Professional Documents
Culture Documents
Personal Assignment 2: Nama: Oky Nur Arya Putra Mahardika ID Student: 2301978186
Personal Assignment 2: Nama: Oky Nur Arya Putra Mahardika ID Student: 2301978186
Personal Assignment 2: Nama: Oky Nur Arya Putra Mahardika ID Student: 2301978186
ID Student : 2301978186
Personal Assignment 2
A. Resource Scheduling
You have prepared the following schedule for a project in which the key resources is a
tractor. There are three tractors available to the project. Activities A and D require one tractor
to complete while activities B, C, E, and F require two tractors.
Develop a resource constrained schedule in the loading char that follows. Use the parallel
method and heuristics given. Be sure to update each period as the computer would do. Record
the early start (ES), the late finish (LF) and slack (SL) for the new schedule.
ID RES DUR ES LF SL 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
A 1 4 0 5 1 1 1 1 1
B 2 5 0 5 0 2 2 2 2 2
C 2 4 5 9 0 X 2 2 2 2
D 1 5 5 12 2 1 1 1 1 1
E 2 3 9 12 0 X X X X 2 2 2
F 2 2 12 14 0 X X 2 2
RESOURCE SCHEDULE 3 3 3 3 2 3 3 3 3 3 2 2 2 2 0 0
RESOURCE AVAILABLE 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Aktivitas
Slack Time
Use the information contained below to compress one time unit per move using the least cost
method. Reduce the schedule until you reach the crash point of the network. For each move
identify waht activity(s) was crashed, the adjusted total cost, and explain your choice if you
have to choose between activities that cost the same.
If the indirect cost for each duration are $1,500 for 17 weeks, $1,450 for 16 weeks, $1,400 for
15 weeks, $1,350 for 14 week, $1,300 for 13 weeks, $1,250 for 12 weeks, $1,200 for 11
weeks, adn $1,150 for 10 weeks, what is the optimum cost-time schedule for the project?
What is the cost?
A B D H I $2000
1 17 -
3 4 4 4 3
A B D H I $2000 + $40 =
2 16 $2040 Change Act. D
3 4 3 4 2
A B D H I $2000 + $60 =
3 15 $2060 Change Act. H
3 4 3 3 2
A B D H I $2000 + $60 =
4 14 $2060 Change Act. H
3 4 3 2 2
A B F G I $2000 + $100 =
5 13 $2100 Change Act. B
3 3 3 2 2
A B F G I $2000 + $100 =
6 12 $2100 Change Act. B
3 2 3 2 2
A B F G I $2000 + $200 =
7 11 $2200 Change Act. I
3 2 3 2 1
A B F G I $2000 + $30 =
8 10 $2030 Change Act. F
3 2 2 2 1