Professional Documents
Culture Documents
Table of Contents: Method Statement FOR Electrical Galvanized Conduits Installation
Table of Contents: Method Statement FOR Electrical Galvanized Conduits Installation
Table of Contents: Method Statement FOR Electrical Galvanized Conduits Installation
FOR
ELECTRICAL GALVANIZED CONDUITS INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1.SCOPE
This procedure to clear the method of the supply, installations of
Electrical Galvanized Conduits for the project.
This document details Electrical Galvanized Conduits Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
4. OPERATION
Material:
Installation:
No conduit smaller than 20mm in diameter or larger than 32mm
diameter shall be used.
Where a terminal block to be accommodated in the circuit box an
extension ring shall be provided.
Draw-in conduit boxes shall be incorporated at intervals not
exceeding:
Straight run - 10 m.
Commissioning:
When conduits are run on shuttering, prior to the laying of concrete
insitu, additional security must be provided near to every box and at
intervals of not more than 1.2 meters by binding short lengths of
steel wire, of not less than 2mm diameter twisted around the
conduit and reinforcing steel. The conduits shall be adequately fixed
to prevent excessive movement and damage during the pouring
and setting of concrete and shall be protected from mechanical
damage. Check there is no damage before screed / concrete is
poured. Unless otherwise indicated to cast in conduits shall not be
less than 30mm.cores to plastered over conduits shall not be less
than 5mm.
Where conduits are left "open ended" prior to wiring they shall be
protected by caps or plugs to prevent the ingress of building
material.
Ensure conduits are not concealed until works has been inspected
and approved. Ensure that conduit and fittings buried in concrete or
behind plaster are protected against corrosion or electrolytic action
prior to rendering.
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the
system after the installation is completed.
This instruction shall be scheduled at the convenience of the
staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shopdrawings and specs and manufacturer recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
Electrical Galvanized Conduits Components and Accessories
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Electrical Galvanized Conduits
Installation will be as follows:
Painting Brush
Measuring tape
Cutting plier
Threading Machine
Box spanner set
Bending Machine
Pipe Wrench
Drilling Machine
Round files
Bench vise
Tripod stand wise
The Rubbish which would be created from our scope of works will be
disposed to the designated dumping ground.
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper