Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 9

CUMULATIVE PROGRESS AS ON DATE

CKT 1
PRIORITY 2 PEGASUS SS - INFOSYS SS PRIORITY 3 INFOSYS SS - HINJ P1 SS
SN Item L1 L2 L3 L4 L5 L6 L7 L8 L9 L10 L11 L12 L13 L14 L15 L16 L17 L18 Total
1 Target date for charging 9/15/2021 10/5/2021
2 Route length 414 411 450 421 431 391 411 406 426 426 406 412 462 466 431 531 541 491 7,927
3 Cable Length 1,296 1,260 1,377 1,290 1,320 1,200 1,260 1,245 1,305 1,305 1,245 1,290 1,440 1,425 1,320 1,620 1,650 1,620 24,468
3 Excavation, including HDD 414 411 - - - 460 440 450 185 213 406 360 - - - - - 232 3,571
4 Sand Bedding - - - - - - - - - - -
a 100 mm 414 411 - - - 391 411 406 - - - - - - - - - - 2,033
b 400 mm 414 411 391 411 406 2,033
5 Cable placement 1,296 1,260 - - - 1,200 1,260 1,245 - - - - - - - - - - 6,261
6 Tile placement 414 411 - - - 391 411 406 - - - - - - - - - - 2,033
7 Backfilling 414 411 - - - 391 411 406 - - - - - - - - - - 2,033
8 Jointing

CKT 2
PRIORITY 1 PEGASUS SS - HINJ P2 SS PRIORITY 4 HINJ P2 SS - HINJ P1 SS
SN Item L1 L2 L3 L4 L5 L6 L7 L8 L9 L10 L11 L12 L13 L14 L15 L16 L17 L18 Total
1 Target date for charging 8/10/2021 10/31/2021
a Route length 440 441 437 421 431 441 441 451 462 572 551 561 561 566 546 516 536 501 8,875
Cable Length 1,374 1,350 1,338 1,290 1,320 1,350 1,350 1,380 1,440 1,770 1,680 1,710 1,710 1,725 1,665 1,575 1,635 1,650 27,312
3 Excavation, including HDD 440 441 435 370 - 441 441 451 185 213 406 360 - - - - - 232 4,415
4 Sand Bedding -
a 100 mm 440 441 - - - 441 441 451 - - - - - - - - - - 2,214
b 400 mm 440 441 441 441 451 2,214
5 Cable placement 1,374 1,350 - - - 1,350 1,350 1,380 - - - - - - - - - - 6,804
6 Tile placement 440 441 - - - 441 441 451 - - - - - - - - - - 2,214
7 Backfilling 440 441 - - - 441 441 451 - - - - - - - - - - 2,214
8 Jointing
DAILY PROGRESS REPORT Date: 01/10/2021

PROJECT : Project Management Consultant (PMC) for Utility shifting for Pune Metro, Pune

Location: Pune Metro Line -3 -Shivaji Nagar to Hinjewadi


Construction Agency : M/S Rahul Cable Pvt. Ltd.
FILE REF :
A - Meetings
Sr No Location Dept. Name & Officials Action Point Remarks

1 N.A N.A N.A N.A

B - Tender preparation for Phase – II

Sr No Document Received Under Preparation Tender under preparation Finalization of Tender document for publish

1 PML3_US_EHLV02 N.A Tender Documents already submitted to PICMRL

2 PML3_US_EHWDS01 N.A. N.A Tender Documents already submitted to PICMRL

C - Status of Invoice
Sr No Received to PMC Name of Contractors Observation Remarks

1 N.A N.A N.A N.A

TUV SUD / Pune Metro -PMC Daily Progress Report / 001 Ver 0.0 /dt.01-02-2021
DAILY PROGRESS REPORT Date: 01/10/2021

PROJECT : Project Management Consultant (PMC) for Utility shifting for Pune Metro, Pune

Location: Pune Metro Line -3 -Shivaji Nagar to Hinjewadi


Construction Agency : M/S Rahul Cable Pvt. Ltd.
FILE REF :
A - Meetings
Sr No Location Dept. Name & Officials Action Point Remarks

D - Daily Site Progress


Sr. No Particulars of Work Total Scope Today's Progress (Meter) Executed Quantity (in Km)Till Date
2.4 Package A4 - Civil -
1) Trench Work
Trench Excavation in
Section L11 - 60 mtr including road crossing. Road crossing done infront
a) all types of Soil ( in 8.80
of Infosys Gate no 06 - 18 mtr
Kms)

100 mm Sand Bedding


b) 8.80 S
(KM)
220kV Cable Laid Included in Cumulative sheet
c) 51.10 0
(KM)
400mm Sand Bedding
d) 8.80 0
(KM)
e) RCC Tiles laying 8.80 0
f) Backfilling 8.80 0

12) HDD Work

a) Phase - 1 0.00 At 'T' Junction, HDD activity completed

Damaged 220 Kv cable JB. No work in progress /Near


fault location manual excavation under progress /JB-3/8
CKT-1/2 / Section L10 - Near Grand Tamanna hotel, from
OET SS JB-3/8 CKT-1/2 a) 18 inches of reamer is in
Section L10 - While doing 24 inches of reamer, reamer got stuck in
b) Phase - 2 0.00 progress by HDD team /Section L10 - Near Grand
hardrock . Now 16 inches reamer is in progress
Tamanna Hotel, from OET SS JB-3/8 CKT-1/2 a) 24
inches of reamer is in progress by HDD Team b) HDPE
jointing work is in progress c0 Road cfrossing done near
amazon ware house - 6 mtr length

1) L9 Sec: On MSETCL request Cable trench backfilling in


c) Phase - 3 0.00 - progress near substation. HDD pilot drilling work in
progress.

3) Joint Bay
1) JB -08 & JB -11 Brick work completed and plastering 2)
a) JB-08 CKT-2 cleaning work in progress at L1 section b) JB-11 CKT -
JB -08 & JB -11 - 06 nos Earth pit with Grid lines
1 cleaning work completed
completed
1) JB -07 & JB -10 Brick work completed and plastering 2)
- JB -07 & JB -10 - 06 nos Earth pit with Grid lines
completed
1) JB -06 - Manual Excavation work in progress (Section
-
L6-L7)
4) MDN Tower

TUV SUD / Pune Metro -PMC Daily Progress Report / 001 Ver 0.0 /dt.01-02-2021
DAILY PROGRESS REPORT Date: 01/10/2021

PROJECT : Project Management Consultant (PMC) for Utility shifting for Pune Metro, Pune

Location: Pune Metro Line -3 -Shivaji Nagar to Hinjewadi


Construction Agency : M/S Rahul Cable Pvt. Ltd.
FILE REF :
A - Meetings
Sr No Location Dept. Name & Officials Action Point Remarks

Curing on Concrete for Stubs in progress / Curing for


foundation is in progress./ Raft foundation and stub
No work at site curing,site cleaning done /Back filling with excavated
material under progress./Back filling under progress and
material procurement for cable trench under progress

TUV SUD / Pune Metro -PMC Daily Progress Report / 001 Ver 0.0 /dt.01-02-2021
DAILY PROGRESS REPORT Date: 01/10/2021

PROJECT : Project Management Consultant (PMC) for Utility shifting for Pune Metro, Pune

Location: Pune Metro Line -3 -Shivaji Nagar to Hinjewadi


Construction Agency : M/S Rahul Cable Pvt. Ltd.
FILE REF :
A - Meetings
Sr No Location Dept. Name & Officials Action Point Remarks

E - Daily Site Observations


Sr No Area / Location Work Description Observation on Quality of Work Photo

1 Section L12 Excavation Work Excavation work is in progress at L12 section near Infosys substation

2 Section L12 Trench Dressing work Trench dressing work at L12 section near Infosys substation

Warning tape laying and backfilling work in progress at L8 section /


3 Section L8 Warning Tape laying and backfilling
Warning tape laid in the trench at L8 section

4 Hinjewadi Phase 3 Cleaning work Cleaning work at JB 8

5 Section L6 Earthing pit Earthing work at ckt2/JB3 L6 section. Depth of earthing pit 3 meter

TUV SUD / Pune Metro -PMC Daily Progress Report / 001 Ver 0.0 /dt.01-02-2021
DAILY PROGRESS REPORT Date: 01/10/2021

PROJECT : Project Management Consultant (PMC) for Utility shifting for Pune Metro, Pune

Location: Pune Metro Line -3 -Shivaji Nagar to Hinjewadi


Construction Agency : M/S Rahul Cable Pvt. Ltd.
FILE REF :
A - Meetings
Sr No Location Dept. Name & Officials Action Point Remarks

L11 section, road access closed by RCPL contractor during the trench
6 Hinjewadi Phase 2 Road access closed
excavation at road side.

MDN Tower - 28 days cube test M20 grade test in progress at


7 Hinjewadi Phase 1 28 days cube testing
Siddhivinayak RMC plant

TUV SUD / Pune Metro -PMC Daily Progress Report / 001 Ver 0.0 /dt.01-02-2021
PROJECT  : Project Management Consultant (PMC) for Utility shifting for Pune M
Width Detail on L8 section 
Length up Length up Length up
Length up to 2 to to 4 to 5
Sr.No. Total
meter width  2.5  meter meter meter
width  width  width 
1 60 147 147 82 436

PROJECT  : Project Management Consultant (PMC


Sr.No. L1 Section L3 Section L4 Section L5 Section L7 Section

Direct
(Road
HDD with
Direct HDD with Normal Cutting )
Normal 200 mm
Footpath 200 mm HDPE cable Normal cable
cable trench HDPE
1 reparing work pipe road trench trench width
length in pipe road
length in meter meter crossing length length in crossing 1.6 meter
in meter meter length in
length in
meter meter

1 270 210 138 210 50 371


Total 270 210 138 210 50 371

PROJECT  : Project
Width in
Sr. No L1 Width in meter L3 meter L4
1 Road Cutting 0
2 Footpath Cutting 270 0.9
3 HDD 0 138 2
4 Embakment 269 1.6 210 2 210
5 Total 539 348 210
or Utility shifting for Pune Metro, Pune 
section 

nagement Consultant (PMC) for Utility shifting for Pune Metro, Pune 
L8 Section L9 Section L10 Section L11 Section

Direct Direct
(Road (Road (Road
Direct Direct burried Cutting ) burried
(Road Cutting Cutting ) Cutting )
Normal HDD with Normal
HDD with cable in Normal cable in
)Normal Normal
200 mm 200 mm HDPE HDPE
cable trench cable cable cable cable
HDPE HDPE pipe for pipe for
width 3- trench trench trench trench
pipe road pipe road open cut open cut
4meter width 4-5 length in crossing width 1.6 crossing road width 1.6 road
length in meter meter meter meter crossing
length in length in crossing
meter length in meter length in meter length in length in length in
meter meter meter
meter meter

147 82 150 115 165 60 6 530 18


229 265 231 548

PROJECT  : Project Management Consultant (PMC) for Utility shifting for Pune Metro, Pune 
Width in Width in Width in Width in Width in
meter L5 meter L6 meter L7 meter L8 meter
229 3 to 5

50 2
2 405 2.7 428 2
50 405 428
L12
Section

(Road
Cutting )
Normal
cable
trench
width 1.6
meter
length in
meter

282
282 537

Pune Metro, Pune 


Width in Width in Width in Width in Width in
L8 meter L9 meter L10 meter L11 meter L12 meter
175 2 165 2 530 2 282 2

115 2 90 2 18 2

115 225 548 282

You might also like