Professional Documents
Culture Documents
Week #3 Bangka - FINAL
Week #3 Bangka - FINAL
2
GRID STRUCTURE
LP
GI KOBA
1x30 MVA
G
2
LP
PROV. SUMATERA LP
SELATAN 3
LOAD SHAPE 2018
4
GENERATOR PORTFOLIO
5
DECEMBER 2018 DISPATCH
PLTUs derated to
Blackout 2/3 of full capacity
on Dec 11
6
GENERATION COST
7
RENEWABLE ENERGY POTENTIAL (1)
Biogas
• Cheapest and most promising
technology: POME-EFB
cofermentation
• Processing of mill POME and EFB
residues; no extra biomass needs
to be bought and transported
• Capacity of largest 7 mills:
430 tons/hour
• Potential of generation capacity:
30.8 MW
9
GENERATOR PROPERTIES BANGKA
10
GAS ENGINES AND RENEWABLES
12
SCENARIOS (UPDATE)
Branch:
New coal unit online Economic optimization
2022 Compare results
Compare results
14
TECHNOLOGY OPTIONS
• Coal
• 2 x 30 MW PLTU Air Anyir
• Potentially 2 x 50 MW PLTU Bangka (currently planned)
15
ECONOMIC OPTIMIZATION
16
INPUTS (1)
• PV: Current cost estimates from Indonesian PV developer and other source; cost
reductions according to IRENA projections
• Other technology options based on obtained historical data
• Fuel prices based on average values of 2018
17
INPUTS (2)
COSTS
FUEL
2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029
Diesel Inflation 0.605 0.629 0.654 0.680 0.707 0.736 0.765 0.796 0.828 0.861 0.895 0.931
(USD/litre) 2018 value 0.605 0.605 0.605 0.605 0.605 0.605 0.605 0.605 0.605 0.605 0.605 0.605
B20 diesel Inflation 0.603 0.627 0.652 0.678 0.705 0.733 0.762 0.793 0.825 0.858 0.892 0.928
(USD/litre) 2018 value 0.603 0.603 0.603 0.603 0.603 0.603 0.603 0.603 0.603 0.603 0.603 0.603
Coal Inflation 0.046 0.048 0.050 0.052 0.054 0.057 0.059 0.061 0.064 0.066 0.069 0.072
(USD/kg) 2018 value 0.046 0.046 0.046 0.046 0.046 0.046 0.046 0.046 0.046 0.046 0.046 0.046
Gas price Inflation 12 12 13 13 14 15 15 16 16 17 18 18
(USD/BTU) 2018 value 12 12 12 12 12 12 12 12 12 12 12 12
• Difficult to predict, but diesel will only play a minor role on Selayar in the future
• It is relatively sure that diesel will not become cheaper in the future
• Gas prices rose from 12 to 13 USD per mBTU during the course of the project
18
MODEL VALIDATION
19
BUSINESS AS USUAL (NO PV/BIOGAS) (1)
20
REALISTIC SCENARIO
21
OPTIMIZATION TO REALISTIC SCENARIO (1)
22
LCOE TECHNOLOGY COMPARISON
23
REALISTIC SCENARIO (2)
• COE reductions with renewables already in the short-term, increasing potential in the long-term
• In 2022-23, the PV/biogas replaces mostly generation coming from the new 2x50 MW PLTUs
and doesn‘t have a high cost advantages compared to the PLTU
24
REALISTIC SCENARIO (3)
FIT range
w/o grid
FIT w/grid
Conclusions
• Both PV and biogas can be tendered to IPPs right away if there is no cable
• With the cable, PV IPPs can be remunerated at 85% starting 2021
• Biogas is slightly above the 85 % rule, BUT it is still cheaper than any PLN generation
25
REALISTIC SCENARIO (4)
• The share of renewables on the electricity generation quickly rises to 20% and
stays relatively constant
• Due to limited bio resources the share of biogas decreases over time, PV shares
increase
• Installation capacities are similar for grid and no-grid scenario. Hence, also RE
shares are very similar
26
TECHNICAL ISSUES (EXAMPLES)
27
SPINNING RESERVE FOR PV (2)
• #1: If gas engines or diesels are already online, reduce their output (diesel before gas).
• #2: Reduce coal power output, minimum output is 80 % (20 % can be activated within 5 minutes).
• #3: Reduce biogas output by 20 – 50 %.
• #4: Dispatch additional gas engines at 50 % output (they could likely go lower in reality).
• #5: Curtail PV.
More than 20 % of PV
covered withing 5
minutes, more than 10 %
within 30s
30
LVRT ENVELOPE
• Based on the fault clearing times (provided by PLN) and the voltage return (simulation),
this LVRT envelope was developed for PV.
• It is less strict than the ones in larger system grid codes and will thus be easily available
from inverter manufacturers.
• Without LVRT, a short-circuit may lead to the loss of a large share of PV = system crash
31
DISPATCH EXAMPLE: ISLAND 2025
32
IMPLEMENTATION PLAN
33
GENERAL STRATEGY
34
OPTIMAL PV DISTRIBUTION (1)
GI AIR ANYIR
entire island LP
1x60 MVA
GI KOBA
presentation) 1x30 MVA
35
OPTIMAL PV DISTRIBUTION (2)
Recommendations:
36
DISTRIBUTION OF BIOGAS UNITS
Biogas distribution is determined by potential. In the grid model, none of the sites
showed any problems with the grid connection (almost always 20 kV).
37
THANK YOU FOR YOUR ATTENTION
38