Professional Documents
Culture Documents
Construction Engineering and Management
Construction Engineering and Management
Construction Engineering and Management
ENGINEERING AND
MANAGEMENT
Group 4
Product
The Product in case of a construction project is the
constructed facility such as a building, a bridge,a highway, a dam,
a canal, a factory etc.
Construction Project
Construction projects involve varying manpower and
their duration can range from a few weeks to more than
five years.
Briefing Stage
Designing Stage
Tendering Stage
Construction Stage
Commission Stage
1. Briefing Stage
This stage is also called the “Report Stage”.
It is the stage where ideas originated
individuals are studied with regard to cost and
benefits so as to establish the economic
viability/social utility of a project.
Purpose
The purpose of the briefing stage is to enable
the client to specify project functions and
permissible costs.
Activities in Briefing Stage
To appoint a project commitee, if necessary.
To appoint a project manager who will have a continuing
responsibility to the client through out the construction
project.
To carry out technical and non-technical investigation so
that alternative proposals may be given dueconsideration.
To study the various alternatives and identify the most
feasibleone.
To prepare the project report which is the outcome of the
firststage.
2. Designing Stage
It is a very important stage in the field of construction because
any modification of the project after this stage would prove
expensive.
A realistic and detailed cost estimate of the project can be
prepared during the designstage.
Purpose
The purpose of this stage is to complete the project summary
and determine the method of construction and estimated costs so
as to obtain necessary approvals from the client.
Activities in Designing Stage
To develop the project summary for the final adoption of the most
suitablealternative.
To carry out technical investigations such as,
◊ Soil investigation
◊ Topographic investigation
◊ Materials surveys
◊ Market surveys
To prepare detailed design, working drawings, specifications, bill
of quantities, final cost estimate and preliminary construction
programme.
3. Tendering Stage
During this stage tenders are invited and the contract is awarded
at the best available terms agreed mutually between the owner’s
team and thecontractors.
Purpose
The purpose of the tendering stage is to appoint a contractor
who will undertake the construction work on the most suitable terms
and conditions of quality, cost and completiontime.
Activities in Tendering Stage
To invite tenders from the contractors for the construction work and to
award thecontract.
Pre-qualification of contractors involves an investigation of the
potential of contractor s financial, managerial and physical resources,
contractor s experience of handling similar projects,etc.
To prepare contract documents,to be signed by the client and
thecontractor.
Holding a pre-bid conference and providing the necessaryinformation.
Negotiating contract price with qualified contractor.
Reviewing documents submitted by contractor.
4. Construction Stage
The construction stage involves the execution of
construction work as per the design, drawing and
within agreed limits of time, cost and specified
quality.
Purpose
The purpose of this stage is to ensure that the construction
work has been carried out as per the drawing and specifications
and all the facilities developed function properly as envisaged
in the design.
Activities in Commission Stage
Economy in Construction
Speed of Construction
It essentially
covers the aspects of
“what to do” and
“how to do it”
SCHEDULING
Scheduling is the
fitting of the final work
plan to a time scale. It
shows the duration and
order of various
construction activities.
It deals with the aspect
of “when to do it”.
Building construction
Infrastructure construction
Industrial construction
► Commercial buildings
► Educational buildings
► Recreational buildings
► Petroleum refineries