Daily Drilling Report

DANAN OILFIELD DEVELOPMENT


General Data
Country/ Province Iran / Ilam Well Type Development W.S.S. Day/ Night H.Ahmadi / H.Jalilzadeh Report No. 30
Field/ Well No. DANAN / DA-17 / E029S Spud Date/ Time 1400/06/01 / 09:00 Operations / Area Manager M.Amini / M.Aliabadi Report Date 09/21/2021 (1400/06/30)
Rig Name NOOR 2 Est. Rig Days 115 Geologist A.Ashrafi / F.Khazaeli Actual Rig Days 30
EPD Contractor MAPNA Hole Section 17 1/2" ICOFC Rep A.Oskooei / M.Khanalizadeh Act Rig Days less
25 Days + 21 Hrs.
Client ICOFC Section Start Date 1400/06/06 Senior/ Night Toolpusher P.Parsi / Y.Raziani NPT
Well Data Bit Data Mud Data
N (m) 3,607,876.35 Bit No. Mud Type WBM (Salt Polymer)
Location (UTM):
E (m) 738,591.12 Bit Size TCI/ MT/ PDC MW Min / Max (pcf) 80
Project TD (m): 3663 Bit Manufacture Flow Line Temp. (deg F) P.CH
R.T.E (m) G.L.E (m) 343.2 334.2 Bit Type Funnel Vis (sec/qrt) 38
Morning Depth (m) 2044 Bit Serial No. Fann 600 43
Mid Night Depth (m) 2044 IADC Code Fann 300 29
Previous Depth (m) 2044 Nozzle Number * Size ( /32 in) Fann 200/ 100 20 / 17
Drilled Interval (m) 0.0 W.O.B (klb) Fann 6/ 3 6/4
Drilling Time (hr) 0.0 RPM / Total bit RPM PV (cp) 14
Average ROP (m/hr) 0.00 Torque (klb.ft) YP (lb/100ft^2) 15
Cum. DRLG Time (hr) 340.0 Pump Type GEL 10 s/ 10 min/ 30 min 5/7/-
Estimated / Actual Rig Days 115 30 Pump Liner Size (in) API Fluid Loss (cc/30 min) 6.0
KOP (m) - Flow Rate (gpm) Mud Cake Thickness (1/32") 1
Last Formation TVD (m) Gachsaran 7-5 2012 Standpipe Pressure (psi) Oil % -
Lithology R.MRL + G.MRL + Anhy TFA (in2) Water % 82
Last casing/ liner shoe 20" @ 57 m Jet Velocity (ft/s) Solid/ Sand Content (%) 18 / 0.6
Last liner lap (m) - Bit Daily Drilled (m) Salinity(ppm)/Chlorides (mg/l) - / 180000
Last FIT TVD (m) EMW (pcf) - - Bit On BTM Hours PH / MBT 9.2 / 12.5
Costs Today Well's Total Cum Drill Out CMT/ Ream (m) Total Hardness/Calcium (mg/l) 1520 / 1320
Day rate Cum Drill Out CMT/ Ream (hr) KCl (%WT)/ Glycol (%Vol) -/-
Mud & Cement Bit Cum. Drilled (m) Vol. in Hole (bbl) 1857
Bit Bit Cum. Hours Vol. in Pits (bbl) 683
Cas/Tub W/H Bit In / Bit Out(m) Mud Sys./ Daily Made (bbl) 2380 / 0
Service Bit Dull Condition Form. Loss/ Mud Pump Repair 0/0
Total Weight Below Jar in mud (klb) Evap./ Shaker / Pit Cleaning 0 / 0 / 30
Mud Materials & Chemicals BHA#5 Dump/ Trip/ Centrifuge/ Other 200 / 0 / 0 / 0
Material Type Unit Rec/Sent Used STK Item Description Length (m) OD (in) ID (in) Cum. L. (m) Total Loss 230
BARITE 1.5 MT 7 156 POB
BENTONITE 1 MT 1 MDCO 6
SODA ASH 50 kg 28 ICOFC 4
SALT (NaCl) 1 MT 144 Services Catering 37 13
CaCO3 (weight agent) 1 MT Rig crew Guests 35 9
CAUSTIC SODA 25 kg 54 Casual labors 10
CITRIC ACID 25 kg Drivers / Radioman 12
Xanthan Gum 25 kg 31 Security 10
G.Starch 25 kg 700 Total 136
Drilling Detergent 55 Gal 4 HSE
Wallnut Shell F/M/C 1 MT 1/0/1 HSE Cases Daily Cum
Starch HT 25 kg LTI free days 1 103
KCl 1MT Man-hours 1632 38424
LIME 25 kg 170 BHA# LTI Accidents
CaCO3 (F/M/C) 25 kg / 1 MT Description length(m) OD (in) ID (in) Cum. L. (m) Non LTI Accidents
MICA F/ M/ C 25 kg / 1 MT 0 / 120 / 0 BOP Drill
SHELL Fish F-M-C 25 kg / 1 MT H2S Drill
PAC-LV/R 25 kg Fire Drill
BIOCIDE 55 Gal Medevac Drill
SODIUM BICARB 25 kg Stop Card 8 126
SPERSENT CF 25 kg PJSM 4 72
PIPELAX 55 gal 8 Toolbox Meeting 1 45
Defoamer 55 gal
OYSTER SHELL COARSE 25 kg
Fiber lock 25 kg
CORROSION INHIBITOR 55 gal
PHPA 25 kg 20
BOP Test
Cement & Cement Additive LAST BOP TEST Date 1400/06/05
Mat. Type Unit Rec / Sent Used STK Days Since Last BOP Test 25
CMT "G" Delijan sx 3900 Pumps Data
CMT "G" Kerman sx 0 Pump # 1 Pump # 2 Pump # 3
Chemical wash can 0 Make KLF KLF KLF
Defoamer (5gal) can 0 DP, HWDP & DC Data Type F1600 F1600 F1600
Dispersant FR-01 sx 0 Size (in) Grade Nominal Weight (ppf) Power (hp) 1600 1600 1600
Spacer SPC-01 sx 0 DP 5 5 G-105 S-135 19.5 19.5 Liner Size (in) 7 7 7
Mutual solvent Dr 0 HWDP 5 G-105 49 Stroke (in) 12 12 12
Accelerator S-01 sx 0 DC 9 3/4 8 1/2 229 169 Max Press (psi) 3100 3100 3100
Light WT Add. LWA-01 Dr 0 Down Hole Equipment
Heavy WT Add LWA-01 B.Bag 0 Equipment (Quantity, OD and Description) ID (in) Serial Number Cum Drlg (hr) Cum W&R/ D/O (hr)
Cement Equipment 9 3/4" DC 3" 1771130002/1771130015 / 5060174 / 1771130016-506181-1771130009 308/297/299/298 3.5 / 6.5
5060132-1771120035-1771120005 / 1771120027-1771120001-5060133 / 5060189-
Equipment Unit Rec Send STK 8 1/2" DC 3" 5060135-1771120017 / 5060127-1771120038-1771120034 294/292/294/289 3.5 / 0
Cement Unit no 3 7 3/4" D.Jar 2 7/8" 5060043 35.5 0/0
Solution Tank no 2
CMT Silo no 5 Solid Control Equipment
Hook Load Data
Air Compressor no 0 Equipment Working Time (hr) Remarks
Surfactant drum 0 Shakers 1 / 2 / 3 22 22 22 170-140-140 / 170-140-140 /170-140-140 H.L (Klb) Pump On Pump Off
Fuel & Water Desilter / Desander / Degasser - - - Pick Up
Fluid Type Unit Rec. Used STK Mud Cleaner 0 320 / 270 / 200 Slack-Off
DIESEL Liter 8,000 63800 Centrifuge #1 / #2 0 0 Rotation
Drill Water bbl 1300 Super Clone - TDS & Block Weight 58 Klb
KOP : Survey Casing Data
No. MD (m) INC (deg) AZ (deg) TVD (m) NS EW DLS Remark Shoe Liner Lap
Casing Size (in) Grade Weight (ppf) Thread Length (m)
1 57.0 0.5 Totco Depth m) (m)
2 93.0 0.5 Totco 20 K-55 106.5 WSP-Big 57.0 57.0 -
3 434.5 1.0 Totco 13 3/8 T-95 & N-80 72 & 68 BTC 2042.0 2042.0 -
4 738.5 1.0 Totco 9 5/8
5 914.00 1.50 Totco 7
6 1219.0 2.0 Totco
7 1493.0 1.75 Totco
8 1797.0 1.5 Totco
Daily Drilling Report

DANAN OILFIELD DEVELOPMENT

Formation Data Well Control (SCR)

Forecasted Top MW (pcf)/ FV


Formation Name Actual Top (m) Lithology Pump # SPM# 1 SPP 1 (psi) SPM# 2 SPP 2 (psi) Depth (m) Time
(m) (s/qrt)

Aghajari Surf. Surf. R.MRL + S.St + G.MRL + Anhy 1

Gachsaran 7- 5 2233 2012.0 R.MRL + G.MRL + Anhy 2

Gachsaran 4 - 2 2448 3

Gachsaran 1 (Cap Rock) 2533 Wellhead BOP Test Record


Asmari 2593 Component Top FLG (Size/ WP) BTM FLG (Size/ WP) Component Type and Size Test Pressure

Kalhur 2673 Xmas Tree Annular 21 1/4" 2k 1500

Pabdeh 2923 THS Top Rams

Gurpi 3383 DSA Pack off Blind Rams

Ilam 3443 CHS Bottom Rams

Sarvak 3543 CHH 21 1/4" 2k Welded - Choke Manif. 5k 1500

Well TD 3663 Wear Bushing Size: 20" IN/ OUT: IN Accumulator 3k

Received

Sent

Request

Outstanding 12 1/4" R.Bit (137, New) + 12 1/4" PDC Bit (M1674,New).

Detail of Operations within Last 24 hours


Code /Activity Hrs From To Hrs Code Remarks
1. Rigging and Moving 00:00 Cont. Run W/53 Jts 13 3/8" CSG (68#, N-80, BTC)(Totally 65 Jts CSG, 72# & 65 Jts CSG, 68#) to 1500 m While Install
2. Drilling 06:30 6.5 11B Bow Centralizer As Program & Break Circ. Mud Each 20 Jts W/NL-NG.
3. Hole Conditioning 06:30 08:00 1.5 11B Change TDS Links & Elevator to Spider Elevator While Slow Circ. Mud Thru Strg W/NL-NG.
4. Coring 08:00 09:30 1.5 11B Drop 1 3/4" Ball & Circ. Mud to Convert Diff. F/U Shoe & Collar to Float Type, Cont. Circ. As 1.2 Cap of Strg W/NL-NG.
5. Mud Condition & Circ. 09:30 Cont. Run W/47 Jts 13 3/8" CSG (68#, N-80, BTC)(Totally 65 Jts CSG, 72# & 112 Jts CSG, 68#) to 2039 m While Install
6. Trips 19:30 10.0 11B Bow & Rigid Centralizers As Program & F/U Strg Each 10 Jts W/NL-NG,Took Weight,Wash Down to 2042 m (Shoe Depth).
7. Rig Services 19:30 21:00 1.5 11B Circ. Mud As 1.2 Cap of Strg W/NL-NG & Check Efficiency of Mud Pumps (P1: 95%, P2: 91%, P3: 95%)
8. Slip and Cut DRLG Line 21:00 L/U CMT lines, R/U CMT Head & Load Top Plug, Press. Test CMT Line W/3000 psi "OK", PJSM.
9. Deviation Survey Perform CMT Job As: Pump 20 bbl Pre-Flush + Pump 70 bbl 88 pcf Mud Push + Mix & Pump 2951 Sxs CMT "G" Delijan
10. Logging 24:00 3.0 12A (S.V: 1231 bbl, S.W: 95 pcf) As Lead Slurry in Progress Till M.N.
11. Running Casing/ Liner 21.0
12. Cementing 3.0
13. Nipple up/ down

14. BOP Test

15. Formation Testing

16. Directional Drilling

17. Well Completion Note : OBS. Oil Leakage From Top Drive & Need to Lubricate Daily.
18. Perforation Note : Pumpsite Water Pumps is Out of Service.
19. Stimulation

20. Production & Well Testing Time 8:00 18:00


21. Suspension/Abandonment Pool Level (m) 0.3 0.2
22. NPT 1.0
23. Other Personnel Shortage On Rigsite: -

TOTALLY 25.0 24.0


From To Hrs Code Morning Report
00:00 Finish Pumping Lead Slurry, Mix & Pump 553 Sxs "G" Delijan CMT (S.V: 135 bbl, S.W: 118 pcf) As Tail Slurry, Drop Top Plug & Disp. CMT
Slurry W/10 bbl Tail CMT + 5 bbl Mud Push + 991 bbl Mud (80 pcf) As Prog, Not OBS. Bumping (Due to Failure of Mud Pump#3 During
Displace) Dump 300 bbl CMT Slurry At Surf & OBS. 200 bbl CMT Loss), Open CMT Head Valve & Check Back Flow "OK" Hang Up Bop
06:00 6.0 12A Stack in Progress.

Note : OBS. Failure Of Weight Indicator During CSG CMT Job.

Total (Hrs) 6.0


Operations Summary
Cont. Run 13 3/8" CSG (Totally 65 Jts CSG, 72# & 112 Jts CSG, 68#) to 2039 m, Wash Down to 2042 m (13 3/8" Shoe Depth) Circ. Mud As 1.2 Cap of CSG, Perform CSG CMT Job As Per Prog.
(Pump 20 bbl Pre-Flush + Pump 70 bbl 88 pcf Mud Push + Mix & Pump 2951 Sxs CMT "G" Delijan (S.V: 1231 bbl, S.W: 95 pcf) As Lead Slurry in Progress Till M.N.

Next Operations
Set CSG HGR & Test Same, Rough Cut L.Jt & L/D Same, N/D 21 1/4" 2K BOP stack, Install Wellhead section "B", N/U BOP Stack & Perform BOP Test
Operations Reference Code
MAPNA Drilling Co.
Code/
Main Activity Details
Subcode
1 Rigging & Moving
2 Drilling
2A Drilling Vertical Drilling using rotary BHA
2B Performance Drilling Vertical Drilling using PDM
3 Hole Conditioning
4 Coring
5 Mud Conditiong & Circulation
5A Preparing Mud Making Mud
5B Displacing the Hole Displacing the well with new mud
5C Mud Circulation Circulation of mud to clean the hole, allow cuttings to reach to surface, etc.
5D Mud Condition Circulation of mud in order to treat the mud condition working on mud properties
5E Loss Control All Activities Associated With Circulate and Condition due to lost circulation
5F Pit Management Cleaning pits, Transferring mud between pits (if cannot be done while doing other operations)
6 Trips
7 Rig Services
8 Slip & Cut Drilling Line
9 Deviation Survey
10 Wireline Logging
11 Running Casing/ Liner
11A R/U & R/D Tubular Running Gear R/U & R/D Casing/ Liner Running Gear
11B Casing/ Liner Running M/U and RIH with Casing Joints (to TD )/ Liner Joints (to DP's, including Liner Hanger)
11C Pulling Casing/ Liner All Activities Associated with Pulling Casing/ Liner
11D CSG/ Liner Pressure Test All Activities Associated with Pressure Test of CSG or liner lap (including Green CMT Test)
11E Running Liner on DP's RIH w/ liner on DP's
11F Pull out Running Tool POOH w/ Running Tool
11G Remedial Job All activities related with Remedial jobs such as Tie-back, casing patch, etc.
12 Cementing
12A Cementing Casing/ Liner Making cement solution, Mix and pump of cement slurry to the wellbore
12B Cement Top Jobs All Activities Associated with Top Jobs for Any Size of Casing
12C Wait on CMT Wait on cement to get hard
12D Drill Out Cement/ Float & Shoe Any Vertical or Directional Drilling of Cement, Float and shoe
12E Cement Plug All Activities Associated with Setting Cement Plug (including trip, pumping time)
12F Remedial Job All Activities Associated with Remedial Jobs such as Squeeze (including trip, pumping time)
13 Nipple up/ down
13A Nipple up/down BOP All activities related to Nippling up or nippling down the BOP

13B Nipple up/down Wellhead


All activities related to Nipple up or nipple down Wellhead (including rough cut, bevel, pressure test)

13C Nipple up/down Xmas Tree


All activities related to Nipple up or nipple down Xmas tree (including rough cut, bevel, pressure test)
14 BOP Test
15 Formation Testing
16 Directional Drilling
17 Well Completion
18 Perforation
19 Stimulation
20 Production & Well Testing
21 Suspension/ Abandonment
22 NPT
22A Waiting on Client
22B Waiting on EPD Contractor
22C Waiting on Service Company
22D Waiting on Rig Contractor
22E Stuck
22F Fishing and milling All preparing, assembling of fishing equipment to recover of junks or fish from a wellbore
22G Side-Tracking All operations related to Sidetracking Original Hole to Bypass a Fish (using cement plug or whipstock)
22H Well Control Issue
22I Washout Including trip out and trip in until reaching previous depth
22J String Plug Including trip out and trip in until reaching previous depth
22K Rig Repair
22L Wait On Weather
22M Force Majeure Other Force Majeures out of Client and Operator's Control
22N Other Down Hole Problem NPTs which is not within the above mentioned Categories
23 Others