Personal Assignment 2: Nama: Oky Nur Arya Putra Mahardika ID Student: 2301978186

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 4

Nama : Oky Nur Arya Putra Mahardika

ID Student : 2301978186

Personal Assignment 2

A. Resource Scheduling

You have prepared the following schedule for a project in which the key resources is a
tractor. There are three tractors available to the project. Activities A and D require one tractor
to complete while activities B, C, E, and F require two tractors.

Develop a resource constrained schedule in the loading char that follows. Use the parallel
method and heuristics given. Be sure to update each period as the computer would do. Record
the early start (ES), the late finish (LF) and slack (SL) for the new schedule.

MGMT8003 – Project and Change Management


Answer :

ID RES DUR ES LF SL 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

A 1 4 0 5 1 1 1 1 1

B 2 5 0 5 0 2 2 2 2 2

C 2 4 5 9 0 X 2 2 2 2

D 1 5 5 12 2 1 1 1 1 1

E 2 3 9 12 0 X X X X 2 2 2

F 2 2 12 14 0 X X 2 2

RESOURCE SCHEDULE 3 3 3 3 2 3 3 3 3 3 2 2 2 2 0 0

RESOURCE AVAILABLE 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3

Aktivitas

Slack Time

MGMT8003 – Project and Change Management


B. Reducing Project Duration

Use the information contained below to compress one time unit per move using the least cost
method. Reduce the schedule until you reach the crash point of the network. For each move
identify waht activity(s) was crashed, the adjusted total cost, and explain your choice if you
have to choose between activities that cost the same.

If the indirect cost for each duration are $1,500 for 17 weeks, $1,450 for 16 weeks, $1,400 for
15 weeks, $1,350 for 14 week, $1,300 for 13 weeks, $1,250 for 12 weeks, $1,200 for 11
weeks, adn $1,150 for 10 weeks, what is the optimum cost-time schedule for the project?
What is the cost?

MGMT8003 – Project and Change Management


Answer :

No Path Normal Time Direct Cost Description

A B D H I $2000
1 17 -
3 4 4 4 3
A B D H I $2000 + $40 =
2 16 $2040 Change Act. D
3 4 3 4 2
A B D H I $2000 + $60 =
3 15 $2060 Change Act. H
3 4 3 3 2
A B D H I $2000 + $60 =
4 14 $2060 Change Act. H
3 4 3 2 2
A B F G I $2000 + $100 =
5 13 $2100 Change Act. B
3 3 3 2 2
A B F G I $2000 + $100 =
6 12 $2100 Change Act. B
3 2 3 2 2
A B F G I $2000 + $200 =
7 11 $2200 Change Act. I
3 2 3 2 1
A B F G I $2000 + $30 =
8 10 $2030 Change Act. F
3 2 2 2 1

Project Duration Direct Cost Indirect Cost Total Cost


17 $2000 $1500 $3500
16 $2040 $1450 $3490
15 $2060 $1400 $3460
14 $2060 $1350 $3410
13 $2100 $1300 $3400
12 $2100 $1250 $3350
11 $2200 $1200 $3400
10 $2030 $1150 $3180

The optimum cost schedule is project duration 10

MGMT8003 – Project and Change Management