01 Method Statement - Installation of Air-Cooled Chillers
01 Method Statement - Installation of Air-Cooled Chillers
01 Method Statement - Installation of Air-Cooled Chillers
BSS-0-GE00-
DOCUMENT HISTORY
Contact Details:
Table of Contents
1.0. General................................................................................................................................................................... 6
2.0. Scope...................................................................................................................................................................... 6
3.0. Purpose................................................................................................................................................................... 6
3.1. Abbreviations.......................................................................................................................................................................6
4.0. References.............................................................................................................................................................. 7
5.0. Definitions.............................................................................................................................................................. 8
6.0. Responsibilities....................................................................................................................................................... 8
6.1. Workflow...........................................................................................................................................................................10
7.0. Materials............................................................................................................................................................... 10
1.0. General
Method Statement for Installation of Air-Cooled Chillers are prepared and controlled by BSS JV in
accordance with project specification and client instructions.
2.0. Scope
This Method Statement describe the methods and standards to be employed in storage,
handling and installation of Air-Cooled Chillers for King Faisal Air Academy project as specified
in the relevant Project Specification Section 15650 – HVAC Air-Cooled Chillers, Approved Shop
Drawings and Material Submittals. The works described in this document will be valid for all
sites within King Faisal Air Academy, AlMajmaah, Saudi Arabia.
The following are covered by this Method Statement:
To establish site execution work plans according to this method statement and comply with
Quality Management, HSE procedure.
Checking the actual condition of specified work activities and coordinate to the contractor
prior starting activities
Establishing and maintain all documents and control data.
Ensuring all records are properly stored, maintained and retrievable when required.
Ensuring all materials is/are complying as per approved specification and approved material
submittal.
Ensure shop drawing to be approved by civil defense before starting the work.
3.0. Purpose
The purpose of generating this method statement is to define the procedures step by step to
implement the correct practices for installation of Air Cooled Chillers(HVAC Equipment) for King
Faisal Air Academy Project, so as to ensure that the job execution complies with the
requirements and serves the intend function to satisfactorily level. As well as the necessary
materials to ensure the health and safety of the employees, making sure to comply with
requirements stipulated in the contract documents.
3.1. Abbreviations
5.0. Definitions
QCP Quality Control Plan evaluate and modify contractor procedures to ensure by providing the
desired results. Quality control plans are often viewed as a set of instructions that should be
followed.
6.0. Responsibilities
Phase Manager is responsible to ensure that adequate manpower, the required materials,
tools, and equipment’s are made available for the works. He shall also ensure that proper
routing and access is provided.
QA / QC Manager is responsible for managing the development and implementation of the
QMS for planning duties within QA/QC staff, inspection, documentation, and operations
activities.
Safety Manager is responsible for monitoring risks and hazards in the workplace and ensuring
the business is legally compliant with all health and safety legislation.
Site Engineer is responsible for ensuring that all application, testing activities are executed in
accordance with the approved shop drawings and specified requirements. He is responsible for
pre-inspection followed by Engineer representative inspection and approval, he ensures that
safety requirements are implemented, and approved Method Statements are followed.
QA/QC Engineer ensure the proper implementation of the quality management system (QMS)
are maintained. conduct inspection and monitor field testing, determine and report any non-
conformance and recommend corrective actions. ensuring that all personnel are aware of the
BSS-0-GE00- Rev: 00 (02/15/2021)
Method Statement for Installation of Air-Cooled Chillers (Rev 0) Page 8 of 24
_____________________________________________________________________________________
6.1. Workflow
7.0. Materials
All the materials received at site should be as per the approved technical material submittal for
chillers to be inspected upon receipt and approved by the engineer prior in proceeding with the
installation. Any discrepancies, damages etc .... , should be reported to the supplier for
rectification or replacement and to be removed from site immediately
All construction preliminary inspection/testing work should be carried out in accordance with
the approved manufacturing drawings, specifications and to be done by Mechanical Engineers
and should be checked and approved by DAR Engineers.
Tool Box complete with hand tools including hammer, wrenches, screw drivers, etc.
Lifting Equipment (Boom Truck / Crane / Manlift / Telehandler / Slings / Ropes / Chain Blocks /
Shackles / Lugs)
Basic Electrical Tools
Measuring Tape
Hack Saw Blade
Electric Drill Machine
Spirit Level
Electrical Grinding Machine
Ladders
Notes:
All tools and equipment shall be functionally safe and checked regularly. Third party certificates
must be available as per approved Safety Plans
All tools and equipment shall be free from any defects before delivery to site.
Mandatory PPE items (safety footwear, helmet, High visibility Vest & Eye protection) are not
included in the above materials. However, PPE kit is mandatory for all site works. Any additional
safety items apart from the standard kit shall be utilized as task dictates and according to Work
Permits and Risk Assessment.
The inspector shall ensure all materials are free from damage. Any damage noted shall be
identified.
Immediate attention investigation shall be made by the material receiving assigned person and
QC Inspector, on materials delivered which have obvious damage to the outer shell or wooden
casing. i.e.: Crates etc.
Ensure that the storage location of the units has solid foundation and vibration free.
It is much recommended not to remove the plastic coverings or packaging materials during the
delivery to avoid any corrosion and deterioration
Ensure that all openings, such as pipe connections, are securely capped.
The condensers should be covered to protect the coils and fins from potential damage and
corrosion, particularly where building work is in progress.
The unit should be stored in a location where there is minimal activity in order to limit the risk
of accidental physical damage.
Avoid any mechanical shocks and strokes during handling operations.
9.2. Prior activities to be completed:
Supervisors shall deliver tool box talk relevant to these activities to staff involved in installation
process.
All staff involved in this installation shall be briefed about this method statement.
All site safety rules and regulations are maintained as per site safety plan and as instructed by
site safety officer. This includes but not limited to;
o Provisions for warning signs, barricades, warning tapes and site lighting as necessary. The
location of the lifting area shall be barricaded/ taped off with warning tape and only
authorized personnel can enter the demarcated zone.
o Lifting plan is in place.
o The lifting operation is conducted in clear weather and accepted wind speed.
o Working area is clean.
o All PPE gear is utilized.
For the crane operation, the following shall be assured to safely control this operation;
o All staff /labor involved in this operation must be qualified for this task and have received
the required induction, training and are 3rd party certified as necessary. All certificates must
be current.
o The crane has a valid 3rd party certificate.
o All tools utilized in this operation are of the correct load rating for the job and are 3rd party
certified as necessary.
Work Clearance is obtained from the civil contractor. Concrete Pads (Plinths) are cast and
approved by DAR.
BSS-0-GE00- Rev: 00 (02/15/2021)
Method Statement for Installation of Air-Cooled Chillers (Rev 0) Page 12 of 24
_____________________________________________________________________________________
Supervisors will deliver tool box talks, relevant to these activities to all operatives involved in
the installation.
All site safety rules and regulation should be complied.
Only competent, experienced and trained personnel should perform all the required activities
stated in this method statement.
During installation, display warning sign boards to be provided and barricade the area
whenever necessary. Close monitoring by the site engineers during installation is much highly
recommended.
Ensure that all operative fully understand the method of these activities.
9.3.1. Preliminary Checks before Chiller Installation
Supervisors will deliver tool box talks, relevant to these activities to all operatives involved
Determine whether the units occur damages during the storage and shifting of location
All relevant approved shop drawings for the installation of the equipment should be available at
the time of Installation
Installation activities should only commence when all concrete pads by the civil has been
completed.
Before commencement of installation activity, the supervisor/ engineer must make sure to
respect minimum distances on all units in order to ensure optimum ventilation to the
condenser coils.
To ensure best performance on the installation site, the following precautions and instructions
must be followed:
o Avoid air flow recirculation.
o Make sure that there are no obstacles to hamper air flow.
o Make sure to provide a strong and solid foundation to reduce noise and vibrations.
o Avoid installation in particularly dusty environments, in order to reduce soiling of
condensers coils.
BSS-0-GE00- Rev: 00 (02/15/2021)
Method Statement for Installation of Air-Cooled Chillers (Rev 0) Page 13 of 24
_____________________________________________________________________________________
Supervisors will deliver tool box talks, relevant to these activities to all operatives involved
Determine whether the units occur damages during the storage and shifting of location
All relevant approved shop drawings for the installation of the equipment should be available at
the time of Installation
Stepwise procedure is illustrated which is typical for all stations
9.3.2.1. Step Wise Illustration for Work Methodology- Elevated
Chiller Location - Roof Level
Step: 1
Lifting & mobilization of chiller shall be as per approved ton capacity crane is used to lift the
chillers from the transit truck to its location as per the shop drawing. Chiller shall be hanged
with the help of Sling belt as per the manufacture’s recommendation.
As shown in the schematics (Step -1), chiller shall be suspended through the accessibility path.
Thereafter it shall be tied to the manual chain hoist with the help of the manlift.
Step: 2
Manual chain hoist shall be hanged to the structural beam as mentioned in the schematics.
Other end of the manual chain hoist shall be clamped to the bottom as shown in the
schematics. chiller is in suspended position. As detailed in the schematics (step-2)
Step: 3
Proper coordination shall be done between the crane and the 4-manual hoist, so that the
chiller shall be pulled inside without placing in the ground. After it is pulled to about 1.4 meters
inside, it shall be placed on the floor level, the crane shall be disengaged from the chiller. As
detailed in the schematics (Step-3)
Step: 4
Hook of the crane shall be repositioned after the supporting beam. After the crane is hooked to
the chiller, manual chain hoist shall be detached from the chiller
Step: 5
Chiller shall be lifted and placed exactly as per the approved shop drawing. After placing the
chiller, hook of the crane shall be disengaged.
Each of the cables (chains or slings), hooks and shackles used to lift the unit must be capable of
supporting the entire weight of the unit.
Lifting cables (chains or slings) may not be of the same length. Adjust as necessary for even unit
lift.
A crane will be used to lift the equipment to its final location. The lifting shall be conducted
using suitable lifting beams, spreader bars and all associated accessories.
The crane operator shall operate under the instruction of a rigger who is positioned as such
that he has a clear and unobstructed view for all the surrounding area.
The lifting area shall be secured with warning tape and only essential personnel may enter in
the demarcation zone.
All personnel within the demarcation zone will function as directed by the rigger. A banksman
can be allocated to control the traffic at the lifting area if necessary.
a. Is everyone aware of and do they fully understand the lifting and hoisting procedures
applicable to the lift?
b. Has everyone attended the toolbox talk?
c. Has a pre-use inspection of the Lifting Equipment been carried out and are the Lifting
Accessories tagged or marked with:
d. Safe Working Load
The Construction Department shall inform the Quality Assurance/Control (QA/QC) Department
of the installation activities by issuing an Field Inspection Request Form (FIR).
When the QA/QC Department is satisfied that the work detailed in the Construction FIR is
completed, they will initiate to DAR.
The Inspector shall verify the installation of work by performing inspections as per the
Inspection and Test Plan (ITP) and shall record his findings on Quality Record (QR). Any defects
noted during the inspection shall be forwarded to the Construction Department (Project
Manager) through an Inspection Report.
The Inspector shall use the QR as a checklist and ensure all points on the checklist are complete.
The QR shall be the quality record document to identify that the inspection has taken place and
the installation is in full compliance with the project.
Verify that the installed unit is free of any visual damages and is installed complete with all
vibration isolators and all connections including pipes and electrical connections as per
approved IFC drawings, specifications and manufacturer's recommendations.
Check clearances provided for service access and air circulation around equipment is
satisfactory as per manufacturer's recommendations.
Check chiller properly piped and pipes are leak tested.
Raise Inspection and Test Request to the Company to get approval for all installations.
All Pre-commissioning works including system flushing, system's purging and refrigerant
charging, etc. must be conducted in accordance to the relevant T&C Method Statement.
Surveillance should be made to monitor the activity for the item installations
Upon completion of installation and inspection has been done with accepted remarks prepare
for testing
Test Report - A certified test report of all data should be forwarded to DAR for approval prior to
project acceptance. Calibration curves and information sheets for all instrumentation should be
provided.
Health and safety training should be provided to personnel for the proper handling of materials
(required Material Safety Data Sheets or MSDS}.
Health and safety training should be provided to personnel in the Control of Substance
Hazardous to Health (COSHH).
Health and safety training should be provided to personnel who will perform work within a
confine space and or hazardous areas.
Health and safety training e.g. on the job training, fire extinguisher training, scaffolds erection
training and first aid training relevant to electrical safety work practices and safety condition
implemented when undertaking installation of Jet Fan.
Conduct Training and supervision of workers in the implementation of electrical safety
procedures to eliminate electrical hazards and electrical risks during the installation of Jet Fan
as per electrical safety training and workplace health and safety training requirements.
11.1. Appendix 1 – HSE Risk Assessment