The document describes 15 scenarios observed during an audit of various organizations. Issues included lack of supplier evaluation and risk assessment, failure to document how external and internal issues were determined and monitored, objectives not being met without defined completion or evaluation, inadequate analysis of resource constraints for increased demand, monitoring of complaints but no analysis or evaluation, risks and opportunities not being documented for maintenance, out of calibration equipment being used, preventive maintenance schedules not being followed, missing documentation for design verification, lack of approval for process parameters, and failure to demonstrate meeting customer requirements among other issues. Non-conformities were identified for various clauses of the ISO standard.
The document describes 15 scenarios observed during an audit of various organizations. Issues included lack of supplier evaluation and risk assessment, failure to document how external and internal issues were determined and monitored, objectives not being met without defined completion or evaluation, inadequate analysis of resource constraints for increased demand, monitoring of complaints but no analysis or evaluation, risks and opportunities not being documented for maintenance, out of calibration equipment being used, preventive maintenance schedules not being followed, missing documentation for design verification, lack of approval for process parameters, and failure to demonstrate meeting customer requirements among other issues. Non-conformities were identified for various clauses of the ISO standard.
The document describes 15 scenarios observed during an audit of various organizations. Issues included lack of supplier evaluation and risk assessment, failure to document how external and internal issues were determined and monitored, objectives not being met without defined completion or evaluation, inadequate analysis of resource constraints for increased demand, monitoring of complaints but no analysis or evaluation, risks and opportunities not being documented for maintenance, out of calibration equipment being used, preventive maintenance schedules not being followed, missing documentation for design verification, lack of approval for process parameters, and failure to demonstrate meeting customer requirements among other issues. Non-conformities were identified for various clauses of the ISO standard.
The document describes 15 scenarios observed during an audit of various organizations. Issues included lack of supplier evaluation and risk assessment, failure to document how external and internal issues were determined and monitored, objectives not being met without defined completion or evaluation, inadequate analysis of resource constraints for increased demand, monitoring of complaints but no analysis or evaluation, risks and opportunities not being documented for maintenance, out of calibration equipment being used, preventive maintenance schedules not being followed, missing documentation for design verification, lack of approval for process parameters, and failure to demonstrate meeting customer requirements among other issues. Non-conformities were identified for various clauses of the ISO standard.
Name of the Participant : Name of the organization :
Note : Identify non-conformity in following scenarios & corresponding clause No.
NC ISO SN Scenario Y/N Cl. No. Records of approval of Supplier M/S QualiTech, supplying very important raw material which may affect final product quality, were not available in purchase section. Purchase in-charge informed that the supplier is well 1. established for years and is rather only source in the country, thus evaluation was not carried out. Risk assessment of this supplier was also not available When the auditor enquired about determination of external and internal issues that are relevant to its strategic direction, Marketing and Product development process owners in an engineering organization gave two 2. different replies. When it was asked whether the information about the said issues is documented, monitored and reviewed both were unanimous that there was no such requirement defined in their QMS documentation and they do not have any evidence to demonstrate. It was observed in an Engineering organization in manufacturing function that three objectives out of five objectives were not achieved. When the auditor asked about the reasons thereof the department head replied that 3. they have not determined when it will be completed as well as how the results will be evaluated and monitored. He claimed that he had utter clarity about what needs to be done to achieve it as compared to other HODs. In an Engineering organization it was observed during audit that capabilities of and constraints on the existing internal resources; necessary for meeting the sudden increased demand of the Key OEM customer CC3 for supplying an important packing material PMXX3 , are not analysed. They were supplying 300 tonnes per month to CC3 and 4. suddenly demand stepped up to 700 tonnes per month for CC3. Marketing has committed to comply with the required delivery schedules without any discussion with production and QA team. Currently they are operating at 80 % capacity utilization and established capacity of plant is 1000 tonnes per month. The customer complaints were monitored in an organization. However the results of monitoring were neither analysed nor evaluated. When asked the top management claimed that they were directed to respective 5. departments and they may be retaining documented information about the results. He further stated that he was confident that the same complaint has never been repeated by the same customer twice and it was a very satisfactory situation.
Qualicon Services, Pune email: qualiconshripad@gmail.com Page 1 of 6
Plant Maintenance departments in a Engineering organisation had not documented the methodology to address the risks and opportunities wrt process outcomes. When asked to explain the scenario both stated that their activities are meticulously monitored and it was discussed and 6. decided in the earlier MRM and objectives are being constantly monitored. On time delivery analysis shown 30 % deliveries were not on time due to unexpected machines breakdowns and time taken to repair due to non availability of spares. Temperature controller cum indicator was being used during process control for controlling the temperature of a hazardous process step. When the auditor asked for the latest calibration certificate it was brought from 7. QA department. The auditor found that the cal certificate indicated that equipment was out of calibration. The production supervisor said that it was not his responsibility to ensure the validity of the calibration and there was no problem with the process control. Preventive maintenance schedule is not adhered to for two particular set of Compressors repeatedly every quarter. Few of the check points were not completed, and few of the Preventive Maintenance occasions were skipped. After analysis of the total breakdown of the plant , 60 % downtime 8. of the process is on account of the same Compressor and resulting to missing on time delivery to customers. Maintenance Engineer said its because of the repeated absenteeism of the experienced contract manpower and new person is not able to complete the workload within the stipulated time. Design and development Plans does not define the stage for Design verification. Records shown as evidence for design verification does not 9. verify all design output meet design input requirements. Methodology for design verification is not defined in design procedure for new product design and variant of existing product as well as for design change. Records of the approval of the process parameters in the paint shop were not available. The production In-charge stated that the parameters for the 10. process were given by their collaborators and hence no approval is required Recently in last quarter, as a part of Kaizen implementation, new material handling platform and a sizing fixture and few sensors are newly added in the current Assembly line machine and hence increasing the productivity of Assembly line by 20 % and reducing the internal rejection due to size 11. variation by 10 % but auditor could not get any evidence of Process change management, revised process control documents or production capacity documentation or Preventive maintenance of sensors of sizing fixtures. During a document review, the auditor notes that QD/QC/05,Rev. no. 03, incoming inspection checklist states that for material xx bending test is to 12. be carried out. When asked the QC inspector about the inspection report of the same, he replied that bending test is not carried out for last 6 months as the measurement device is under breakdown Qualicon Services, Pune email: qualiconshripad@gmail.com Page 2 of 6 Customer has defined acceptance criteria as 61 to 73 for Product characteristic PCC07 as per PO no. 200122 dated 01/12/2019. At the final product release point QPoint 12, at 2.00 p.m., auditor picks up random 5 samples for each lot of 100 ready products, asks the concerned QC person to verify the reading for Product characteristic PCC07 and later confirms reading between 72-75 for all 5 samples. After verifying for few 13. more batches in ready for dispatch condition , auditor confirmed the same deviation. Auditor asks for Final inspection and test records, and he is shown lot release records by authorized personnel for all 32 lots but no evidence is available to demonstrate that the lot met the customer specified requirements. After verifying it was noted that sixteen lots were already dispatched till 2 p,m and rest twenty lots were ready for dispatch . Records shows that Customer has raised more than 10 complaints in last Quarter on delayed deliveries and damages in transit but organization 14. could not demonstrate the Risk assessment for delivery delays and transit damages in Risk and opportunity register. Risk register is also not updated in last one year. Stores could not achieve their quality objectives of reducing the rejection of important chemical having shelf life of 3 months, from current 10 % level to 2 % level . After probing auditor could get the action plan for achieving the quality objectives but could not evidence of its completion as Stores did not get support of Purchase and maintenance team to do the necessary modification of racking system for FIFO implementation. When asked for 15. the reason for not providing needed support, Purchase and maintenance head said that they are unaware of such support to be provided for achieving Quality objectives of Stores, They did not have copy of the action plan and never remember of any such discussion in any meeting. There is no evidence of review by Stores head for achievement of Quality objectives.
Qualicon Services, Pune email: qualiconshripad@gmail.com Page 3 of 6
Audit report No. Sr. No.
Observation: ( What you have observed + Objective Evidence)
Attribution cum Explanation : ( Why its NC)
Audit report No. Sr. No.
Observation: ( What you have observed + Objective Evidence)
Attribution cum Explanation : ( Why its NC)
Qualicon Services, Pune email: qualiconshripad@gmail.com Page 4 of 6
Audit report No. Sr. No.
Observation: ( What you have observed + Objective Evidence)
Attribution cum Explanation : ( Why its NC)
Audit report No. Sr. No.
Observation: ( What you have observed + Objective Evidence)
Attribution cum Explanation : ( Why its NC)
Qualicon Services, Pune email: qualiconshripad@gmail.com Page 5 of 6
Audit report No. Sr. No.
Observation: ( What you have observed + Objective Evidence)
Attribution cum Explanation : ( Why its NC)
Audit report No. Sr. No.
Observation: ( What you have observed + Objective Evidence)
Attribution cum Explanation : ( Why its NC)
Qualicon Services, Pune email: qualiconshripad@gmail.com Page 6 of 6