Professional Documents
Culture Documents
Appendix - 7: Appendix 7 - Inspection Test Procedure of
Appendix - 7: Appendix 7 - Inspection Test Procedure of
If the specific site conditions differ from the reference conditions the performance
measurements obtained shall be corrected in accordance with the included
equations, prior to being compared to the performance guarantees.
All the performance tests shall be carried out in accordance with this contract.
All functional tests on equipment relevant to the performance test and any system
adjustments must be finished before starting the performance test. Sufficient
operating media must be available and continuously supplied by the EMPLOYER.
The EMPLOYER must secure the power demand of the grid.
The Generating Sets shall have reached normal steady state operation before any
performance tests can begin. Steady state operation is assumed to be achieved
when the variation of power output reaches stability (as defined below) for a period of
15 minutes and the lube oil and facility components have reached thermal stability as
per ISO 15550:2002.
If during the performance test the ambient temperature exceeds the maximum
temperatures stated in the technical specification, test results may not accurately
represent the normal operating performance of the Power Plant. In this circumstance,
the validity of the test results must then be considered by both the customer and
supplier and corresponding correction curve will be applied to calculate the
performance.
Here fluctuation means the difference between the highest and lowest value of a
series of measurements for any single test point compared with the average value
recorded for that test point.
Mass flow meters installed at fuel oil Booster Module shall be used for measurement
and any by-pass valves around these meters must be closed during the test.
Mass flow meters, power meters and other instruments used during the test must
have their calibration certificates or measurement precision declarations checked
before the test. These calibrations should not be older than three year.
During testing, the Generating Sets, Boilers, Turbine are normally operated by the
CONTRCATOR.
A Performance test report shall then be issued stating the operating conditions, the
method and results of all measurements, the equipment used with their calibration
certificates and the results of the fuel analyses.
B.1 General
There will be two separate RRT, one for simple cycle and other for combined cycle.
The Reliability Test Run shall begin first, and requires the Generating Sets to operate
at full capacity for duration of 100 Hrs for Simple Cycle and 100 Hrs for Combined
Cycle, to demonstrate the proper function of all equipment and systems within the
plant, and to prove the reliability of the plant as a whole. The Reliability Test Run and
Dependable Capacity Test with BPDB to fulfill PPA requirement can be done
together while The Contractor will perform the tests with the Employer for Simple
Cycle.
This test shall have been satisfactorily completed if the reliability run continues
without interruption (arising out of factors internal to the Facility) for not less than one
hundred (100) hours. In the event that the reliability run is interrupted for reasons
external to the Facility, the accumulated testing time prior to such interruption shall
be deemed acceptable for testing purposes. The CONTRACTOR shall be required to
carry out the reliability run only for such remaining period after such interruption
ceases and the reliability runs carried out during the period prior to the interruption
and the period after the interruption shall be deemed as one continuous period as if
such interruption had not occurred.
C.1 General
To confirm the guarantee of Net Power Output for the Plant, a live assessment will be
performed while the Generating Sets are in full operation for net power output test
(simple cycle/combined cycle).
A list of further instrumentation to be used during the test and the corresponding
calibration certificates or measurement precision declarations shall be provided with
the final test report.
The readings of the Ambient Conditions (which include temperature and pressure)
must also be taken at the beginning and end of the test manually and the plant
operating values must be taken either from the line recorder of the EDS system or
the control system, and must include time references.
D.1 General
To confirm the guarantees of Net Heat Rate of the plant, a live assessment will be
performed while the Generating Sets, Boilers, Steam Turbine are in full operation
running at rated plant capacity with a positive tolerance of 500kW. The heat rate test
will take One Six (16) continuous hours to complete and comprise of measurements
of the energy produced, the Fuel Oil consumed and the ambient conditions unless
recommended otherwise by the OEM.
Test Preliminaries
The load on the Generating Sets shall not be adjusted during this test except to
prevent damage to equipment or respond to the system’s needs. If the load is
adjusted during the Performance Test to prevent damage to the equipment then the
test for those Generating Sets shall be stopped and a new test shall commence at a
later time. If the load is adjusted to respond to the system’s needs, the test can only
continue once the system has reached steady state again.
A list of further instrumentation to be used during the test and the corresponding
calibration certificates or measurement precision declarations shall be provided with
the final test report.
Furthermore the Leakage Fuel Oil from the leakage fuel oil tank will be measured by
an accurate scale. At the beginning of the Specific Fuel Oil Consumption test the
tank will be drained and the level will be checked and noted with the time. After the
consumption test is finished the tank will be measured again and the level will be
noted with the time. This amount will be calculated as leakage fuel oil which will be
transferred to the day tank.
To determine the specific gravity of the fuel and its lower calorific value, three fuel
samples (each no less than 0.25 liters) shall be taken for analysis immediately before
and after the test. One of these 3 samples shall be sent to the certified chemical
laboratory of MAN Diesel & Turbo SE in Augsburg for analyzing. The other two
samples are for the Employer and the Contractor. Fuel shall only be taken from the
fuel oil supply line at the fuel oil booster module during the test.
D.3 Calculations
Power Output
E.1 General
In case guaranteed values for lubricating oil consumption are not met during
performance tests, the Contractor shall be entitled to repeat such tests after a
running-in period of 1000 running hours. Until then, no liquidated damages shall be
applicable, and this repeated test shall not be a reason to delay provisional receipt of
the plant, but shall be part of the punch list.
If an engine is stopped during the test, the operating counter and energy counter
must be recorded.
At the beginning and end of the test, the following measurements shall be taken:
Time [hh:mm]
Engine Operating Hours [hrs]
Lubricating Oil flow Counter [m³]
Twenty (20) minutes before ending the test, the lubricating oil service tank refilling
shall be manually triggered then stopped after a short period. This shall be repeated
until the high level indicator stops filling by closing a solenoid valve. This is meant to
allow the fresh oil to reach the same temperature as that within the service tank.
During any tank refilling, the temperature of the fresh lubricating oil taken at the flow
counter shall be recorded.
Once the test time has ended, the mass of all lubricating oil leakage must be
measured. This includes oil lost from filters and oil contained in return lines to the
leakage tank.
Only lube oil that has been returned to or will be returned to the lube oil reservoir is
allowed to exclude from the calculation.
F.1 General
The Exhaust Gas Emissions parameters for the Generating Sets, a live assessment
will be performed while the Generating Sets are in operation running at 100%
capacity. The test shall determine the levels of Nitrogen Oxides, Sulphur Oxides,
Carbon Monoxide, Oxygen and the total solid particulates contained within the
exhaust gas.
Before any measurements are made, all test equipment shall be calibrated using
nitrogen gas to set the zero points and using calibration-gases for the span points.
The exhaust gas sampling point shall be determined by both the Contractor and the
Employer, and must comply with ISO safety standards. The sampling pipes used
must not contaminate the exhaust sample and must be heated for proper analyses,
according to ISO.
Test measurements shall only be taken after the appropriate time has elapsed (as
shown here) to ensure steady state conditions:
Two (2) hours after an engine load change of more than 7.5%
Twelve (12) hours after a “cold” start (engine has been stopped for more than 3
hours)
Six (6) hours after a “hot” start (engine has been stopped for less than 3 hours)
Two (2) hours after boiler “blow down”
G.1 General
For Noise Measurement Procedure, international standard will follow.
The Contractor shall ensure the compliance with the Applicable Laws including but
not limited to the requirements imposed by the relevant environmental authorities of
Bangladesh in relation to the noise measurement of the Facility and obtain all the
necessary clearances, certificates, licenses and permits on behalf of the Employer
and ensure compliance of the terms and conditions included therein. Noise data shall
collect at 1 meter distance from plant property line, every 100 meter interval to get
average value.
Tests of Steam Turbine
The steam turbine shall be tested as per the standard ISO/DIN/ASME PTC/BS EN
with all the diesel engines operating on predefined load and temperature.
No. of
S/L Equipment units Status
Running
A Engine Auxiliaries
1. Lube oil separator module 6 ON
2. Oil mist eliminator 6 ON
3. Two-circuit radiator cooling system 6 AUTO
4. Fuel oil booster module 6 ON
5. Nozzle cooling water module 6 ON
6. Heavy fuel oil supply pump 1 ON
7. Engine Hall Ventilation Fans 12 AUTO
B Secondary Cycle Auxiliaries
8. Cooling Water Pumps 3 ON
9. Cooling Towers 1 AUTO
10. Feed Water Pumps 2 ON
11. Condensate Extraction Pump 1 ON
12. Air Blower Motor 1 ON
13. Vapor extractor Motor 1 ON
C Plant Loads
14. All Lighting except non plant building and street lights 1 ON
Air Conditioning (Control Room, MV & LV Switchgear
15. 1 ON
Room)
16. Hydrophore Pump for purifiers 1 AUTO
17. Fire Water Jockey Pump 1 AUTO