Professional Documents
Culture Documents
Ugbenyen 2011
Ugbenyen 2011
and after stimulation, and also, reservoir and simple screening module flow chart for this model is
mechanical problems that could cause the treatment to shown in Figure 1.
be unsuccessful.
Development of a Model for Optimizing Stimulation An objective function is defined to maximize the net
Decisions post-stimulation production subject to the limitations
Figure 2 shows the production profile (production rate imposed by the system. Therefore:
vs. time) of a well that at some point during its !! ! !!" ! !!"# ! !!" (1)
producing life was profitably stimulated. This figure
shall serve as the theoretical basis for the model where !!" is the discounted production from
developed in the following sections. The curve ABC stimulation, !!"# is the discounted production loss
represents the well pre-stimulation decline curve from stimulation, and !!" is the discounted production
profile. The well initial production rate is!!! . At point equivalent to total stimulation cost.
B, the well is considered for stimulation. The curve
DEF is the resulting post-stimulation production In Figure 2, let us shift the time axis such that the time
profile. The production rate !! is the abandonment rate at the start of the stimulation job !! is set to zero. Then
of the well. The time !! is the abandonment time of the
let !! be the duration of the stimulation job and !!" be
well if it is not considered for a stimulation treatment.
the abandonment time of the post-stimulation
The stimulation treatment is initiated at time !!
production profile. Exponential decline curve analysis
corresponding to the production rate!!! . At time !! the
is used to derive the mathematical expressions for each
stimulated well is open for production. Thus, the
of the components of Equation 1.
difference between the times !! and !! is the duration of
the stimulation job. The production loss due to the As shown in Appendix A, combining the components
duration of the stimulation job is represented by the of the objective function, Equation 1 can be written as:
shaded area BCHI. The initial production rate after
stimulation is represented by !! which corresponds to !! !!
point D in Figure 2. The well is now produced along ! ! !! ! !!! ! ! !!!! !! !! !! !
the curve DEF until the abandonment rate !! is reached !! !
at time !!" corresponding to point F in the figure !! ! ! !!
!!! !!!! !!
shown. The area DEFH represents the incremental !"! ! ! !
production due to stimulation treatment. The model !
formulated in the following section uses this production
!! ! !
!! !!!! !! !
profile together with exponential decline curve analysis ! ! ! ! ! ! ! !!!! (2)
!!!! !
with economic concept of continuous discounting.
Similar derivations for several cases of hyperbolic
where ! is the total cost of the stimulation treatment in
decline are presented in Ugbenyen (2010) and Sinson et
al (1988). dollars; ! is the exponential decline rate per day; ! is
the stimulation productivity ratio; ! is the effective
Model Assumptions interest (discount) rate per day; and ! is the price (in
The following assumptions are used in the development dollars) per barrel of oil. The stimulation productivity
of the model: ratio, ! is defined as:
1. The stimulation will result in improved !!
!!
(3)
productivity. !!
2. The well could be operated profitably if stimulated. where qs is the production rate after stimulation and q0
3. The factors that control production in the past will is the production rate before stimulation.
continue to control production in the future. Equation 2 is the objective function of the optimization
4. The well production-rate versus time decline model used in this work.
profile is exponential.
5. The well pre-stimulation decline profile will be the
same as the post-stimulation profile. Optimization Model Constraints
To obtain a practical solution to the objective function,
6. The nominal decline rate constant ! is the same
the formulation must include some constraints. In this
for both the pre-stimulation and post-stimulation
paper, a budgetary constraint is imposed such that the
profile.
cost of the stimulation does not exceed the budget as
7. The abandonment rate of the well is the same for
determined by management. Also, a break-even
both the pre-stimulation and post-stimulation
condition is imposed such that the revenue obtained
profile.
from the stimulation is at least equal to the stimulation
cost. The reservoir sets a limit on the maximum
Defining the Objective Function,!!
cumulative production, and existing facilities, both in
the sub-surface and surface, limit production rates that
can be obtained from the stimulation treatment. These
4 Benson O. Ugbenyen, David O. Ogbe and Samuel O. Osisanya SPE 150760
constraints are developed mathematically as presented where !!"# is the maximum productivity ratio that can
below. be obtained given the reservoir and treatment
parameters. It is the productivity ratio obtained from the
1. Break-even Requirement treatment design module discussed above.
The discounted revenue from any stimulation decision
should be greater than or at least equal to the discounted 6. Productivity Improvement Constraint
cost of the project. i.e., The stimulation must, at least, result in an improvement
!!" ! !!"# ! !!" (4) in the productivity ratio and must not itself cause more
damage to the formation. This constraint is imposed on
In a practical sense, this constraint is satisfied if and the productivity ratio such that it must not be less than
only if the value of the objective function !! is one or negative. It can be formulated mathematically
positive, that is, if: as:
! ! !!"# (9)
Maximize:
where !!"# is the maximum budget allocated by
management for stimulation. !! ! !! !! !! !! ! ! ! !! !! !! ! ! !! ! !! !
!!! !! ! ! (13)
higher amount of recoverable oil remaining in the Step 1: Enter each well data given into the Acidizing
reservoir. But a reduced incremental production is Design and Optimization Model and generate the Cost
expected because when the abandonment rate is set versus Productivity-Ratio relationship for each well.
high, the incremental production will be reduced since
Step 2: Obtain the relationship between the stimulation
there is a limit to which the well can produce.
cost (C) and productivity ratio (F) in form of power
Consequently, a reduced incremental production will
equation of a trend line through a log-log regression of
eventually decrease the optimal point of the objective
the data.
function.
For the Well BU 3 input data, the equation is obtained
as shown in Figure 9:
6. Effect of Stimulation Time
The stimulation time represents the duration of time the ! ! !"!!"! !!!"" (28)
stimulation job is performed. The effect of the
stimulation time on the optimal point of the objective Step 3: Use Equations presented in the section titled
function is shown in Figure 8. The optimal point of the “General Form of the Optimization Model” to
objective function lowers as the stimulation time formulate the objective function and its constraints as:
increases. This means that if more time is spent on the Maximize:
stimulation job, the production loss during the duration !! ! !!!!""#!!"!!"# ! !!"#!!" ! !!!"#$!!"! !
of stimulation will increase, and hence, lowers the !!!!"#$! !!!"" ! !"#$!!"#$! (29)
overall benefit derivable from the stimulation job.
Subject to:
1. Break-even Constraint:
Model Application
!!!!""#!!"!!"# ! !!"#!!" ! !!!"#$!!"! !
The optimization model is applied with the acidizing
treatment module to quantify stimulation benefit ! !!!"#$! !!!"" ! !"#$!!"#$ (30)
derivable from four typical acidizing jobs, and also, to
rank the wells for the stimulation process. Production 2. Remaining Reserve Constraint:
data from four wells: Well BU 1, Well BU 2, Well BU 3 !!!"#$! ! !"#$%&!!"# ! !!!"! !!!!
and Well BU 4 were used to validate the model. The (31)
four wells completed in May 2004 are located in
Bestfield, offshore Niger Delta. This high permeability 3. Flow String Capacity Constraint:
field is located in a water depth of 200m. The average ! ! !!!" (32)
peak production recorded in January 2006 from each of
the four wells is 7000 stb/d. Production decline starts 4. Budget Allocation Constraint:
after a 3-year peak production period. The available !"!!"! !!!"" ! !"""""" (33)
production data for each of the four wells shows that
the decline profile for each well is exponential. The 5. Productivity Improvement Constraint:
wells are being considered as potential candidates for
acidizing after a well test confirms the presence of !!! (34)
formation damage. The field data is presented in Table
2. These data served as input data for the acidizing 6. Maximum Formation Productivity Ratio:
design and optimization model. Additional data used ! ! !!!" (35)
were taken from published literature by Ofoh and From the non-linear programming optimization
Heikal (2006), Nnanna et al. (2009), Nnanna and problem presented above it could be seen that, simply,
Ajienka (2005). The data in Table 2 are used to we seek an optimum value for the productivity ratio
formulate the Bestfield Model, which gives an insight which has a lower and upper bound of 1 and 3.21,
into how the model can be used to optimize and rank respectively. This is true because the limit sets by the
acidizing candidates. facility constraints (Equation 32) is more binding than
the maximum productivity ratio attainable given the
In addition, let’s assume that the remaining recoverable reservoir and treatment parameters (Equation 35).
reserve is 500 MM bbl, and the tubing maximum design
flow rate for each well is 12500 stb/d. Also let’s assume It is important to note that the spreadsheet application
an average oil price of $80/bbl, effective discount rate developed for this model will only use the input
of 10% and a maximum acidizing budget of $1200000 parameters to generate the optimization results. Hence,
per well. the steps above are only presented for better
Using these data, the model is formulated. Well BU3 is understanding of how the model and its constraints are
considered for the following analysis. formulated.
7 Efficient Methodology for Stimulation Candidate Selection and Well Workover Optimization SPE 150760
2. For effective use of the model, the lease operating a New HF-Acid System: Case Histories” paper
cost (LOE), federal and state taxes must be SPE 112558 presented at the 2008 SPE
considered before ranking the wells for stimulation. International Symposium on Formation Control,
Lafayette, Louisiana (Feb 13-15).
Acknowledgments
2. Al Qahtani, A., and Al Shehri, D.: “The Ec-Factor:
The authors wish to thank Dr. Ebere P. Ofoh of NPDC A Correlation for Optimizing Completion
for providing the some of the data used for this
Efficiency,” paper SPE 81490 presented at the
research, and Schlumberger Nigeria Limited, for
reviewing the optimization spreadsheet application 2003 SPE Middle East Oil Show, Bahrain (April 5-
developed in this work. 8).
3. Al-Araimi, M., Mahajan, M.: “Successful Revival
Nomenclature of Long-term Closed-in Gas Well by Right Matrix
bbl barrel Stimulation Treatment,” paper SPE 96735
Cmax maximum stimulation budget, $ presented at the 2005 SPE Annual Technical
! decline rate, per day Conference & Exhibition, Dallas, TX (Oct. 9-12).
!!"# maximum productivity ratio 4. Economides, M.J., and Nolte, K.G., Reservoir
! stimulation productivity ratio Simulation, Third Edition. Wiley, N.Y. 2000,
gal gallon
Chapter Eighteen, p. 24-25.
h thickness of the oil sand, ft
I effective discount rate per day, % 5. Jennings, A. R.: “Good Wells Make the Best
! permeability of undamaged zone, md Candidates for Well Stimulation,” SPE Production
!! permeability of damaged zone, md Engineering (Nov., 1991), pp 371-376.
P price per barrel of oil, $ 6. Jones, L. G.: Course Notes, Formation Damage
Pr average reservoir pressure, psi School, Mobil, Duncan, OK (March 1989).
!! well standard flow rate, stb/d 7. Kartoatmodjo, G., Caretta, F., Flew, S., Jadid, M.:
!! ! abandonment flow rate, stb/d
“Risk-Based Candidate Selection Workflow
!!! initial production rate, stb/d
qmax tubing maximum design flow rate, stb/d Improve Acid Stimulation Success Ratio in Mature
!! the production rate, stb/d Field,” paper SPE 109278 presented at the 2007
!! damaged zone radius, ft SPE Asia Pacific Oil & Gas Conference, Jarkata,
!! reservoir drainage radius, ft Indonesia (Oct. 30 to Nov. 1st).
!! wellbore radius, ft 8. Lee, W. J.: Well Testing, Society of Petroleum
ROIP remaining recoverable reserve, bbl Engineers Textbook (1982).
stb stock tank barrel
9. Lindo, 2010: http://www.lindo.com/
!! duration of the stimulation job, days
!! abandonment time, day 10. Nitters, G., Roodhart, L., Jongma, H., Yeager, V.,
!!" abandonment time of the post-stimulation Buijse, M., Fulton, D., Dahl, J., and Jantz, E.:
production, days “Structured Approach to Advanced Candidate
! pressure gradient, psi/ft Selection and Treatment Design of Stimulation
Treatments,” paper SPE 63179, presented at the
Subscripts 2000 SPE Annual Technical Conference and
a abandonment Exhibition held in Dallas, Texas (Oct. 1-4).
d damaged zone 11. Nnanna E., Osuagwu M., and Okereke O.:
i initial condition
“Important Considerations in Matrix Stimulation
max maximum
o oil Candidate Selection in Niger Delta”, paper SPE
r reservoir 128604 presented at the 2009 SPE Annual
s stimulation International Conference and Exhibition, Abuja
(Aug 3-5).
References 12. Nnanna, E; Ajienka, J: “Critical Success Factors
1. Afolabi, A, Opusunju A, Henri J, Onyekwere for Well Stimulation”, paper SPE 98823 presented
Cletus, Onyekwere Chris and Davalos J.: at the 2005 Nigerian Annual Conference &
“Increasing Production in a Brown Field with Exhibition, Abuja (August 1-3).
Heavy Crude and Fines Problem by Application of 13. Ofoh, E. P., and Heikal S.: “Reservoir
Management Optimization through a Systematic
9 Efficient Methodology for Stimulation Candidate Selection and Well Workover Optimization SPE 150760
J+)@*)+<='*C'O2P#@<#3'!@+3' 0:5G'1#'
,-EB'(%<#' /'../0-%2'
N%C#'Q%$&+2'C*$'O2P#@<+*2',$#))-$#' /00'#$%'
1+%E#<#$'*C'R*+8'>-9+2&' 4:G5'%21*&$'
R*)<'*C'!@+3',#$'H2+<'J*8-E#'' S'6T'#&"345/'
!'' 0:M'#$%0'('
R-$$#2<',$*3-@<+*2'(%<#.'67' 4000'$(.0+'
!9%23*2E#2<'(%<#.'65' /00'$(.0+'
UVB*2#2<+%8'1#@8+2#'(%<#.'8' 0:6/'#&"3+59'
1-$%<+*2'*C'N<+E-8%<+*2.3($' /'+59$'
(#E%+2+2&'(#@*"#$%98#'(#)#$"#.':;<!' 6'==3$(.'
,$+@#',#$'W%$$#8'*C'X+8.'!' T03>0$(.'
UCC#@<+"#'1+)@*-2<'(%<#',#$'1%=.'<' 40I'
>-9+2&'Q%V+E-E'1#)+&2'D8*Y$%<#.'6-5?' 40000'$(.0+'
Q%V+E-E'N<+E-8%<+*2'W-3&#<.'@-5?' 4:/'==3>'
12 Benson O. Ugbenyen, David O. Ogbe and Samuel O. Osisanya SPE 150760
Fig. 3: Effect of oil price on the objective function Fig. 4: Effect of discount rate on the objective function
Fig. 5: Effect of decline rate on the objective function Fig. 6: Effect of pre-stimulation production
rate on the objective function
14 Benson O. Ugbenyen, David O. Ogbe and Samuel O. Osisanya SPE 150760
Fig. 7: Effect of abandonment rate on the Fig. 8: Effect of stimulation time on the
objective function objective function
Fig. 9: Cost versus productivity ratio plot for Well BU 3 Fig. 10: Effect of oil price on Well BU 3 model result