Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

CONTRACTS

LETTERS OF INTENT • Ensure that all essential terms to start work, then the contractor
of the agreement are described may have good reason to believe
Andrew Kelly, Partner with certainty (including the scope it has been successful in winning
DLA Phillips Fox, Brisbane of works, payment, completion the contract. A principal who then
date, insurance and termination). resiles from this position may
experience delays to the project
• Provide something of value
as well as other disruptions. It
to pass from one party to the
will also diminish leverage in
other, such as a monetary sum in
negotiating a final price.
exchange for work done.
The old adage ‘look before you Whether a letter of intent will give Ensure that you retain
leap’ has particular significance rise to a binding contract depends control of what is occurring
in relation to contracting and on the circumstances of each We recommend including a
especially in relation to letters of case. clause in the letter of intent to
intent. ensure the contractor must cease
PRACTICAL TIPS FOR work on the principal’s written
The use of letters of intent in PRINCIPALS instruction. The inclusion of this
contracting is ingrained within Principals are generally in a clause requires the contractor to
the construction industry stronger position when a binding vacate the site on request, and
and can often provide a fast contract exists. A contractual makes it clear that the contractor
solution to finalising contractual letter of intent may carry with it may not claim for overheads
arrangements and ensuring the following advantages for a or loss of profit regarding
the timely commencement of a principal over a non–binding letter outstanding work if the principal
project. of intent: issues a notice to cease work.
However, beware the fast • An agreement clearly spells out
solution and the quick fix. There Make your intentions clear
essential terms. Include a statement in the letter
are a number of important
considerations that must be taken • When a contract is formed a of intent that there is no intention
into account before issuing or number of implied terms arise to enter into a binding contractual
responding to a letter of intent. as a matter of law, such as under relationship with the contractor,
a supply agreement, where other than on the terms set
WHAT ARE LETTERS OF the goods are to be fit for the out in the letter of intent. This
INTENT AND WHAT ARE intended purpose. precaution will help you to avoid
THEY USED FOR? any claim by the contractor for
• It may be easier to claim
A letter of intent is a statement of loss of profit based on the value of
against a contractor for defective
intention that outlines an intended the whole works if the works are
or substandard work.
agreement between two or more abandoned.
parties. Letters of intent can be • As an incentive to ensure
contractors finish the job. Be precise
used for a number of purposes, The basis, method and frequency
including: Principals therefore need to act of payment for the work being
• As a comfort letter, that without with caution in issuing letters executed under the letter of intent
more will not form any type of of intent, and should consider should be clearly determined to
contract. whether they wish a letter of avoid problems associated with
intent to form a contractually having to later value the work.
• As a preliminary contract binding arrangement. There are a
between the parties. number of steps that a principal Limit your liability to make
• To direct a contractor to start may take to help manage and payments
works. minimise risk when dealing with A principal should consider
letters of intent: imposing a financial ceiling on its
WHEN ARE LETTERS OF liability for payment. A monetary
INTENT BINDING? Timing is essential cap may be included on the
To ensure that a letter of intent is Sending a letter of intent to a amount of work or commitments
contractually binding, it should: contractor too early during the which the contractor is allowed to
course of contractual negotiations
• Clearly state that it is a take, or, alternatively a provision
can undermine a principal’s
contractually binding document. that all work or commitments
bargaining position. If a contractor must be approved by the
is granted access and permitted superintendent in advance.

28 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #112 JANUARY/FEBRUARY 2007


Make provision for reasonable value of the work Determine whether the
subcontractors done. letter of intent is binding
A clause should be included • Limited liability in respect of If the letter of intent does not
providing that any subcontract defects, as these will only factor create contractual obligations, a
entered into by the contractor in a calculation of the reasonable contractor is under no obligation
should be assignable to the work done. to either continue with or to
principal. complete the work. This may be
However, in large commercial
beneficial to a contractor if there
A formal agreement is dealings certainty and risk
is a delay in the execution of the
important allocation is important to
formal contract.
To entice a contractor to enter principals and contractors alike
a formal contract as soon and we therefore recommend FORMALISE YOUR
as possible, a clause should formal contracts to manage AGREEMENTS
be included stating that the and allocate this risk. There are Although letters of intent are
contractor is not entitled to any a number of precautions that useful as they enable work
payment for profit or overheads a contractor may take to help to commence on site prior
under the letter of intent. Further, manage and minimise risk when to a formal contract being
a term providing that the formal dealing with letters of intent: entered into, they should never
contract is to have retrospective Get it in writing be regarded as a permanent
effect and that any payments Ideally a signed contract substitute for a formal contract.
made under the letter of intent should be executed prior to This is because a formal contract
are deemed to have been made commencement of work on site. allows the parties to set out with
under the formal contract. If this is not possible, a contractor particularity exactly what they
should not commence works are agreeing to do and what
Use insurance to manage obligations they are agreeing
your risk until a clear written agreement is
obtained. to adopt. This is particularly
Insurance of the works should be important in substantial contracts
addressed. Although there is no Make your intentions clear where significant risk allocation is
formal contract in place, this does A contractor should be extremely necessary.
not reduce the risk associated cautious in its preliminary
with carrying out construction dealings with a principal to
works. The provision of insurance avoid entering into unintentional
is necessary to manage this risk. obligations. Care should be
PRACTICAL TIPS FOR taken to ensure terms of any
agreement are clear to avoid
CONTRACTORS future confusion.
It is often true that non–binding
letters of intent benefit Getting advice up front will
contractors. This is because in save you money
the absence of a contractual Letters of intent should only be
arrangement there are very used after obtaining legal advice,
few obligations imposed upon as they have the capacity to form
a contractor. The advantages of legally binding contracts at law.
non–binding letters of intent to
contractors include the following: Deal with payment now
Although a contractor may be
• A contractor may have no able to claim on a quantum
obligation to complete the work. meruit basis, it is preferable
• A contractor may start and stop that the issue of payment is
work as it pleases. addressed in the letter of intent.
This should take the form of an
• A contractor may change its
express undertaking given by the
mind as to the terms of the
principal that all costs, together
agreement, leaving the principal
with a reasonable allowance for
with the only real option of
overheads and profits will be
directing the contractor to leave
reimbursed should the contract
the site. Where this occurs, a
not proceed.
contractor will be entitled to the
AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #112 JANUARY/FEBRUARY 2007 29

You might also like