Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

CONTRACTS

DAMAGES FOR BUILDING INTRODUCTION The proceedings were


CONTRACT BREACHES In Janet Campbell v CJ Cordony commenced in the Consumer
& Sons Pty Limited [2009] NSWSC Tenancy and Trader Tribunal
David Jury, Senior Associate 63, the Supreme Court of New and for procedural reasons were
Laura Iskander, Solicitor South Wales confirmed that the transferred to the District Court
damages for breach of a building and finally to the Supreme Court
DLA Phillips Fox, Sydney contract are the costs of bringing of New South Wales.
the defective work up to the The proceedings were ultimately
contract standard. set down for hearing before
THE FA CTS Justice Hammerschlag.
Mr and Mrs Campbell HEARING
(Campbells) decided to renovate
their house in Beecroft, New Legal principles
South Wales. They entered into a Justice Hammerschlag confirmed
contract for $534,059 (plus GST) that when claiming for breach of a
(contract) with CJ Cordony & building contract:
Sons Pty Limited (builder). The • The cost of reasonable and
builder was represented by Mr necessary work to make it
Cordony. The contract stated that conform to the contract plus
the builder had home warranty consequential losses because
insurance. However, the builder of the breach (in excess of any
never obtained this insurance. amount of the contract price
Practical completion occurred unpaid) is recoverable (Bellgrove
82 days after the contracted v Eldridge (1954) CLR 613).
completion date. The Campbells • The rectification of the work
engaged property inspectors who must be a reasonable course to
found a number of incomplete adopt.
and defective items of work.
• Consequential loss is claimable
Negotiations between the if the loss arose naturally from
Campbells and the builder over the breach of contract, and if the
the rectification of the defective loss may reasonably have been
items of work and completion in the contemplation of both
of the incomplete works failed. parties at the time they made
The Campbells then lodged a the contract (the rule in Hadley v
complaint with the Department of Baxendale (1854) 9 Exch 341).
Fair Trading.
• The plaintiff bears the onus of
Subsequently, the Campbells proving its loss.
sued the builder and Mr Cordony:
• The plaintiff must mitigate its
• To retrieve amounts paid for damages arising from a breach
work the builder had not done. of contract. However, the onus is
• For defects in the builder’s on the defendant to show that the
work. plaintiff has not done so.
• For breach of section 52 of the Contractual claim
Trade Practices Act 1974 (Cth) Justice Hammerschlag reviewed
(TPA) by representing that it had the evidence on the defective and
home warranty insurance, when incomplete works and held that
it did not. the Campbells were entitled to
• To recover their consequential damages for breach of contract
loss for rental and removal costs. for various claims of defective
building work. The builder argued
The builder cross–claimed for the that by the Campbells painting
outstanding amount of $57,022.90 over the builder’s defective work
for work it had done. they had waived the right to

52 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #127 JULY/AUGUST 2009


claim for the builder’s breach. • Whether the other builders had in the northern Sydney suburbs
This argument was rejected as the ability to obtain insurance at did not establish the actual
painting over the work made no the time. rentals being paid in the area.
practical difference to the builder At best it established the asking
• The capability of any of the
or to the work that would be price of real estate agents but
alternative builders to have
required to fix its defective nature. did not even reach the level of
performed the work.
establishing an offer.
TPA claim Therefore, it was held that the
Justice Hammerschlag found Campbells were not entitled to IMPLICATIONS
that: damages for misleading and For builders and their insurers
deceptive conduct because this case confirms that if a
• The contract recorded that the
they failed to establish that they building contract is breached the
builder had insurance from Royal
suffered loss or damage in the damages available to the innocent
& Sun Alliance.
manner contended. party can include:
• Mr Cordony assured the
Further, Justice Hammerschlag • The cost of labour and material
Campbells before the contract
relying on Anema E Core Pty to remedy a breach of contract.
was signed that he had insurance
from Royal & Sun Alliance. Ltd v Aromas Pty Ltd [1999] FCA • Consequential loss such as loss
904 stated that even if they had of profit.
• Following this conversation, Mr suffered loss or damage, the
Cordony gave the Campbells a • The cost of removal and rental
damage suffered was not caused
certificate of currency from Royal expenses.
by the builder’s conduct. In
& Sun Alliance. Anema, it was held that it was not For those seeking to claim for
• A letter from the builder’s enough to show that the contract breach of a building contract,
solicitor admitted that the resulted from the inducement. this case confirms that the claim
builder had failed to obtain the What had to be shown was that must be reasonable, arising
insurance and intended to obtain the loss flowed directly from as a direct consequence of the
retrospective cover. the inducement. Therefore, the breach of contract and within the
Campbells’ damage was actually contemplation of both parties
Justice Hammerschlag held
suffered by defective work being to the contract. In addition, it
that the builder engaged in
done, not by the inducement to is imperative to keep adequate
misleading and deceptive conduct
enter into the contract. documentation throughout
by representing that it held home
the project to ensure there is
warranty insurance when it did Rental claim sufficient evidence to support any
not. In addition, Mr Cordony knew Justice Hammerschlag found future claim.
the builder had no such insurance that damages for removal and
and was therefore knowingly rental expenses satisfied the David Jury and Laura Iskander’s
involved in the misleading and rule for claiming consequential article was previously
deceptive conduct within the loss. Despite the fact that the published in DLA Phillips Fox’s
provisions of section 75B of the Campbells submitted that they Construction Bulletin—July
TPA. were required to move out due to 2009. Reprinted with permission.
Justice Hammerschlag stated health reasons and the fact that
that even if he was to infer that the husband ran his business
the Campbells would have from home, the Court found
proceeded with another builder that the Campbells had failed to
at ‘a comparable price’, the establish that it was necessary for
Campbells failed to lead evidence them to move out, although it may
about: be highly inconvenient for them
to stay.
• The price at which they would
have proceeded. Additionally, the claim failed as
the Campbells failed to prove
• The terms on which the work any damage suffered by them as
might have been done by any they did not lead proper evidence
other builder. as to rental value. Justice
• Whether the quotes conformed Hammerschlag stated that a
with the sets of documents issued mere print out from an internet
to other builders. website ‘Domain’ of rental prices

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #127 JULY/AUGUST 2009 53

You might also like