CONSTRUCTION METHODS AND PROJECT MANAGEMENT

(C.E. 511)
QUIZ NO.1 AND PRELIM EXAM
Date: September 30,2021

Instructions:

Part1: Identification (Number 1 – 10, 1point per correct answer)

PART 1: QUIZ NO.1

1.) ______________ refers to a list of the specific pay items of the Works under this Contract, particularly their
identification numbers, descriptions, units of measurement, and qualities, together with their corresponding
unit and total bid prices.

2.) _______________is a legal agreement between the Procuring Entity and the Contractor to Execute, Complete,
and Maintain the Works.

3.) _______________is any part of the Works not constructed in accordance with this Contract.

4.) _______________ is the allowed percentage of the contract amount to be paid in advance to the contractor
prior to his accomplishment by the Procuring Entity (DPWH).

5.) _______________ is a delay in work execution occurring when an actual accomplishment falls below target as
measured by the difference between the Scheduled and Actual Accomplishment of the Works by the Contractor
as Established from the Work Schedule. This is actually described as a percentage of the Whole Works.

6.) _______________ is plan originally made by the Implementing Entity for the program proposal and
implementation.

7.) _______________ is a plan that should be provided by the Contractor depicting the actual field condition and
requirements derived from the As- Staked Survey but must be reviewed and evaluated by the Implementing
Agency/Entity.

8.) _______________ is a plan that must be provided by the contractor after the completion of the project as a
reflection of the final output of the project and must be reviewed /verify by the implementing agency/entity.

9.) _______________also known as the path where there is Zero slack tie nr floated time.

10.)________________type of heavy equipment usually used for subgrade preparation for road construction
(Spreading of materials, road grade elevations).
CONSTRUCTION METHODS AND PROJECT MANAGEMENT
(C.E. 511)
QUIZ NO.1 AND PRELIM EXAM
Date: September 30,2021
PART II: PRELIM EXAM
Project: CONSTRUCTION OF PUBLIC COMFORT ROOM (4 Water Closet, 1 Handwashing)
Instructions: Fill the blanks on the Table below(30pts.), Draw the network diagram (10pts), Answer Correctly the
2 Questions (5pts/each).

ACTIVITIES Starting Completion DESCRIPTION DURATION( PREDECESSOR


Event Event C.D) ACTIVITY

A 1 2 Permits and Licensing 14 ------


B Materials and Deliveries 14 -------
C Layout and Excavation 2 B
D Cutting, Rebars and Installation of RSB 4 A
E Formworks and Sacaffoldings 40 B
F Concrete Works 21 D
G Embankment 1 I
H Masonry Works 8 B
I Plumbing and Sanitary 2 H
J Fixtures 1 O
SteelWorks(trusses & Purlins)W/
K Installation 10 F,G,E
L Roofing 2 K
M Electrical works 2 L
O Ceiling works 2 M
P Plastering 6 J
Q Paintings /Architecturtal Works 6 P
R 1 14 Construction Safety and Health 83 ------

What is the Critical Path?

What is the Shortest Project Completion period?

GOODLUCK AND GODBLESS!!!!! 😊

PREPARED BY: KEVIN DEXTER M. PENEYRA C.E.