1 Objective........................................................................................................................ 2
2 Local regulations.......................................................................................................... 2
6 Measurement Sources..................................................................................................6
7 Tools.............................................................................................................................. 6
8 Reference Documents..................................................................................................6
Page 1 of 6
1 Objective
Qualified and licensed personnel where appropriate shall work with the local
Electricity Authority and shall carry out the works. All material and work shall
comply with the requirements of the local Electricity Authority, including any
amendments or other regulations issued by National or local Authorities
Install signs and barriers, electrical warning signs and power on signs
around the test area as applicable
Ensure the personnel assigned for the task are fully aware of all
applicable hazards and JSA is made.
Ensure the suppliers factory acceptance testing documentation and test
results are available.
Ensure all critical safety items in the punch list under category A is
completed and Category B items are agreed.
Obtain permit to work.
Ensure all work is carried out in compliance with the relevant work
permit and JSA.
The Phasing test is conducted to check cables are correct with phases i.e. L1 to
L1, L2 to L2 and L3 to L3. This is done by verifying continuity of the cable using
Digital Multimeter.
Page 3 of 6
5.3 Insulation Resistance Test
Prior to carrying out insulation Test ensure the cable to be tested are disconnected and
prepared at each end.
Insulation resistance of the cable is carried out with 5kV Insulation tester – Megger.
HV test shall be conducted on each phase and earth with remaining phases conducted to
earth and loads disconnected.
Keep the DC Hipot kit to the Point of test of the HV cable under test.
Connect HV lead to one phase/the HV cable under test and other two phases / cables to the
ground terminal in the test kit.
Now connected the kit Ground terminal to the General mass of earth.
High Voltage DC from the test kit is applied to cables under test for 15 minutes.
Page 4 of 6
Uo- Is the rated power frequency voltage between conductor and earth or metallic screen
which the cable is designed
U- Is the rated power frequency voltage between conductors for which the cable is
designed
All equipment must be disconnected from the cable circuit such a surge arrestor, switches
transformer busbars
Select the required Voltage and current range in the HI pot Test kit meter.
Gradually increase the test voltage by the knob, with 10 steps (each step =1/10 of test
voltage) to the required level and observe the leakage current.
Observe for 15 minutes and record final voltage and current readings.
During the period, readings should be more or less steady and minor fluctuations to be
ignored.
At the end of elapsed time, reduce the voltage gradually to zero and isolate kit power supply.
Then discharge the MV cable under test and charge to next phase / MV cable to be tested
Hipot kit
After completing hi pot test discharges the cables with discharge rod and carry out insulation
test again as mentioned in above 6.1.3.
Page 5 of 6
5kV megger test to be carried out for each phase / MV cable and readings are to be
recorded
Check and confirm cable markings and terminations are as per cable schedules drawings
6 Measurement Sources
7 Tools
Power tools
Hand Tools
Digital Multimeter
Jumper Leads
Mobile Telephones / Handheld Radios
5KV Insulation Tester
DC HIPOT
Temp/Hygrometer
First Aid Equipment
Gas Testers/Analyzer
Warning Tape
PPE
Tools and associated appliances
8 Reference Documents
Hand Over Package
Manufacturers Documents
MV Cables FAT and associated documents
Permit to work
JSEA
Cable Schedule.
SQAD Form
Page 6 of 6