Pune Metro DPR - 01!10!21
Pune Metro DPR - 01!10!21
CKT 1
PRIORITY 2 PEGASUS SS - INFOSYS SS PRIORITY 3 INFOSYS SS - HINJ P1 SS
SN Item L1 L2 L3 L4 L5 L6 L7 L8 L9 L10 L11 L12 L13 L14 L15 L16 L17 L18 Total
1 Target date for charging 9/15/2021 10/5/2021
2 Route length 414 411 450 421 431 391 411 406 426 426 406 412 462 466 431 531 541 491 7,927
3 Cable Length 1,296 1,260 1,377 1,290 1,320 1,200 1,260 1,245 1,305 1,305 1,245 1,290 1,440 1,425 1,320 1,620 1,650 1,620 24,468
3 Excavation, including HDD 414 411 - - - 460 440 450 185 213 406 360 - - - - - 232 3,571
4 Sand Bedding - - - - - - - - - - -
a 100 mm 414 411 - - - 391 411 406 - - - - - - - - - - 2,033
b 400 mm 414 411 391 411 406 2,033
5 Cable placement 1,296 1,260 - - - 1,200 1,260 1,245 - - - - - - - - - - 6,261
6 Tile placement 414 411 - - - 391 411 406 - - - - - - - - - - 2,033
7 Backfilling 414 411 - - - 391 411 406 - - - - - - - - - - 2,033
8 Jointing
CKT 2
PRIORITY 1 PEGASUS SS - HINJ P2 SS PRIORITY 4 HINJ P2 SS - HINJ P1 SS
SN Item L1 L2 L3 L4 L5 L6 L7 L8 L9 L10 L11 L12 L13 L14 L15 L16 L17 L18 Total
1 Target date for charging 8/10/2021 10/31/2021
a Route length 440 441 437 421 431 441 441 451 462 572 551 561 561 566 546 516 536 501 8,875
Cable Length 1,374 1,350 1,338 1,290 1,320 1,350 1,350 1,380 1,440 1,770 1,680 1,710 1,710 1,725 1,665 1,575 1,635 1,650 27,312
3 Excavation, including HDD 440 441 435 370 - 441 441 451 185 213 406 360 - - - - - 232 4,415
4 Sand Bedding -
a 100 mm 440 441 - - - 441 441 451 - - - - - - - - - - 2,214
b 400 mm 440 441 441 441 451 2,214
5 Cable placement 1,374 1,350 - - - 1,350 1,350 1,380 - - - - - - - - - - 6,804
6 Tile placement 440 441 - - - 441 441 451 - - - - - - - - - - 2,214
7 Backfilling 440 441 - - - 441 441 451 - - - - - - - - - - 2,214
8 Jointing
DAILY PROGRESS REPORT Date: 01/10/2021
PROJECT : Project Management Consultant (PMC) for Utility shifting for Pune Metro, Pune
Sr No Document Received Under Preparation Tender under preparation Finalization of Tender document for publish
C - Status of Invoice
Sr No Received to PMC Name of Contractors Observation Remarks
TUV SUD / Pune Metro -PMC Daily Progress Report / 001 Ver 0.0 /dt.01-02-2021
DAILY PROGRESS REPORT Date: 01/10/2021
PROJECT : Project Management Consultant (PMC) for Utility shifting for Pune Metro, Pune
3) Joint Bay
1) JB -08 & JB -11 Brick work completed and plastering 2)
a) JB-08 CKT-2 cleaning work in progress at L1 section b) JB-11 CKT -
JB -08 & JB -11 - 06 nos Earth pit with Grid lines
1 cleaning work completed
completed
1) JB -07 & JB -10 Brick work completed and plastering 2)
- JB -07 & JB -10 - 06 nos Earth pit with Grid lines
completed
1) JB -06 - Manual Excavation work in progress (Section
-
L6-L7)
4) MDN Tower
TUV SUD / Pune Metro -PMC Daily Progress Report / 001 Ver 0.0 /dt.01-02-2021
DAILY PROGRESS REPORT Date: 01/10/2021
PROJECT : Project Management Consultant (PMC) for Utility shifting for Pune Metro, Pune
TUV SUD / Pune Metro -PMC Daily Progress Report / 001 Ver 0.0 /dt.01-02-2021
DAILY PROGRESS REPORT Date: 01/10/2021
PROJECT : Project Management Consultant (PMC) for Utility shifting for Pune Metro, Pune
1 Section L12 Excavation Work Excavation work is in progress at L12 section near Infosys substation
2 Section L12 Trench Dressing work Trench dressing work at L12 section near Infosys substation
5 Section L6 Earthing pit Earthing work at ckt2/JB3 L6 section. Depth of earthing pit 3 meter
TUV SUD / Pune Metro -PMC Daily Progress Report / 001 Ver 0.0 /dt.01-02-2021
DAILY PROGRESS REPORT Date: 01/10/2021
PROJECT : Project Management Consultant (PMC) for Utility shifting for Pune Metro, Pune
L11 section, road access closed by RCPL contractor during the trench
6 Hinjewadi Phase 2 Road access closed
excavation at road side.
TUV SUD / Pune Metro -PMC Daily Progress Report / 001 Ver 0.0 /dt.01-02-2021
PROJECT : Project Management Consultant (PMC) for Utility shifting for Pune M
Width Detail on L8 section
Length up Length up Length up
Length up to 2 to to 4 to 5
Sr.No. Total
meter width 2.5 meter meter meter
width width width
1 60 147 147 82 436
Direct
(Road
HDD with
Direct HDD with Normal Cutting )
Normal 200 mm
Footpath 200 mm HDPE cable Normal cable
cable trench HDPE
1 reparing work pipe road trench trench width
length in pipe road
length in meter meter crossing length length in crossing 1.6 meter
in meter meter length in
length in
meter meter
PROJECT : Project
Width in
Sr. No L1 Width in meter L3 meter L4
1 Road Cutting 0
2 Footpath Cutting 270 0.9
3 HDD 0 138 2
4 Embakment 269 1.6 210 2 210
5 Total 539 348 210
or Utility shifting for Pune Metro, Pune
section
nagement Consultant (PMC) for Utility shifting for Pune Metro, Pune
L8 Section L9 Section L10 Section L11 Section
Direct Direct
(Road (Road (Road
Direct Direct burried Cutting ) burried
(Road Cutting Cutting ) Cutting )
Normal HDD with Normal
HDD with cable in Normal cable in
)Normal Normal
200 mm 200 mm HDPE HDPE
cable trench cable cable cable cable
HDPE HDPE pipe for pipe for
width 3- trench trench trench trench
pipe road pipe road open cut open cut
4meter width 4-5 length in crossing width 1.6 crossing road width 1.6 road
length in meter meter meter meter crossing
length in length in crossing
meter length in meter length in meter length in length in length in
meter meter meter
meter meter
PROJECT : Project Management Consultant (PMC) for Utility shifting for Pune Metro, Pune
Width in Width in Width in Width in Width in
meter L5 meter L6 meter L7 meter L8 meter
229 3 to 5
50 2
2 405 2.7 428 2
50 405 428
L12
Section
(Road
Cutting )
Normal
cable
trench
width 1.6
meter
length in
meter
282
282 537
115 2 90 2 18 2