Professional Documents
Culture Documents
Excavation Awareness Training
Excavation Awareness Training
IMS # 40-T008-000E
EXCAVATION
AWARENESS TRAINING
Slide 4
40-T008-000E Rev A 21.10.2017
EXCAVATION HAZARDS
Slide 5
40-T008-000E Rev A 21.10.2017
EXCAVATION HAZARDS
Cave-In:
• Means the movement of soil or rock into an excavation, or the
loss of soil from under a trench shield or support system, in
amounts large enough to trap, bury, or injure and immobilize a
person.
Collapse of Sides:
Slide 6
40-T008-000E Rev A 21.10.2017
EXCAVATION HAZARDS
Slide 7
40-T008-000E Rev A 21.10.2017
EXCAVATION HAZARDS
Some Other Excavation Hazards:
• Water Accumulation;
• Hazardous Atmosphere;
• Equipment Falls.
Slide 8
40-T008-000E Rev A 21.10.2017
EXCAVATION HAZARDS
Water Accumulation Hazards
Slide 9
40-T008-000E Rev A 21.10.2017
EXCAVATION HAZARDS
Hazardous Atmosphere
Test excavations more than 4
feet before an employee enters
into the excavation for:
• Oxygen deficiency;
• High combustible gas
concentration;
• High levels of other
hazardous substances.
Slide 10
40-T008-000E Rev A 21.10.2017
EXCAVATION HAZARDS
Slide 11
40-T008-000E Rev A 21.10.2017
EXCAVATION HAZARDS
Equipment falls
Slide 12
40-T008-000E Rev A 21.10.2017
EXCAVATION HAZARDS
Causes of Cave-Ins / Collapse of side
Slide 13
40-T008-000E Rev A 21.10.2017
EXCAVATION HAZARDS
Improper Means of Access
and Egress:
Slide 14
40-T008-000E Rev A 21.10.2017
EXCAVATION HAZARDS
Improper Means of Access
and Egress:
• These two ladders which are
lashed together are not an
adequate means of egress
The ladder should extend 3
feet above the top of the
excavation.
• Ladder cannot be joint
together unless it is
manufactured for that
purpose.
Slide 15
40-T008-000E Rev A 21.10.2017
INADEQUATE PROTECTION SYSTEM
Slide 16
40-T008-000E Rev A 21.10.2017
INADEQUATE PROTECTION SYSTEM
• This worker is in a
trench with no
protective system, that
is not sloped or
benched, no means of
egress and no PPE.
Slide 17
40-T008-000E Rev A 21.10.2017
HAZARDOUS CONDITION
• Telephone pole
adjacent to excavation,
not supported /
removed.
Slide 18
40-T008-000E Rev A 21.10.2017
HAZARDOUS CONDITION
• The weight and
vibrations of the
machinery above make
this a very hazardous
condition.
Slide 19
40-T008-000E Rev A 21.10.2017
EXCAVATION PROTECTION SYSTEM
It shall be a requirement of all projects to implement a
procedure that provides effective safety measures and methods
to protect personnel who are required to work in and around
excavations and trenches. Such methods include, but are not
limited to:
• Cave-in protection (sloping, shoring and shielding);
• Access and egress requirements;
• Edge protection (barriers, warning signs, etc.);
• Inspection requirements.
Slide 20
40-T008-000E Rev A 21.10.2017
EXCAVATION PROTECTION SYSTEM
Protection of Equipment Falling into Excavation
Slide 21
40-T008-000E Rev A 21.10.2017
EXCAVATION PROTECTION SYSTEM
There are 3 basic protective systems used in excavations
and trenches:
1. Sloping Systems;
2. Shoring Systems;
3. Shielding Systems.
Slide 22
40-T008-000E Rev A 21.10.2017
EXCAVATION PROTECTION SYSTEM
1. Sloping System
Slide 23
40-T008-000E Rev A 21.10.2017
EXCAVATION PROTECTION SYSTEM
1. Sloping System
SOIL / ROCK TYPE MAXIMUM SLOPE ANGLE HORIZONTAL TO
TO VERTICAL (ANGLE OF VERTICAL RATIO
REPOSE) (BENCHING)
STABLE ROCK 90 degree N/A
TYPE A 53 degree 0.75 to 1
TYPE B 45 degree 1 to 1
TYPE C 34 degree 1.5 to 1
Slide 24
40-T008-000E Rev A 21.10.2017
EXCAVATION PROTECTION SYSTEM
1. Sloping System
Slide 25
40-T008-000E Rev A 21.10.2017
EXCAVATION PROTECTION SYSTEM
1. Sloping System
Slide 26
40-T008-000E Rev A 21.10.2017
EXCAVATION PROTECTION SYSTEM
2. Shoring System
Slide 27
40-T008-000E Rev A 21.10.2017
EXCAVATION PROTECTION SYSTEM
2. Shoring System
Slide 28
40-T008-000E Rev A 21.10.2017
EXCAVATION PROTECTION SYSTEM
2. Shoring System – Timber Shoring
Slide 29
40-T008-000E Rev A 21.10.2017
EXCAVATION PROTECTION SYSTEM
2. Shoring System – Aluminum Hydraulic Shoring
Slide 30
40-T008-000E Rev A 21.10.2017
EXCAVATION PROTECTION SYSTEM
3. Shielding System
Trench Boxes:
• The space between the
outside of the trench box and
the face of the trench should
be as small as possible, and
backfilled to prevent
movement of the box.
Slide 31
40-T008-000E Rev A 21.10.2017
EXCAVATION PROTECTION SYSTEM
3. Shielding System – Trench Box
Slide 32
40-T008-000E Rev A 21.10.2017
EXCAVATION PROTECTION SYSTEM
Means Of Access and Egress
Excess with ladders:
• The ladder should be placed
always 3 feet extended from
the trench.
Excess by slope:
• Provide the slope as per the
type of soil by considering the
slope chart provided in
previous slide.
Slide 33
40-T008-000E Rev A 21.10.2017
EXCAVATION PROTECTION SYSTEM
Safety Requirements include, but are not limited to:
• Inspect the excavation and adjacent areas at least once
a day for possible cave in, failure of protective systems
and hazardous conditions.
Slide 34
40-T008-000E Rev A 21.10.2017
EXCAVATION PROTECTION SYSTEM
• Soil removed from an excavation and any other material
storage must be kept at least the same horizontal
distance away from the excavation edge as the total
depth.
• Excavations and trenches shall be appropriately
identified with signs, warnings and barricades.
• Barricades shall be kept at least 1.8 meters from open
edges of trenches and excavations.
• Support for excavations deeper than 20ft shall be
designed by a registered professional engineer.
• No Employee shall be permitted to work under lifting or
digging equipment.
Slide 35
40-T008-000E Rev A 21.10.2017
EXCAVATION PROTECTION SYSTEM
• Employees shall be required to stand away from any
vehicle being loaded or unloaded to avoid being struck
by any spillage or falling material.
Slide 36
40-T008-000E Rev A 21.10.2017
EXCAVATION PROTECTION SYSTEM
Barricade System
• Barricades are used to segregate areas on site and
protect employees from the hazards that may exist
within.
Slide 37
40-T008-000E Rev A 21.10.2017
EXCAVATION PROTECTION SYSTEM
Barricade System
Soft Barriers
• Use to prevent pedestrians entering a hazardous area i.e.
barricade around cranes.
• Must be of Neftlon fencing or other similar type.
• Red and White warning tape can be used.
Hard Barriers
• Used to provide physical protection around a hazard i.e.
excavations and trenches, working next to roadways must be
capable of withstanding potential force impacting upon it.
• Must be a complete physical barricade i.e. linked jersey barriers,
scaffold tubing, removed spoil mounds (if using spoil, soft
barricading also required to increase visibility).
Slide 38
40-T008-000E Rev A 21.10.2017
EXCAVATION PROTECTION SYSTEM
Barricade System
Soft Barriers Hard Barriers
Slide 39
40-T008-000E Rev A 21.10.2017
EXCAVATION PROTECTION SYSTEM
Barricade System
All barricading regardless of type, must:
• Be complete around the hazard;
• Be of sufficient height;
• Have clear access / egress ways;
• Be of sufficient strength to protect the hazard;
• Have sufficient anchorage to withstand wind speeds;
• Have signage fixed to the barrier to describe the hazard or usage of
the barrier;
• Must be set back a sufficient distance from the hazard;
• Be maintained and inspected daily.
Slide 40
40-T008-000E Rev A 21.10.2017
EXCAVATION PROTECTION SYSTEM
Barricade System
All barricading regardless of type, must:
• Provide guard rails and toe boards where necessary;
• Avoid spoil or other materials close to excavation – they could fall
in or cause sides to collapse;
• Wear hard hat in excavations.
Note: Where people may get onto the site out of hours, backfill or
cover excavations to reduce risks.
Slide 41
40-T008-000E Rev A 21.10.2017
IDENTIFY THE HAZARDS
Slide 42
40-T008-000E Rev A 21.10.2017
IDENTIFY THE HAZARDS
Slide 43
40-T008-000E Rev A 21.10.2017
IDENTIFY THE HAZARDS
Slide 44
40-T008-000E Rev A 21.10.2017
PLANT, TOOLS AND EQUIPMENT SAFETY
• All equipment's must have Inspection sticker clearly displayed;
• All equipment shall be sound and properly maintained all time;
• Shall have reverse horn and all mirrors clean and intact;
• Authorized and competent driver / operator;
• Operator to check equipment every day before start of work;
• Operator / Supervisor / Banks man to Check for no one is in the
line of fire;
• Check for ground condition, edges of excavation;
• Barricade the area of line of fire during excavation;
• Ensure hand tools are in good condition and are not home-made.
Slide 45
40-T008-000E Rev A 21.10.2017
ARCHEOLOGICAL FINDINGS
• All Excavations carried out on Qasr al Hosn project must have a
Flagman/Spotter present. He is responsible to monitor the
excavation to identify if any artifacts are discovered;
• During Excavation if you find any archeological items or Structures
all works need to stop immediately and report directly to the
Construction Manager and Safety Manager.
• The Excavation should have all equipment stop working and all
entrants must be out from the Excavation and work area barricaded
until it has been checked and reviewed by the Project Management.
Contact Numbers:
• Construction Manager – Mohamad Alaeddine – 0564103785;
• Safety Manager – Pankaj Ingale – 0547910947.
Page 46
40-T008-000E Rev A 21.10.2017
RISK CONTROL MEASURES
RISK / HAZARD CONTROL
Underground utilities Prepare an excavation permit for any activity that will break
ground.
Ensure that all utility avoidance measures have been taken.
If in doubt, hand dig the trial pit / trench to sufficient a depth to
expose any utilities that may be present..
Unexploded If unexploded ordnance is anticipated, do not commence work
ordnance until written advice that the issue has been mitigated in the area
of interest.
If unanticipated ordnance is encountered, stop all work, move to
a safe distance, and notify the local authorities.
Access and egress Requirements for ladder access / egress.
Excavated materials must be stored a minimum of 1.5 meters
from the top of excavation to ensure clear access / egress.
This distance requirement may increase on a case-by-case
basis depending on the ground conditions, the depth of the
hole, the details of installed shoring, etc.
Slide 47
40-T008-000E Rev A 21.10.2017
RISK CONTROL MEASURES
RISK / HAZARD CONTROL
Confined space Depending on the size of a trench, this may be considered a
confined space. Confined space entry procedures apply.
Open excavations Barricading and signage required for any excavations which may
be left open, including those left open through the night.
Working within the vicinity of open excavations greater than 1.8m
deep is considered working at height. Personnel working at the
top of the excavation are required to follow the appropriate
requirements.
Slope instabilities A daily inspection, from surface, shall be performed of the faces
of the excavation, to assess any movements or potential slope
instabilities, prior to entering. This inspection shall be logged and
recorded, with the records remaining on file until completion of
the work.
For depths greater than 1.2m, shoring shall be provided,
designed to sufficient strength to withstand the lateral pressures
of the soils and any surcharge loading.
Slide 48
40-T008-000E Rev A 21.10.2017
RESPONSIBILITIES
Supervisors:
• To ensure that Excavation Permit is in place prior to start of any
work in Excavation;
• To ensure that all potential hazards and risks communicated to the
work force daily in accordance with Conduct STARRT briefing;
• Make sure Pre-entry and Cat Scan; Gas Test shall be done before
starting of any excavation;
• To ensure that all persons under their control receive all required
HSE training to perform their duties;
• To ensure that all persons under their control are trained in
Emergency Response procedures;
• To ensure that any changes to construction processes are
communicated to HSE to enable the re-evaluation of relevant Risk
Assessments.
Slide 49
40-T008-000E Rev A 21.10.2017
RESPONSIBILITIES
Supervisors: (Cont.)
• Ensure entry / exit is secured;
• Verifying all emergency plans and specific entry conditions before
allowing any one into Excavation;
• Make sure access ways free of obstructions;
• Ensure that, workers are using the correct and proper PPE.
Slide 50
40-T008-000E Rev A 21.10.2017
EMERGENCY PROCEDURES
Fire:
• Raise Alarm (Verbal and Air Horn if required) and Evacuate;
• ONLY If trained - attempt to extinguish small Fires;
• DO NOT PUT YOURSELF OR OTHERS AT RISK;
• Call HSE 24 Hour Duty Phone;
• Watchmen prohibits any further entry other than Emergency team.
Gas Alarm:
• Raise alarm (Verbal and Air Horn);
• Call HSE 24 Hour Duty Phone;
• Watchman prohibits any further entry other than Emergency team.
Serious Injury:
• Raise alarm and surface team call for First Aider / Nurse to attend scene;
• Call HSE 24 Hour Duty Phone;
• Evacuate casualty via rescue stretcher as required following evaluation by Nurse /
external services.
Slide 51
40-T008-000E Rev A 21.10.2017
EXCAVATION
AWARENESS
PROOF OF LEARNING
ASSESSMENT
PASS MARK = 8 / 10
Slide 52
40-T008-000E Rev A 21.10.2017
1 What is Excavation?
A. A cut in the earth’s surface formed by earth removal.
B. A trench in the earth’s surface formed by earth removal.
C. A digging in ground formed by earth removal.
D. All of the above.
Slide 53
40-T008-000E Rev A 21.10.2017
4 Which type of these are the excavation protection method?
A. Moving vehicles near edge.
B. Spoil near edges.
C. Sloping, Shoring, Shielding.
D. None.
Slide 54
40-T008-000E Rev A 21.10.2017
7 How we can protect the falling of people / vehicle into the excavation?
A. By Soft / Hard Barricading.
B. By Keeping open.
C. By Blocking the Access / Egress.
D. By a Signage.
Slide 55
40-T008-000E Rev A 21.10.2017
10 Plant or Equipment working near the excavation requires?
A. Check for ground condition, edges of excavation.
B. Authorized and competent driver / operator.
C. Can drive as they wants to.
D. A and B.
Slide 56
40-T008-000E Rev A 21.10.2017
1 What is Excavation?
A. A cut in the earth’s surface formed by earth removal.
B. A trench in the earth’s surface formed by earth removal.
C. A digging in ground formed by earth removal.
D. All of the above.
Slide 57
40-T008-000E Rev A 21.10.2017
4 Which type of these are the excavation protection method?
A. Moving vehicles near edge.
B. Spoil near edges.
C. Sloping, Shoring, Shielding.
D. None.
Slide 58
40-T008-000E Rev A 21.10.2017
7 How we can protect the falling of people / vehicle into the excavation?
A. By Soft / Hard Barricading.
B. By Keeping open.
C. By Blocking the Access / Egress.
D. By a Signage.
8 Any trench / digging in earth’s surface, requires an Excavation
Permit?
A. True.
B. False.
9 Excavation – Supervisor is responsible:
A. Ensure required Permit is in place prior to start the job.
B. Make sure the Access way free from obstacle.
C. Verifying all emergency plans and specific entry conditions
before allowing any one into Excavation.
D. All of the above.
Slide 59
40-T008-000E Rev A 21.10.2017
10 Plant or Equipment working near the excavation requires?
A. Check for ground condition, edges of excavation.
B. Authorized and competent driver / operator.
C. Can drive as they want to.
D. A and B.
Slide 60
40-T008-000E Rev A 21.10.2017
OUR SAFETY PHILOSOPHY
Slide 61
40-T008-000E Rev A 21.10.2017
Discussion…
Slide 62
40-T008-000E Rev A 21.10.2017