3 September Report
3 September Report
3 September Report
Dated 03-08-2020
Overview:
Visited the power plant site and followed the operation and maintenance
activities performed during the day.
Operation Activities:
The complex was operating with a combination of 2+1 minimum load in the
morning.
Last night GT-1 start command was received but GT tripped on alarm
‘exciter not ready to start’.
GT-1 is now in forced outage mode.
GT-2 was in operation.
GT-3 was in operation.
ST was in operation.
Maintenance Activities:
During the day, visited the plant site area and closely observed the maintenance
activities performed by different departments. The maintenance activities
attended are listed below: