Professional Documents
Culture Documents
Co-Gasification of Solid Waste and Ligni
Co-Gasification of Solid Waste and Ligni
Co-Gasification of Solid Waste and Ligni
com
a
Centre for Research and Technology Hellas (CERTH)/Institute for Solid Fuels Technology and Applications (ISFTA),
4th km N.R. Ptolemais-Kozani, 502 00 Ptolemais, Greece
b
Laboratory of Steam Boilers and Thermal Plants, Mechanical Engineering Department, National Technical University of Athens,
Heroon Polytechniou Ave., 157 80 Zografou Athens, Greece
Abstract
Co-gasification of solid waste and coal is a very attractive and efficient way of generating power, but also an alternative way, apart
from conventional technologies such as incineration and landfill, of treating waste materials. The technology of co-gasification can result
in very clean power plants using a wide range of solid fuels but there are considerable economic and environmental challenges.
The aim of this study is to present the available existing co-gasification techniques and projects for coal and solid wastes and to inves-
tigate the techno-economic feasibility, concerning the installation and operation of a 30 MWe co-gasification power plant based on inte-
grated gasification combined cycle (IGCC) technology, using lignite and refuse derived fuel (RDF), in the region of Western Macedonia
prefecture (WMP), Greece. The gasification block was based on the British Gas-Lurgi (BGL) gasifier, while the gas clean-up block was
based on cold gas purification.
The competitive advantages of co-gasification systems can be defined both by the fuel feedstock and production flexibility but also by
their environmentally sound operation. It also offers the benefit of commercial application of the process by-products, gasification slag
and elemental sulphur.
Co-gasification of coal and waste can be performed through parallel or direct gasification. Direct gasification constitutes a viable
choice for installations with capacities of more than 350 MWe. Parallel gasification, without extensive treatment of produced gas, is rec-
ommended for gasifiers of small to medium size installed in regions where coal-fired power plants operate.
The preliminary cost estimation indicated that the establishment of an IGCC RDF/lignite plant in the region of WMP is not profitable,
due to high specific capital investment and in spite of the lower fuel supply cost. The technology of co-gasification is not mature enough and
therefore high capital requirements are needed in order to set up a direct co-gasification plant. The cost of electricity estimated was not com-
petitive, compared to the prices dominating the Greek electricity market and thus further economic evaluation is required.
The project would be acceptable if modular construction of the unit was first adopted near operating power plants, based on parallel
co-gasification, and gradually incorporating the remaining process steps (gas purification, power generation) with the aim of eventually
establishing a true direct co-gasification plant.
Ó 2007 Elsevier Ltd. All rights reserved.
Abbreviations: BGL, British Gas-Lurgi; CFB, circulating fluidised bed; CHP, combined heat and power; COS, carbonyl sulphide; DEC, delivered
equipment cost; HRSG, heat recovery steam generator; IGCC, integrated gasification combined cycle; MDEA, methyl diethanol amine; MSW, municipal
solid waste; PPC, process plant cost; PPC S.A., Public Power Corporation S.A.; RES, renewable energy sources; RDF, refuse derived fuel; SCOT, shell
claus off-gas treatment; TCR, total capital requirement; TPC, total plant cost; TPI, total plant investment; WID, waste incineration directive; WMP,
Western Macedonia prefecture.
*
Corresponding author. Tel.: +30 2106546637; fax: +30 2106527539.
E-mail address: koukouzas@techp.demokritos.gr (N. Koukouzas).
0956-053X/$ - see front matter Ó 2007 Elsevier Ltd. All rights reserved.
doi:10.1016/j.wasman.2007.04.011
1264 N. Koukouzas et al. / Waste Management 28 (2008) 1263–1275
and the size limitation of a power plant using just waste or use of syngas in the boilers does not require feedstock dry-
biomass (Hotchkiss et al., 2002). ing and advanced fuel gas clean-up and therefore consider-
Co-gasification of coal with other kinds of fuels such as able savings in capital costs are realized, compared to
wastes and biomass, is considered to be a promising tech- complete IGCC systems (Mory and Tauschitz, 2000). It
nology to reduce CO2, SO2 and NOx emissions, even in has to be mentioned that only solids are recovered from
dealing with high ash coals, like the Greek lignite, and the syngas stream in most of these installations. Usually,
has been extensively investigated (Valero and Uson, 2006; the flowrate of syngas is lower, compared to the main fuel,
Aznar et al., 2006; Yuehong et al., 2006; Pinto et al., and further gas clean-up is not required. In Fig. 1, a simpli-
2002, 2003; Liebner and Ulber, 2000; Collot et al., 1999;) fied process flow diagram for the parallel gasification tech-
at bench and pilot scales. nology is depicted.
Co-gasification of coal and solid wastes can be achieved The parallel gasification technology does not provide the
through parallel or direct gasification. Both technologies ability of utilizing the produced synthesis gas for direct
are mainly still in a demonstration stage, while a few oper- power generation, since there is no gas purification unit.
ate at commercial level. These technologies appear to hold On the other hand, it has a low capital investment and
the most promising potential, concerning technical potential shutdowns in the gasification process unit do
improvements, compared to other power generation tech- not result in a total shutdown of the entire thermal power
nologies based on solid fuels (Karg et al., 2000). station. The heat content of solid wastes/biomass is trans-
ferred from the gasifier to the boiler in three forms, as sen-
2.1. Parallel gasification sible heat, as chemical energy in the form of a low calorific
value gas and as finely divided char particulates that may
In this method, the produced syngas comes out from the have escaped from the solids recovery.
gasifier and is ducted, without extensive treatment, to con- Parallel gasification has been demonstrated successfully
ventional pulverized coal-fired boilers, where it is burnt as at the Zeltweg power plant in Austria (BioCoComb pro-
an auxiliary fuel along with coal (co-firing). The immediate ject), funded by the European Community Thermie Fund.
FLUE GAS
TREATMENT
LIGNITE
SOLID
WASTES
SYN GAS
BOILER
STEAM
GASIFIER
STEAM TURBINE
MILL CONDENSER
ASH
FEED WATER
PUMP
A biomass gasifier for bark, wood chips and sawdust has Another successful co-gasification project is the Ruien
been installed at the 137 MWe pulverized-coal fired power plant in Belgium, located at West Flanders. This plant is
station in Zeltweg/Styria. According to the thermal capac- basically a copy of the existing atmospheric CFB gasifier
ity of 10 MW, the produced gas substituted approximately in Lahti, Finland as also supplied by Foster Wheeler.
3% of the coal fired in the boiler. The separate gasifier was The gasifier was commissioned at the end of 2002 and
realised in circulating fluidised bed (CFB) technology, started commercial operation in January 2003. The gasifier
which guarantees even relatively low temperatures in all uses either wood chips originating from forestry or recycled
parts of the gasifier to prevent slagging. The intense wood residues from the wood manufacturing industry. The
motion of the bed material also favours attrition of the biomass fuel (between 40 and 80 MW of fuel input depend-
biomass particles (Simader and Moritz, 2000). The CFB ing on moisture content) is gasified in the atmospheric CFB
reactor also guarantees a high flexibility to a wide range gasifiers and then directly fired into one of the coal furnaces
of biofuel types. Via the hot gas duct the product gas is of the plant. A low gas quality is quite sufficient and there-
led directly to the coal boiler, where the injected gas is fore no pre-drying or milling of the biomass and no hot gas
burned together with the coal by the present oxygen sur- cleaning or gas cooling is necessary (Ryckmans and Van
plus. The Zeltweg parallel co-gasification concept was den Spiegel, 2004). Specific investment costs are in the
commissioned between 1997 and 1998 and operated at range of 500–1000€/KWe (Jouret et al., 2005). The opera-
commercial scale until 2002 when it was shut down because tional performance of the gasifier is satisfactory.
electricity generation at the plant was too expensive and The Amer 9 co-gasification plant in Geertruidenberg
there was an overcapacity in the area (Granatstein, 2002). (The Netherlands) is also a very interesting example of gas-
Nevertheless, its demonstration and commercial operation ification where the fuel gas is co-fired in the main coal boi-
has been considered as very successful, and it has been indi- ler. In the original set-up of the Amer gas project, the fuel
cated that gasifier operation played no part in the shutdown (demolition wood) is gasified in a CFB gasifier (atmo-
decision. spheric pressure, 850 °C). The fuel is pre-treated (size
Another example of parallel co-gasification is provided reduced) to meet the gasifier specifications (size <50 mm,
by the installation at Kymijarvi CHP power plant in Lahti moisture content <20%). After gasification the raw fuel
(Finland), designed and supplied by Foster Wheeler, where gas is cleaned in low-temperature gas clean up (baghouse
a 240 MWth boiler fired with hard coal, operated since filter, scrubber), after which the clean gas is combusted in
1976, has been retrofitted to a CFB gasifier, rated at 40 the coal boiler via specially designed low calorific gas burn-
to 70 MWth, which can gasify wood chips, wood waste, ers (Willeboer, 1998). Five percent of the total energetic
paper, cardboard, plastics, demolition wood, sawdust, plant input responds to the co-firing of the demolition
plastic waste and shredded tires. A cyclone is fitted down- wood. Features of the concept are: the relatively stringent
stream of the gasifier that directs solid particles back to the fuel constraints that have to be met and the relatively high
bed. After dust removal, gas is fed directly to burners specific additional investment costs. An advantage of this
located in the lower part of the combustion chamber, concept is that the main part of the fuel-based contami-
where it replaces part of the coal. This installation has been nants is separated from the gas before entering the coal-
designed to gasify biomass with a moisture content up to fired boiler. This means that a wide range of fuels can be
60% and therefore the gas quality is very low. The Kymi- co-fired in this concept, without causing applicable emis-
jarvi CHP plant produces electricity and district heat to sion constraints or problems related to ash quality require-
the Lahti city. The maximum power capacity is ments. The application has recently turned to wood chips
167 MWe, and the maximum district heat production is as additional fuel input (Jounginger et al., 2006).
240 MW. The biomass gasifier was connected to the boiler
at the end of 1997. Concerning the gasification process 2.2. Direct gasification
itself; the results have met expectations. The operating
experience of the gasifier during the years 1998–2003 has In direct gasification, coal and solid wastes or biomass
been excellent (Nieminen, 2004). The stability of the main are mixed and then fed to the gasification unit. The whole
boiler steam cycle has also been excellent. Moreover, the process incorporates three mature technologies: gasifica-
changes in emissions were very small. tion, gas clean-up and combined cycle power generation.
Operational experience from both of these installations The functional combination of these processes comprises
has shown that: it is possible to gasify biomass of very the so-called IGCC systems, as shown in Fig. 2.
diverse types; co-firing of syngas and coal does not cause Co-gasification with two main power generation
boiler combustion chamber slagging; biomass gasification cycles, the Brayton cycle and the Rankine steam cycle,
requires only a short residence time in the bed which means has proved to be quite efficient in the power generation
a small reactor size and consequently low cost (Golec et al., sector. Moreover, the produced syngas can be converted
2003); there is no need to cool and purify fuel gas and to into useful chemical products of high additive value such
remove solids before supplying it to the combustion cham- as hydrogen, methanol, sulphur, ammonia, synthetic nat-
ber; and only minor modifications of the main boiler are ural gas and fertilizers (US Department of Energy, 2001).
necessary. At the same time, there is the ability of incorporating
N. Koukouzas et al. / Waste Management 28 (2008) 1263–1275 1267
PURIFIED
GASIFIER
SYNGAS
LIGNITE SYN GAS
SOLID TREATMENT
WASTES
AIR s2
H2
o2
ASH TRANSPORTATION FUELS
CHEMICALS
AIR
GAS TURBINE
SEPERATION
UNIT
HEAT RECOVERY
STEAM GENERATOR FLUE GASES
STEAM TURBINE
STEAM
advanced power generation technologies to the process, started running on wood dust, and demolition wood will be
such as fuel cells or reciprocating engines. IGCC installa- added soon (Van der Drift, 2006).
tions are characterized by very low SO2 and NOx emis- BGL co-gasification of coal and solid wastes takes place
sions, the possibility of achieving very high efficiency in at the facilities of SVZ GCC/Methanol Plant at Schwarze
accordance with gas turbine development, pure sulfur Pumpe GmbH in Germany and in Kentucky (USA), also
recovery and solid waste products in the form of a glassy incorporating fuel cells apart from IGCC (US Department
slag (Golec et al., 2003). of Energy, 1999). Both plants utilize the oxygen-blown,
The Eclogas IGCC power plant in Puertollano (Spain) moving-bed, slagging gasifier technology of British Gas
and the Nuon power plant in Buggenum (The Netherlands) Lurgi (BGL) and are owned by Global Energy Inc., a leader
are the largest IGCC installations in Europe and they uti- in direct gasification projects. This specific gasifier has been
lize the entrained-flow gasification system with dry powder designed and developed for coarse solid materials without
feeding system. Puertollano uses a mixture of coal and any limitation concerning the ash and moisture content,
petroleum coke (50% w/w). Buggenum was commissioned whereas the produced ash of vitreous structure is well
in 1993 running on natural gas; in 1994 it replaced its major within the limits imposed by the German waste manage-
thermal input with syngas from coal. It is the first IGCC ment regulations (German Ministry of the Environment,
power plant in Europe and its electric capacity comes up 2001). BGL gasifiers have the most operational experience
to 250 MWe. Power generation is now governed by the net- with fuels of widely differing mechanical properties. The
work requirement and not in base-load mode, as designed. BGL gasifier has been selected for this present work.
The fuel commonly used in Buggenum is a mixture of the The SVZ Schwarze Pumpe facility represents a major
cheapest coals from the world market, which is also used investment in an innovative and efficient system for the
in the conventional power plants in The Netherlands (Rad- large-scale processing of a wide variety of solid and liquid
tke et al., 2005). In 2002 it initiated biomass co-gasification waste materials with heat recovery, power generation and
trials with a variety of waste fuels such as sewage sludge, methanol production. The project is a true co-gasification
chicken litter and wood residues. It was proven to be tech- project with various waste streams and lignite (Malkow,
nically viable. In March 2006, there was an official opening 2004). Some of the co-gasification projects in Europe are
of the biomass facilities for 30% w/w co-gasification. They reviewed in Table 1, along with some additional data.
1268 N. Koukouzas et al. / Waste Management 28 (2008) 1263–1275
Table 1
Large co-gasification projects (DTI, 2002)
Plant Output/gasifier output Comments
Amercentrale 9 (Netherlands) 600 MWe/85 MWth Lurgi CFB gasifier using demolition wood which supplies
gas to the main boiler
Kymijarvi CHP plant (Lahti, Finland) 350 MWe/70 MWth Foster wheeler gasifier using a range of biomass. Again the
gas is co-fired
Zeltweg power plant (Austria) 137 MWe/10 MWth Austrian energy CFB biomass gasifier. Again the gas is co-
fired in the main boiler. Not in operation anymore
SVZ GCC/Methanol Plant at Schwarze Pumpe 1 new BGL gasifier 7 old Lurgi True co-gasification including lignite, waste plastics and
(Germany) Global Energy ownership fixed-bed gasifiers 2 entrained sewage sludge
gasifiers
Elcogas (Spain) 300 MWe 70% petroleum coke, 30% coal by thermal input
Berrenrath (Germany) Methanol from MSW and lignite High Temperature Winkler
(tests only)
3. Case study for Western Macedonia mental sulphur, were calculated based upon the results
obtained from a US DOE/NETL report (NETL/Process
Taking into account the above available technologies, a Engineering Division, 2000), after appropriate escalation.
case study for WMP was carried out with regard to the The report deals with BGL gasifier IGCC base cases of
potential of establishing and operating a direct co-gasifica- the same type as was selected for the case study performed.
tion (IGCC) unit utilizing lignite and solid wastes in the The heat and mass balances in this report were performed
form of RDF. The selection of this specific geographical using ASPEN PLUS (Version 10.1) simulation models. The
region relies mainly on the presence of significant lignite proximate and ultimate analysis of RDF and lignite from
deposits, but also on the operation of an integrated solid W. Macedonia and some technical data of the plant sce-
waste treatment system within this region. nario under evaluation are presented in Tables 3 and 4,
The annual production of lignite in Greece is around respectively. For this specific RDF/lignite co-gasification
60 millions tons, out of which 48 million tons derive from concept, cold gas clean-up was selected instead of hot gas
the coalfields of WMP. This advantage has been exploited clean-up, because the syngas produced from RDF contains
to a great extent, since 67% of the total power requirements hazardous contaminants (HCl, H2S, heavy metals, alkalis,
of Greece are generated within this region (Koukouzas etc.) that cannot be effectively removed by the ceramic can-
et al., 2004). The location of power stations, deposits and dle filters usually used for hot gas clean-up. The extensive
lignite mines in WMP is presented in detail in Fig. 3. purification unit that was incorporated in the process is
The annual amount of municipal solid waste in WMP is capable of achieving the emissions limits imposed by regu-
117,000 ton. The mass composition of MSW produced lations (WID) and simultaneously the strict requirements
within the region is presented in Table 2. Around 20% of of the gas turbine, in order to avoid corrosion. A short
this quantity consists of non-combustible components, description of the main process steps follows.
which will be removed during RDF production (Solid
Waste Management of Western Macedonia S.A., 2004).
RDF was selected instead of MSW because of its better 3.1. Fuel pre-treatment and gasification (Gasification block)
quality characteristics, although the RDF production unit
increases considerably the total process plant cost (PPC). A simplified process flow sheet of the entire process is
The main process stages in the case of direct gasification depicted in Fig. 4. The RDF production unit (1) consists
include fuel pre-treatment, gasification, syngas clean-up of standard equipment such as shredder, magnetic separa-
and finally power generation. The gasifier feed consists of tors for metallic materials removal, classifier and screens
a RDF and lignite mixture in the form of pellets with for inert materials removal, dryer, mixer, cooler and pelle-
75:25 mass proportions. This high RDF/lignite mass frac- tising press. MSW (stream 1) enters the fuel preparation
tion is feasible for utilization for direct BGL co-gasi- unit and at the pelletising process step, lignite is added
fication, according to tests performed at the facilities of (stream 2) acting as a binder medium and hence producing
SVZ Schwarze Pumpe during the THERMIE project uniform RDF/lignite pellets with great mechanical
(CERTH/ISFTA, 2002). Taking into account the total stability.
annual production of MSW, the installed power capacity The feed mixture (stream 3), lignite/RDF pellets, is fed
of the unit was calculated at around 30 MWe. The power into the top of the BGL gasifier (2) via a lock hopper sys-
capacity estimation was also based upon the heating values tem where it is pressurized to the operating pressure of
of the fuels and process efficiency. about 27–30 bars and reacts while moving downward
The feedstock requirements concerning lignite, RDF through the gasifier. The BGL gasifier is a counter-current,
and oxygen and the by-products throughput, ash and ele- moving-bed, slagging gasifier. The reactor vessel is water
N. Koukouzas et al. / Waste Management 28 (2008) 1263–1275 1269
Fig. 3. The location of power stations, deposits and lignite mines in WMP (Koukouzas et al., 2004).
and refractory lined. The drying and reduction zone 3.2. Syngas treatment and power generation (gas-clean up
temperature is from 40 to 700 °C. The gasification zone block and power block)
temperature is approximately 700–1500 °C, whereas the
combustion zone temperature is around 1500–2000 °C. Cooling of the produced synthesis gas via direct water
The gasification medium, steam (stream 4) and oxygen quench (4) results in condensation of the heavy hydrocar-
(stream 5), is injected through the bottom of the gasifier bons components, such as tars, oils and naphtha. These
via tuyere nozzles, whilst the raw syngas (stream 6) exits compounds are then recovered in a separation unit (4)
from the top at approximately 500 °C. Ash is removed and recirculated to the gasifier (stream 7). After additional
from the bottom of the gasifier as molten slag through a cooling and carbonyl sulphide (COS) hydrolysis (5), the
slag tap, then quenched in water and removed. syngas is then driven to the cold gas clean-up unit, where
1270 N. Koukouzas et al. / Waste Management 28 (2008) 1263–1275
Table 4 Capital costs for the RDF/lignite IGCC plant were esti-
Technical data of the IGCC plant mated using a combination of capacity factored and equip-
Feedstock requirements ment-based methods. Capacity factored estimations utilize
Lignite 3.36 ton/h the ratio of the capacity (flow rate, heat duty, etc.) of an
RDF 10.1 ton/h
Oxygen 0.2 m3/m3 of syngas
existing piece of equipment to the new equipment multi-
plied by the cost of the existing equipment, to estimate
Power generation
the cost of the new equipment. A scale-up factor particular
Gas turbine 159,192 MWh/y
Steam turbine 78,408 MWh/y to the equipment type was applied to the capacity ratio
Internal consumption 7.5% (Peters and Timmerhaus, 1991; NREL, 1996). This
By-products
technique is used quite frequently to an accuracy of ±20–
Ash 12,300 ton/y 30%. All costs were calculated to instantaneous 2006
Elemental sulphur 330 ton/y Euros. Where necessary, costs were corrected to 2006 basis
Efficiency
using the Marshall and Swift equipment cost indices,
HHV 45% published in chemical engineering magazine. The major
LHV 47% delivered equipment costs (DEC) were multiplied by a
factor to arrive at the process plant cost (PPC). Table 6
lists the factors used to determine PPC.
the methyl diethanol amine (MDEA) (6) and shell claus PPC is converted to total plant cost (TPC) initially and
off-gas (SCOT) (7) methods are used in sequence to separate then to total plant investment (TPI), after adjustment for
sulphur compounds, chlorides and ammonia, while elemen- interest and inflation during the construction period.
tal sulphur to be marked is reclaimed simultaneously Lastly, total capital requirement (TCR) is estimated.
(stream 9) from the Claus unit (8). Afterwards, the clean TCR is used so that realistic estimates of constructing an
syngas (stream 10) is preheated and resaturated (9) and RDF/lignite IGCC plant can be calculated. The assump-
after the addition of nitrogen (stream 11), derived from tions used for the above conversions are presented in Table
the cryogenic air separation unit (3), is fed to the gas turbine 7, whereas the total capital requirement estimation for the
(10). Nitrogen is added in order to increase the volu- IGCC plant is shown in Table 8.
metric flow though the gas turbine and thus increase power For the case of Western Macedonia, the specific capi-
output. tal investment for the 30 MWe IGCC plant came up to
N. Koukouzas et al. / Waste Management 28 (2008) 1263–1275 1271
6 8
8
6 7
2 7 9
5
2
9
1 3
Steam
12
12
1 4
11
Air 13
5
11 `
14
3 10
Air
Power 13
Block
Fig. 4. IGCC process flow chart: (1) Fuel preparatiion; (2) BGL gasifier; (3) Air separation unit; (4) Gas quenching – cooling and Gas – liquid separation;
(5) Gas cooling and COS hydrolysis; (6) MDEA unit; (7) SCOT unit; (8) Claus unit; (9) Gas preheating and saturation; (10) Gas turbine; (11) Combustion
chamber; (12) HRSG unit; (13) Steam turbine.
Table 5 Table 7
Economic analysis default values Capital cost assumptions
Parameter Value Cost component Factor used
Currency basis €2006 Process plant cost (PPC)
Project life 20 y Engineering and supervision 10% of PPC
Book life 20 y Contingency 15% of PPC
Construction period 4y
Total plant cost (TPC)
Nominal interest rate 10%
Adjustment for interest and inflation Calculated
Construction interest rate 5%
Annual inflation rate 3% Total plant investment (TPI)
Prepaid royalties 0.5% of TPI
Catalyst and chemical inventory Calculated
Table 6 Start-up costs 2.5% of TPI
Cost factors used for calculation of PPC Spare parts 0.5% of TPC
Cost component Factor used Working capital 1% of TPI
Land Calculated
Process water systems 7% of DEC
Yard improvements – Civils 9% of DEC Total capital requirement (TCR)
Piping 7% of DEC
Instrumentation and control 2.5% of DEC
Electrical 8% of DEC
to examine the effects of scale. As noted from Fig. 6, the
3.867€/KWe. The contribution of plant components to specific capital investment for units smaller than 350 MWe
overall delivered equipment cost (DEC) is shown in is not competitive enough compared to the cost of conven-
Fig. 5. The BGL gasifier and the HRSG-steam turbine unit tional power stations utilizing solid fuels, which comes up to
exceed 50% of the total DEC. The air separation unit 1000–1200€/KWe (McMullan et al., 2001).
also has a great contribution to DEC. For this reason, it
is recommended to erect small-scale gasification plants 3.5. Cost of electricity
(<100 MWe) within large industrial areas, in order to share
utilities without bearing additional capital costs. The cost of electricity was estimated using the bus-bar
The specific capital investment per installed capacity cost method by dividing the total annual production cost
(MWe) was then calculated, as shown in Fig. 6, in order by the annual electricity output (Ntelkis, 2000). No profit
1272 N. Koukouzas et al. / Waste Management 28 (2008) 1263–1275
Table 8
Total capital requirement estimation for the 30 MWe IGCC plant
400 MW
Cost component Cost (k€2006)
RDF production 4224 300 MW
BGL gasifier 19,080
Gas/liquid separation and treatment 4048 200 MW
Gas cooling/gas saturation 3446
MDEA unit 1656
100 MW
Claus-SCOT unit 1253
Gas Turbine 4879
HRSG – Steam turbine unit 15,702 50 MW
Air Separation Unit 10,291
0 500 1000 1500 2000 2500 3000 3500 4000
Delivered equipment cost (DEC) 64,579
Specific capital investment cost (Euros/KW)
Process water systems 4520
Yard improvements – civils 5812 Fig. 6. Specific capital investment cost per installed MW.
Piping 4520
Instrumentation and control 1614
Electrical 5166 Table 9
Process plant cost (PPC) 86,211 Operating and maintenance assumptions
Engineering and supervision 8621 Consumable materials prices
Contingency 12,930
Lignite cost 10.27€/ton
Total plant cost (TPC) 107,762 Process water cost 0.21€/ton
Adjustment for interest and inflation 3200 MDEA solvent cost 1.60€/ton
Total plant investment (TPI) 110,962 Ash treatment cost 8€/ton
Prepaid royalties 554 Number of shifts 3 in rotation
Catalyst and chemical inventory 35 Labour requirements 20 persons/shift
Start-up costs 2774 Average annual salary 35,290€/person
Spare parts 538 Maintenance costs 2.2% of TPC
Working capital 1109 Supervision and clerical 10% of labour cost
Land 36 labour
Miscellaneous operating 20% of
Total capital requirement (TCR) 116,008 costs (maintenance + labour + supervision) costs
Specific Capital Investment Cost 3867€/kWe Capacity factor 90% (7920 h/y)
(Availability)
Electricity production or CHP production remain the lation of plants doubling. Co-gasification is handicapped
most likely area for the application of co-gasification. by the typical characteristics of a new technology: high
The lowest investment cost per unit of electricity generated capital costs, high labour and low reliability. These are
is the use of the gas in an existing large power station (par- additional reasons why economic analyses cannot use data
allel gasification). This has been done in several large boil- based on experience and always rely on the costs for build-
ers, often with the gas fired alongside the main fuel and it ing the first plant, which almost always make investments
seems to be the best way of applying co-gasification, espe- look unattractive.
cially for small-scale gasification units and preferably as an The increasing costs of conventional waste management
initial stage. The option allows a comparatively small ther- and disposal options and the trend, in most developed
mal output of gas to be used with the same efficiency as the countries, to divert an increasing fraction of mixed organic
main fuel in the boiler, as a large steam turbine can be used. waste materials from landfill disposal, for environmental
These findings are in agreement with previous results (Hot- and legislative reasons, will make the investment in waste
chkiss et al., 2002) and are supported by the successful to power projects increasingly attractive.
operation of the demonstration and commercial projects In the medium term, coal, biomass, solid wastes and
that have been previously discussed. mainly the combination of them will constitute the main
The above technical considerations and the high cost of feedstock fuels for gasification systems. The need for
electricity that was estimated during the case study for extensive recycling, the stricter environmental regulations,
WMP indicate some of the incentives for a large size power and the relatively high availability of coal deposits in
plant. Labour requirements per unit of installed capacity conjunction with the crude oil resources shortage do
provide yet another driver towards large unit size. High not allow any other option. Especially in Greece, relying
efficiency IGCC power plants are therefore almost always on the domestic lignite deposits, the innovative power
in the size range of several hundreds of MWe. At smaller technologies of the 21st century can be applied directly
capacities, reciprocating engines can become relatively and effectively to the energy and waste management
more attractive compared to rotating turbines. system.
However, the available MSW capacity in WMP does not
provide the option of establishing a large unit. Efforts
Acknowledgements
should be taken in order to examine other potential waste
fuels such as sewage sludge and woody biomass. These
The authors are grateful to the European Commission
efforts should definitely be based on trial tests, and state
for providing partial financial support for this work, under
financial support is a prerequisite towards this direction.
the project THERMIE – Type A (SF/08/98/DE). Mr. Kli-
If many sources of waste fuel feedstocks for IGCC systems
mantos of CERTH/ISFTA is also acknowledged for his
are guaranteed, the establishment of a large station relying
valuable contribution.
on co-gasification with lignite would be an attractive
option to examine.
An economic factor that may confine this option is the References
obligation to monitor emissions, since the installation will
be subject to the WID. Extra costs to achieve the limits Aznar, M.P., Caballero, M.A., Sancho, J.A., Frances, E., 2006. Plastic
imposed by the directive, for syngas and flue gas treatment, waste elimination by co-gasification with coal and biomass in
fluidised bed with air in pilot plant. Fuel Processing Technology 87,
are not necessary since the equipment selected for the pro-
409–420.
posed scenario has proved to be very efficient in reducing CERTH/ISFTA, 2002. Co-gasification of coal and wastes for power
hazardous pollutants to very negligible amounts. This also generation, THERMIE-SF/08/98/DE, Final Report.
justifies the high capital investment cost that was calcu- Chmielniak, T., Sciazko, M., 2003. Co-gasification of biomass and coal for
lated. It is assumed that the expenses for the operation of methanol synthesis. Applied Energy 74, 393–403.
Collot, A.-G., Zhuo, Y., Dugwell, D.R., Kandiyoti, R., 1999. Co-pyrolysis
the monitoring system will be counterbalanced by the
and co-gasification of coal and biomass in bench-scale fixed-bed and
potential benefits from the selling of the process by-prod- fluidised bed reactors. Fuel 78, 667–679.
ucts. Sulphur is a raw material for the chemical industry De Filippis, P., Borgianni, C., Paolucci, M., Pochetti, F., 2004. Prediction
and the vitrified slag has many potential applications in of syngas quality for two-stage gasification of selected waste feed-
the construction and cement industry (lightweight aggre- stocks. Waste Management 24, 633–639.
Department of Trade and Industry, 2002. Technology status report No.
gate, cement additive, paving blocks, etc.).
17, Waste/Biomass Co-gasification with Coal, London.
Co-gasification involving solid waste and coal does not German Ministry for the Environment, 2001. Nature Conservation and
appear to be of significant interest worldwide. There are Nuclear Safety, Ablagerungsverordnung, Berlin.
still a few technical matters that have to be solved, such Golec, T., Rakowski, J., Swirski, J., 2003. Projections of Technological
as the cost-effective syngas cleaning and the gas turbine Progress in Hard Coal, Lignite and Gas Fired Power Plants and their
Environmental Impact. Institute of Power Engineering Publications,
modifications for utilizing the syngas. In general, the costs
Warsaw.
of a process decrease as more units are built and experience Granatstein, D.L., 2002. Case study on BioCoComb Biomass Gasification
is gained. A learning factor may be observed, which is a Project Zeltweg Power Station, Austria, IEA Bioenergy Agreement-
fixed percentage reduction in cost as the cumulative instal- Task 36.
N. Koukouzas et al. / Waste Management 28 (2008) 1263–1275 1275
Hotchkiss, R., Livingston, W., Hall, M., 2002. Waste/biomass co- Nieminen M., 2004. Technology brief: fluidised bed gasification, gas
gasification with coal, Report No. COAL R216, DTI/Pub URN 02/ cleaning, and fuel gas utilization systems, IEA Bioenergy Agreement-
867, London. Task 33.
Jounginger, M., de Wit, M., Faaij, A., 2006. IEA Bionergy Task 40, U.S. Department of Energy/./N.R.E.L., 1996. Cost and performance
Country Report for the Netherlands-Update 2006. analysis of biomass-based integrated gasification combined-cycle
Jouret, N., Helsen, L., Van den Bulck, E., 2005. Study of the wood gasifier power systems, NREL/TP-430-21657, Colorado.
at the power plant of electrabel-ruien. In: Proceedings of the European Ntelkis, K., 2000. Electric Power Production Cost. National Technical
Combustion Meeting. University, Electric Power Department, Athens, in Greek.
Kakaras, E., Grammelis, P., Agraniotis, M., Derichs, W., Schiffer, H.P., Peters, M.S., Timmerhaus, K.D., 1991. Plant Design and Economics for
Maier, J., Hilber, T., 2005. Solid recovered fuel as coal substitute in the Chemical Engineers, fourth ed. McGraw-Hill Inc., New York.
electricity generation sector. Thermal Science International Scientific Pinto, F., Franco, C., Andre, R.N., Miranda, M., Gulyurtlu, I., Cabrita,
Journal 9 (2). I., 2002. Co-gasification study of biomass mixed with plastic wastes.
Karg, J., Haupt, G., Zimmerman, G., 2000. Optimized IGCC cycles for Fuel 81, 291–297.
future applications, in: Gasification Technology Conference, San Pinto, F., Franco, C., Andre, R.N., Tavares, C., Dias, M., Gulyurtlu, I.,
Francisco. Cabrita, I., 2003. Effect of experimental conditions on co-gasification
Koukouzas, N., Kakaras, E., Grammelis, P., 2004. The lignite electricity- of coal, biomass and plastic wastes with air/steam mixtures in a
generating sector in Greece: current status and future prospects. fluidized bed system. Fuel 82, 1967–1976.
International Journal of Energy Research 28, 785–798. Radtke, K.R., Battensby, D., Marsico, C., 2005. Renaissance of gasifi-
Kwak, T.-H., Maken, S., Lee, S., Park, J-W., Min, B., Yoo, Y.D., 2006. cation based on cutting edge technologies, VGB PowerTech, 9/2005.
Environmental aspects of gasification of Korean municipal solid waste Regulatory Authority of Energy, 2006. Schedule of Rates for Electricity
in a pilot plant. Fuel 85, 2012–2017. from Co-generation and Renewable Energy Sources, Athens (in Greek).
Liebner, W., Ulber, D., 2000. MPG-Lurgi multipurpose gasification: Ryckmans, Y., Van den Spiegel, 2004. Biomass gasification and use of
application in gas-gasification. In: Proceedings of the 2000 Gasification syngas as an alternative fuel in a Belgian coal-fired boiler. Technology
Technologies Conference, San Francisco, CA. Brief.
Malkow, T., 2004. Novel and innovative pyrolysis and gasification Simader, G., Moritz, G., 2000. Analysis Report of Power Plant Zeltweg.
technologies for energy efficient and environmentally sound MSW The Austrian Energy Agency, Vienna.
disposal. Waste Management 24, 53–79. Solid Waste Management of Western Macedonia S.A., 2004. General
McIlveen-Wright, D.R., Pinto, F., Armesto, L., Caballero, M.A., Aznar, Data on Integrated Solid Waste Treatment System of Western
M.P., Cabanillas, A., Huang, Y., Franco, C., Gulyurtlu, I., McMu- Macedonia, Kozani (in Greek).
llan, J.T., 2006. A comparison of circulating fluidised bed combustion US Department of Energy, 1999. Kentucky Pioneer Energy IGCC,
and gasification power plant technologies for processing mixtures of Program Update, Washington DC.
coal, biomass and plastic waste. Fuel Processing Technology 87, 793– US Department of Energy, 2001. Clean Coal Technology, Report No. 21,
801. Washington DC.
McMullan, J.T., Williams, B.C., McCahey, S., 2001. Strategic consider- Valero, A., Uson, S., 2006. Oxy-co-gasification of coal and biomass in an
ations for clean coal R&D. Energy Policy 29, 441–452. integrated gasification combined cycle (IGCC) power plant. Energy 31,
Mory, J., Tauschitz, K., 2000. BioCoComb-gasification of biomass and 1643–1655.
co-combustion of the gas in a PF boiler in Zeltweg power plant. The Van der Drift, B., 2006. Country Report-The Netherlands, IEA-Task 33,
use of Coal in Mixture with Waste and Residues II, In: Conference Energy Research Centre of the Netherlands.
proceedings, 145-157, Gottbus. Willeboer, W., 1998. The Amer demolition wood gasification project.
Murphy, J.D., McKeogh, E., 2004. Technical, economic and environ- Biomass and Bioenergy 15, 245–249.
mental analysis of energy production from municipal solid waste. Williams, C.B., 2000. In: Workshop Proceedings: Profit from Gasification,
Renewable Energy 29, 1043–1057. Report No. COAL R197, DTI/Pub URN 00/1079, London.
US Department of Energy/N.E.T.L./Process Engineering Division, 2000. Yuehong, Z., Hao, W., Zhihong, X., 2006. Conceptual design and
BGL Gasifier IGCC Base Cases, PED-IGCC-98-004, Washington simulation study of a co-gasification technology. Energy Conversion
DC. and Management 47, 1416–1428.