30
70,434.00
311,024.08
Date
Page 2 of 8
EPARTMENT OF PUBLIC WORKS AND HIGHWAYS (DPWH)
BILL OF QUANTITIES
Amount
(Pesos)
(6)
144,672.69
54,285.84
143,788.69
29,970.36
18,015.48
695,485.48
Date
Page 3 of 8
EPARTMENT OF PUBLIC WORKS AND HIGHWAYS (DPWH)
BILL OF QUANTITIES
290,130.82
Date
Page 4 of 8
EPARTMENT OF PUBLIC WORKS AND HIGHWAYS (DPWH)
BILL OF QUANTITIES
1,051,233.28
Date
Page 5 of 8
EPARTMENT OF PUBLIC WORKS AND HIGHWAYS (DPWH)
BILL OF QUANTITIES
81,001.62
416,807.62
Date
Page 6 of 8
EPARTMENT OF PUBLIC WORKS AND HIGHWAYS (DPWH)
BILL OF QUANTITIES
60,061.68
403,546.50
Date
Page 7 of 8
EPARTMENT OF PUBLIC WORKS AND HIGHWAYS (DPWH)
BILL OF QUANTITIES
317,852.64
3,807,493.82
Date
Page 8 of 8
DEPARTMENT OF PUBLIC WORK AND HIGHWAYS (DPWH)
Contract ID : 21JA0020
Contract Name : REPAIR OF DENTAL BUILDING, CAMP DON BASILIO NAVARRO, CALARIAN, ZAMBOANGA CITY
-----------------------------------------------------------------------------------------------------
SUMMARY OF BID PRICES
(All Parts of Bill of Quantities)
GRAVEL FILL
804(4) 22,417.92
1046(2)a1 100MM CHB NON LOAD BEARING WALL (INCLUDING REINFORCING STEEL) 70,434.00
ALUMINUM FRAMED GLASS DOOR SLIDING TYPE
1007(1)a 144,672.69
1003(2)a1 4.5MM THK FIBER CEMENT BOARD WALL ON METAL FRAME DOUBLE WALL PARTITION 67,784.53
Total of All Amounts in words: THREE MILLION EIGHT HUNDRED SEVEN THOUSAND FOUR HUNDRED NINETY THREE PESOS & 82/100
Pesos : 3,807,493.82
Signed : Date :