Professional Documents
Culture Documents
Case Analysis - Litigation, Mediation & Arbitration - India
Case Analysis - Litigation, Mediation & Arbitration - India
jigarbakotra@gmail.com
CONTRIBUTOR
ARTICLE
Case Title:
National Highways Authority of India versus Gwalior Jhansi
Expressway Limited (Decision by Hon'ble Supreme Court
of
India in Civil Appeal No. 3288 of 2018 on 13.07.2018)
Facts:
On December 17, 2006, National Highways Authority of India
('NHAI') entered into a Concession Agreement
with Gwalior
Jhansi Expressway Limited ('GJEL') for the work of
widening of existing two-lane portion, from Km
16.000 to Km 96.127,
to four lanes in the States of Uttar Pradesh and Madhya Pradesh.
NHAI asserted that
GJEL failed to undertake the project work at the
requisite pace, inter alia, due to inadequate deployment of
machinery, plant, material and manpower. GJEL had achieved only 62%
progress and eventually abandoned
the project site in March 2012.
NHAI then issued a Cure Period Notice on October 19 2013, requiring
GJEL to
cure the breaches within 30 days from receipt of the
notice. GJEL denied the notice by a written reply. NHAI
thereafter,
issued letters expressing its intention to issue termination notice
of the Concession Agreement.
GJEL then filed a petition under
Section 9 of the Arbitration and Conciliation Act 1996
('Act of 1996') seeking
stay of Cure Period Notice
dated October 19 2013, as well as the notice expressing the
intention to issue
termination notice. The High Court of Delhi
passed an interim stay on March 12, 2014, restraining the
appellant
from taking any coercive action and the petition was finally
disposed-off on April 22, 2015 with a
direction to the Arbitral
Tribunal, which was already constituted in the meantime, that the
interim order dated
March 12, 2014 would continue during the
pendency of the arbitral proceedings with liberty to the parties to
seek its modification or revocation before the Arbitral Tribunal
('AT').
The AT, vide order dated May 24,, 2017 allowed the application
filed by GJEL. NHAI filed an appeal under
Section 37(2)(b) of the
Act of 1996 before the High Court of Delhi but the same was
dismissed on August 21,
2017.
Decision:
The Hon'ble Supreme Court took note of the tender conditions
and observed that the plain wording of the
eligibility clause in
the tender documents and the incidental stipulations made it
explicitly clear that GJEL was
required to participate in the
tender process by submitting its sealed bid (both technical and
financial). GJEL
neither participated in the tender process despite
the express terms in the tender documents nor challenged
the
validity of the tender conditions which stipulated the requirement
for GJEL to participate in the tender
process.
AUTHOR(S)
Rupesh Gupta
Singh & Associates
About
|
Blog
|
Contact Us
|
Contributors
|
Feedback
|
Free News Alerts
|
T&Cs
| Unsubscribe
|
Your Privacy