CONTRAC NO :

QA/QC
SP-203/PG0300/2014-SO

DOCUMENT NO : 5 Halaman
GRSM-00-PRC-QAC-PRO-155
INDUSTRY & TRADING
DAYA MUDA PRAKARSA

JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI PEMBANGUNAN PIPA


TRANSMISI GAS GRESIK – SEMARANG

FAT PROCEDURE
PT. DAYA MUDA PRAKARSA

Re-Issued For
B 12-10-15 AGW NFL BRT
Approval

A 21-09-15 Issued For Approval AGW NFL BRT

BY CHECK APPD APPD APPD


REV. DATE DESCRIPTION
PT. DAYA MUDA PRAKARSA PMC PERTAGAS
Instrument & Test Plan for Screw Compressor Testing
Introduction:
The purpose of the instrument and test plan for screw compressor testing is to control manufacturing
process of the compressors, as well as to recognize its result in accordance with the related specifications
and the fulfillment of the designated function and safety

Screw Compressor Testing - General

Scope of Application:

This document covers procedures and methods of test plan to be performed to the Screw Compressor
which has been manufactured and supplied by screw compressor vendors.

Test Plan Procedures

The compressor shop running test will be performed by the procedures described in the test plan
procedures.

See attached (page 1 & 2)

Code & Reference:

This Test run is according to ISO-1217 Annex X – Fourth Edition 2009-07-01

Reports to be submitted:

Screw Compressor Mechanical Running Test

Following Items are measured in Mechanical Run:

 Atmospheric Pressure
 Atmospheric Temperature
 Relative Humidity
 Inlet Pressure
 Inlet Temperature
 Discharge Pressure
 Discharge Temperature
 Compressor speed
 Noise Level
Date Of Inspection : ___________________________
Customer Name : ___________________________
Project : ___________________________
Custamer Address : ___________________________
Distributor/Air Center : ___________________________

Compressor Type : ___________________________


Model No. : ___________________________
Serial No. : ___________________________
Work Order No. : ___________________________

1. 8,5/5,0 Bar Package Discharge Press (Off Line/On Line) _________________


2. Clock Wise Check Rotation _________________
3. Clean Inlet Filter Condition _________________
4. Level Gauge Check Oil Level _________________
5. No Leaks Inspect for Oil Leaks _________________
6. 10-46 Room Ambient Temperature (◦c) _________________
7. - Belts Tight and in Good Condition _________________
8. - Idler Pulley Condition _________________
9. No Leaks Inspect for Air Leaks _________________
10. Check Inspect All Oil Cooler Cores _________________
11. Clean Inspect and Clean Condensate Drain _________________

12. 15 Safety Valve Checked Nameplate (Bar) _________________

1
1. 380-415 Voltage (Full Load) L1._______ L2._______ L3._______
2. 380-415 Voltage (No Load) L1._______ L2._______ L3._______
3. Max 65 Motor Amperage (Full Load) T1/U_____ T2/V______ T3/W_____
4. Max 30 Motor Amperage (No Load) T1/U_____ T2/V______ T3/W_____
5. +/- 10% Voltage Drop Across Starter L1._______ L2._______ L3._______
6. Max 69,1 Total PKG Ampe (Full Load) L1._______ L2._______ L3._______
7. 22 Motor Nameplete Data (KW) RPM_______ V _______ A _______
8. Push Botton Inspect Contactors ______________________________
9. Good Check Elektrikal Connections ______________________________
10. Indicator On Check Lamp ______________________________
11. Push Botton Check Emergency Stop ______________________________

2
Inspected By : __________________________________ Cert.#____________________________

Revlewed By : ___________________________________________________________________
(Customer,s Signature) PERTAMINA GAS

Revlewed By : ___________________________________________________________________
(Customer,s Signature) KWRK

Revlewed By : ___________________________________________________________________
(Customer,s Signature) DAYA MUDA PRAKARSA