Table of Contents: Method Statement FOR Electrical Galvanized Conduits Installation

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 9

METHOD STATEMENT

FOR
ELECTRICAL GALVANIZED CONDUITS INSTALLATION

 TABLE OF CONTENTS

1. SCOPE

2. DEFINITIONS

3. HEALTH AND SAFETY

4. OPERATION

5. INSTALLATION AND FIXATION

6. RESPONSIBILITIES

7. MANPOWER REQUIRED

8. MATERIALS REQUIREMENTS

9. EQUIPMENTS REQUIREMENTS

10. WASTE MANAGEMENT

11. SPECIAL CONTROL MEASURES.

12. SUPPORTING DOCUMENTATION

13. DISTRIBUTION
1.SCOPE
 This procedure to clear the method of the supply, installations of
Electrical Galvanized Conduits for the project.
 This document details Electrical Galvanized Conduits Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.

2. DEFINITIONS
PQP : Project Quality Plan

PSP : Project Safety Plan

QCP : Quality Control Procedure

HSE : Health, Safety and Environment

MS : Method Statement

ITP : Inspection Test Plan

QA/QC : Quality Assurance / Quality Control Engineer.

WIR : Inspection and Test Request

MIR : Material Verification Record.

3. HEALTH AND SAFETY


 Strictly followed as per the manufacturer's Health and Safety
recommendations for handling and use of the materials.
 Ensure all involved personnel shall be aware of the same.
 Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.

4. OPERATION
 Material: 

 Material used will be as approved by the Engineer.


 The sizes and routes routing will be as per the approved Shop
Drawings.

 Storage and Protection: 


 Deliver components parts to site, completely identified in accordance
with shop and certified CAD Drawings prepared for this work.

 Store in accordance with the manufacturer’s instructions, above


ground, properly protected from the weather and construction activities.

5. INSTALLATION AND FIXATION


 Pre-Installation:
 All materials and documentation relevant to this particular section of
works will be checked and verified ensuring that these are correct
and approved type.

 Prior to the commencement of works, ensure that the areas for


permanent installation are ready, accessible and in suitable
condition.

 Installation:
 No conduit smaller than 20mm in diameter or larger than 32mm
diameter shall be used.
 Where a terminal block to be accommodated in the circuit box an
extension ring shall be provided.
 Draw-in conduit boxes shall be incorporated at intervals not
exceeding:

 Straight run - 10 m.

 Run with four bends - 2.5 m.

 Run with three bends - 5 m.

 Run with one or two bends - 10 m.

 Conduits, which are more than slightly damaged, shall be rejected.


Conduits in floors shall be routed and installed so as to avoid the
fixings of floor standing equipment to be installed on the floor.
 All joints in PVC conduits, other than screwed joints, shall be
cemented with a waterproof adhesive. This adhesive shall be as
recommended by the conduit manufacturer.
 Screwed connections between steel conduits and accessories shall
be screwed up tight , where coupled by a socket the conduit ends
shall butt together; running joints shall be provided with back nuts
which shall be screwed up tight.
 PVC conduit shall be saddled at a minimum of 1 meter intervals. All
saddles, tubes and boxes must be in perfect alignment to avoid any
appearance of warping when the installation is complete. Saddles
should not be so tight as to prevent expansion of the conduit.
 Steel conduits run on the surface shall be secured with galvanized
saddles spaced not mores than 2 meters apart, on the other hand,
a space bar type saddles will NOT be permitted.
 Conduits shall not be run closer than 0.15m to any steam or hot
water pipes and shall be run underneath such pipes rather than
over them. It should not also be run closer than 0.05m to any
telephone, bell or other signaling circuit.
 No wiring or draw-in wires, cables or wire of any description are to
be drawn into the conduits until the section of the conduit system
involved is complete.
 Drawn-in boxes must be provided to give access to all conduit for
the drawing-in or out of any cable after the installation is completed.
 Particular care shall be taken to ensure that no grout or other
foreign materials enters the conduit system through joints, or
through surface openings. Screw holes in boxes must kept entirely
free and clean. After screeding, a compressed air is to be blown
through the conduit system to ensure that it is clean and a steel
draw wire of adequate size to be pulled through to a certain that no
obstructions is adhering to the inside of the conduits.

 Commissioning:
 When conduits are run on shuttering, prior to the laying of concrete
insitu, additional security must be provided near to every box and at
intervals of not more than 1.2 meters by binding short lengths of
steel wire, of not less than 2mm diameter twisted around the
conduit and reinforcing steel. The conduits shall be adequately fixed
to prevent excessive movement and damage during the pouring
and setting of concrete and shall be protected from mechanical
damage. Check there is no damage before screed / concrete is
poured. Unless otherwise indicated to cast in conduits shall not be
less than 30mm.cores to plastered over conduits shall not be less
than 5mm.

 Where conduits are left "open ended" prior to wiring they shall be
protected by caps or plugs to prevent the ingress of building
material.

 All conduits runs must be designed to permit wiring to be readily


installed after the complete erection of the conduits through the
available draw-in, accessory and luminary suspension boxes.

 Where surface mounted equipment (other than luminaries) is


specified, all concealed conduits shall be terminated and an
adaptable box installed recessed into the wall at every surface
mounted equipment position.
 Where conduits pass through an external wall/roof the conduit box
shall be fitted on the side and after wiring filled with an inert,
permanently plastic compound having a high insulation value.

 Make provision in conduit and trunking, installation where building


expansion joints are crossed or settlement is likely

 Ensure conduits are not concealed until works has been inspected
and approved. Ensure that conduit and fittings buried in concrete or
behind plaster are protected against corrosion or electrolytic action
prior to rendering.

 Technical Assistance:
 The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the
system after the installation is completed.
 This instruction shall be scheduled at the convenience of the
staff.
 All such instruction shall be properly recorded.
 WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shopdrawings and specs and manufacturer recommendations.

6. RESPONSIBILITIES

 PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.

2. To ensure that the progressing of works is carried out according


to the planned program and as per the approved method of
statement.

3. To ensure that all the equipment and material required


executing the work are available according to the planned
construction program.

4. To co-ordinate with the Main contractor, MEP coordinator,


Safety Officer for a safe and proper execution of the works.

 SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.

2. To provide all necessary information and distribute


responsibilities to his construction.

3. To monitor the progress of work in relation with the work


program and to report to the Project Manager.

4. To co-ordinate with the safety officer and to ensure that the


works are carried out in safe practicing method.

 FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.

2. To ensure that his assistant foreman/ charge hand are aware of


the job requirements and they have enough information to carry
out their duties properly.

3. To ensure that the daily work is progressing as planned and


advice the site engineer of any requirement for additional
resources.

4. To ensure in consultation with the site engineer that the


manpower involved in the works are moving as agreed and
planned for the work.

5. To control disposal of waste materials according to the


instructions received from the site engineer.

6. To ensure full coordination with the safety officer to maintain


safe working and proper house keeping of the site, following the
proved safety measures and further ensure that all his working
team are aware of the same to prevent accident and losses.

7. To inform the site engineer regarding areas ready for inspection.

8. Foreman and the storekeeper are responsible for the distribution


and control of materials.

 SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.

2. Ensure all the implemented safety measures are adequate to


maintain safe working on the site.

3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.

4. Ensure that the site is maintained clean and tidy.

 TECHNICIAN FROM SUPPILER


1. The carrying-out of work and the proper distribution of all the
available resources in coordination with the sub-contractor
Site Engineer on a daily basis.
2. Daily reports of the works are achieved and coordinated for
the future planning with the Site Engineer.
3. Complying with the sub-contractor basic design practices,
particularly those related to safety and engineering
4. Meeting with any type of unforeseen incident or requirement
and reporting the same to the Site Engineer immediately.

 STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.

7. MANPOWER REQUIRED
 Charge hand and Experienced Technicians

8. MATERIALS REQUIREMENTS
 Electrical Galvanized Conduits Components and Accessories

9. EQUIPMENTS REQUIREMENTS
 The Equipment that will be engaged for Electrical Galvanized Conduits
Installation will be as follows:
 Painting Brush
 Measuring tape
 Cutting plier
 Threading Machine
 Box spanner set
 Bending Machine
 Pipe Wrench
 Drilling Machine
 Round files
 Bench vise
 Tripod stand wise

10. WASTE MANAGEMENT

 The Rubbish which would be created from our scope of works will be
disposed to the designated dumping ground.

11. SPECIAL CONTROL MEASURES


 The following general control measures against Safety, Environment and
Quality shall be required for our scope of work and special control
measures are not applicable for us :

 Proper PPE must be worn at all time


 Permit to work at height > 2m where applicable
 Lifting operation permit (using crane) where applicable.
 Confined space permit where applicable.
 Approved work method statement and risk assessment will be made
available to site.
 All workers doing the work shall be briefed on this method statement
and risk assessment.

12. SUPPORTING DOCUMENTATION


 This method Statement should be read in conjunction with the below
referenced documentations:

 ITP for Anti – termite Treatment.

 Insulation Resistance and continuity Test Report.


13. DISTRIBUTION
 Copy of this method statement shall be issued to the following for
information / action / comments:

1. Project Manager

2. Site Engineer

3. Foremen

4. Safety Engineer

5. Technician From Supplier

6. Store Keeper

You might also like